Manage a building control application for a higher-risk building
Use this service to apply for and manage building control applications for higher-risk buildings in England.
Applies to England
If you’re proposing higher-risk building work, or work to an existing higher-risk building, you can use this service to:
- apply for building control approval (including where your building work is being transferred from another building control body)
- apply for change control
- apply for a full or partial completion certificate
- submit a notice of intention to start work or
commencementcommencement - tell us that you have reached a certain point in your inspection schedule
During the design and construction phases, a higher-risk building has at least 7 storeys or is at least 18 metres in height and either:
- is a hospital or care home
- has at least 2 residential units
Before you start
You’ll be asked for your contact details. We’ll use these if we need to check anything you have told us in this application.
You’ll also be asked for details of the client, principal designer and principal contractor for the higher-risk building. We’ll use these details if we have questions about the building work.
CostBuildings in progress
ItThe costsfollowing guides will help you understand the building control process for buildings in progress:
-
transitional building control approval for work on existing higher-risk buildings
-
transitional building control approval for new higher-risk buildings
Cost
It costs:
- £180 to apply for building control
approval.approval - £180 to apply for change control
- £216 to apply for a full or partial completion certificate
You can pay this charge by debit card, credit card, or invoice.
You’ll also be charged:
- £144 per hour for Building Safety Regulator
(BSR)(BSR) staff to work on your case - for any costs BSR incur from relevant authorities or third parties
There is no charge to:
- submit a notice of intent to start work or commencement
- tell us you have reached a certain inspection point
- apply for building control approval, if your building work is being transferred from another building control body and that work has not sufficiently progressed with full plans
Personal information
You must only provide the personal data we ask for. Make sure you redact any other personal data before you submit it to us. Find out more in our privacy notice.
If you need help using this service
Contact usBSR if you need help using this service.
Last updated 5 April 2024 + show all updates
-
Service updated to allow applications for: building control approval when building work is transferred from another building control body, change control, a full or partial completion certificate. Information about charges added to include £180 for change control applications, and £216 for full or partial completion certificate applications.
-
First published.
Update history
2025-03-27 09:53
Information added about what you can use this service for and links added to relevant guidance.
2025-03-25 07:55
Charges updated.
2024-04-05 09:00
Service updated to allow applications for: building control approval when building work is transferred from another building control body, change control, a full or partial completion certificate.Information about charges added to include £180 for change control applications, and £216 for full or partial completion certificate applications.
2023-10-02 09:00
First published.