Guidance

Applying to register a high-rise residential building

How principal accountable persons, or someone authorised to act for them, can register a high-rise residential building in England.

Applies to England

Check if you need to register a building

A high-rise residential building contains one or more high-rise residential structures. A high-rise residential structure has:

  • at least 7 floors or is at least 18 metres in height
  • at least 2 residential units

A high-rise residential building can contain one or more high-rise residential structures. You may need to apply to register 2 or more structures as one building if they’re connected in certain ways.

Use the independent section criteria on each structure to help you decide if the structures are connected in one of those ways.

The building must be registered with the Building Safety Regulator (BSR) before people live there. These buildings are known as higher-risk buildings under the Building Safety Act 2022.

Types of buildings you do not need to register

Do not register buildings that are entirely used as a:

  • hospital
  • care home
  • secure residential institution
  • hotel
  • military premises
  • prison

Read the full guidance on buildings that need to be registered.

Check who can register the building

The principal accountable person (PAP) must make sure the building is registered.

A principalPAP accountable person is usually an organisation like a:

  • housing association
  • local authority
  • company

Someone from the organisation must be the single point of contact (SPOC) for theBSR. Building Safety Regulator. The SPOC will:

  • discuss building safety issues with the regulator
  • have authority relating to the safety of the building

SPOCs cannot be the principalPAP accountable person or an accountable person.person (AP). The organisation is the principal accountable person.PAP.

In limited circumstances, an individual can be the principalPAP. accountable person. For example, if they are:

  • the owner of the building
  • named on the leasehold as responsible for maintenance of common parts

Read the guidance on accountable persons and the principal accountable person to understand their roles and legal duties.

Authorising someone else to register

The principalPAP accountable person can authorise someone else to register the building for them. For example, they can authorise a managing agent or legal representative.

The authorisation must be in writing like an email, letter or written contract. Authorising someone to act for you does not make them the principal accountable person.PAP.

A principalPAP accountable person is usually an organisation. You do not have to authorise individual employees of that organisation.

Register the building

It is an offence to allow residents to occupy an unregistered high-rise residential building.

New buildings must have a relevant completion certificate or final certificate. They must be registered before residents can occupy them.

You can apply to register a high-rise residential building online.

You will need:

You’ll also need a credit or debit card to pay the £251 application fee for each building.

If you cannot pay by card, you may be able to pay by invoice. You must pay the invoice before weBSR can assess your application. If you do not pay within 30 days of the invoice, weBSR may reject your application.

Building summary

As part of the application to register a high-rise residential building you need to give usBSR a summary of the building.

Number of floors at or above ground level

Count all floors from ground level to the top floor, whether they have residential units or not.

If all of a ceiling is at or above ground level, count the floor as above ground level.

Count mezzanine floors that are 50% or more of the area of other floors as separate floors. If a mezzanine floor is less than 50% of the area of any of the other floors, do not count it as a floor.

Do not count:

  • floors below ground level unless all the ceiling is above ground level
  • the roof

Ground level

Ground level is the level of the land immediately next to the building. If that land is uneven, it is the lowest part of the land immediately next to the building. All or part of a ceiling below that level is below ground level.

Top floor

The top floor is the top of the floor surface of the top storey of the building. Ignore the roof.

Height of the building

Measure the height in metres (up to 2 decimal places) from ground level to the top floor. Do not measure the roof.

You can estimate the height if the building:

  • has at least 7 floors
  • is clearly over 18 metres

Keep a record of how you estimated the height.

Number of residential units

Count all residential units, whether someone is living in them or not. A residential unit is a place where someone can live, like a flat, apartment, maisonette or a room in student accommodation.

When the building was completed

Tell usBSR the year the building was originally built. If you do not know the exact year, you can select from a range.

For buildings completed in 2023 or later, you must tell usBSR the:

  • name of the building control body that issued the completion certificate or final certificate
  • certificate number
  • certificate date

For buildings completed between 1985 and 30 September 2023, you should take reasonable steps to find this information.

For buildings completed before 1985, you do not need to give this information.

For buildings completed on or after 1 October 2023, you must also upload a copy of the relevant completion or final certificate. You will not need to upload a copy of the certificate if it was issued by the Building Safety Regulator.

Structure and fire safety information

You need to give usBSR information about the building’s structure and fire safety, this is also known as key building information. We’llBSR will ask you about:

  • fire and smoke controls
  • energy supplies, storage and generation
  • type of structure, roof, staircases and external walls
  • the building’s use
  • building work since original build
  • connections between structures or to other buildings

You should be able to get the information weneeded need from the most recent fire risk assessment. If there’s an external wall system (EWS) appraisal, the information might also be there meaning you should not need to do a full separate survey.

You have 28 days after submitting your registration application to give BSR more detailed information about the structure and fire safety of the building. The information you give here will help you when you assess the building’s risks, as part of your safety case.

