Under section 38 of the Commons Act 2006, you need our consent to carry out any restricted works on land registered as common land.
Applies to England and Wales
Documents
Details
This guidance sheet contains information on:
do I need consent
how do I know that making a section 38 application is the best way forward
what steps should I take before applying
if I apply under section 38, is my application likely to succeed
how do I make an application, and what will happen to it
how long will all this take
what happens if I make a mistake with my application
what should I do if I need to carry out emergency work on a common
Published 1 January 2015
Last updated
1726 FebruaryMarch 20222024
+ show all updates
26 March 2024
Information update on 'What steps should I take before applying' and new section 'post decision'
17 February 2022
Updated text under: What steps should I take before applying?
16 March 2021
Document updated in line with new accessibility regulations
29 April 2020
Guidance sheet updated.
22 January 2020
Guidance sheet updated to reflect how long our cases are taking.
14 September 2018
guidance sheet updated with links to other guidance and legislation.
21 May 2018
Guidance document updated
1 January 2015
First published.