Read the Building Safety Regulator: giving us information about structure and safety (key building information) guide to help you understand:

  • what structure and safety information we’llBSR will ask for
  • how you might find it

Making changes to your application: before you submit it

You can make a change in your application at any stage before submitting it.

You can make these changes using the register a high-rise residential building service.

Withdraw an application

UseYou thecan register a high-rise residential building service to withdraw an application.

Contactapplication theto Buildingregister Safetya Regulatorbuilding. if you need help. You cannot withdraw an application after weBSR havehas made a decision about it.

Contact BSR if you need help.

Decisions

We’llBSR will assess your application and make a decision:

  • to register the high-rise residential building
  • reject your application – we’llBSR will set out the reasons why

The reasons weBSR might reject your application include:

  • you have not paid the fee
  • the building you’re applying to register is not a high-rise residential building
  • you have not given usBSR the information we needed

Reviews

If you disagree with the decision about your registration, you can ask theBSR Building Safety Regulator to look at the decision again.

You must ask for this review within 21 days of the decision (excluding public holidays).

A review costs £288. You must pay this before weBSR carry out the review.

If you cannot pay by credit or debit card, you may be able to pay by invoice. You must pay the invoice before weBSR carrycarries out the review.

When you ask for a review, you need to include the following information:

  • your name
  • an address in England and Wales that weBSR can serve notices to (including notices in proceedings)
  • your email address
  • your telephone number
  • if you’re authorising someone else to act for you, their name and address
  • the name, address and postcode of the building the decision is about
  • a way to identify the decision being reviewed, like the application reference
  • your reasons for asking for the review

You should also tell usBSR about any new information relevant to the original decision.

You must also confirm that you have told any other accountableAPs persons that you have asked for a review.

Contact the Building Safety RegulatorBSR if you want to ask for a review. You cannot ask for a review over the telephone.

Making changes: after a building is registered

Once your building is registered, you must tell usBSR within 14 days of becoming aware of any changes to the:

  • building summary
  • principal accountable personPAP
  • accountable personsAPs
  • parts of the building each accountableAP person or the principalPAP accountable person is accountable for

You must tell usBSR within 28 days of becoming aware of any changes to the building’s structure or fire safety information.

Use the register a high-rise residential building serviceinformation to tell the Building Safety Regulator make these changes..

Changing a user  

The person who completes the application is known as the primary user.

As the primary user you can:

  • access the register a high-rise building service to manage the building information

  • change the primary user

You will need your email address and application reference number to do this.

Adding a user

The primary user can add a second user to manage the building’s information.information.

You will need your email address and application reference number to do this.

The second user cannot add or change any users.

Taking a building off the register

AYou higher-riskcan buildingask canBSR beto removedtake froma building off the register if any of the following apply:

  • it now has less than 7 floors and are less than 18 metres in height
  • it now has less than 2 residential units
  • it was incorrectly registered
  • everyone has permanently moved out of the building, for example pending demolition

You do not need to tell usBSR if your building is student accommodation that is empty over a holiday period.

You can ask the Building Safety Regulator to take the building off the register. You do this through the register a high-rise residential building service.

If there are multiple accountableAPs persons for the building, theBSR Building Safety Regulator will send them a copy of its decision to remove the building.

Where an accountableAP person disagrees with this decision, they can ask the BuildingBSR Safety Regulator for a review.

Published 12 April 2023
Last updated 2016 DecemberApril 20232024 + show all updates
  1. Warning note added to structure and fire safety section telling users they have 28 days following submission to give further detailed information to BSR

  2. New section on taking a building off the higher-risk register.

  3. Updated information about: - making changes to your application - the cost of a review (£288) - managing your information - how to change and add a user for the service

  4. Update to the 'Building summary' section on where the ground level is.

  5. Deadline dates in the 'register a building section' removed. 'When the building was completed' section updated to explain which buildings require certain information to be submitted for registration. 'Reviews' section updated to explain how public holidays affect the review period. 'Number of floors at or above ground level' section updated to explain where you should count the number of floors from.

  6. Added information about the alternative payment option for those who cannot pay the application fee by credit or debit card.

  7. New guidance added to ‘check if you need to register a building’ section to help you decide if the building structures are connected. An example of when a principle accountable person is usually an organisation added to ‘check who can register the building’ section. New guidance added to ‘making changes’ section, which now asks you to tell the Building Safety Regulator of detailed changes. Contact the Building Safety Regulator if you need to 'withdraw an application' section. New heading added 'decisions' which includes reasons why the Building Safety Regulator might reject your application. New guidance added to ‘reviews’ section to tell you that you cannot ask for a review over the telephone.

  8. Added a link to the full guidance on buildings that need to be registered. Clarified that only high-rise residential buildings in England need to be registered.

  9. Added more guidance on building structure and safety information (key building information) and provided a link to a guidance publication

  10. First published.