Section 62A Planning Application: S62A/2024/0045 Land at Wickham Hall Estate, Bishops Stortford, Uttlesford, CM23 1JG
Overview of case details, documents, key dates and how to make a representation.
Applies to England
Type of application:
Full Planning Application
Applicant name
Endurance Energy and Wickham Hall Ltd
Site address:
Land at Wickham Hall Estate, Bishops Stortford, Uttlesford CM23 1JG
Description of proposed development
Erection of a Solar Photovoltaic Farm with supporting infrastructure and battery storage, inverters and transformers, fencing, landscaping works and connecting cable.
Case Officer
Section 62A Applications Team
Procedure
Hearing
Key dates
Date | |
---|---|
Date application valid | 20 June 2024 |
Date by when representations must be made | 29 July 2024 |
Hearing date and venue | |
Target decision | 19 September 2024 |
Decision date | TBC |
Hearing Documents
Decision
Make a representation
The application can be inspected under the application plans and documents heading below.
You will be able to comment on this application until 29 July 2024
Please base your comments on planning matters.
Please avoid the use of inflammatory, discriminatory or abusive comments
All representations made in connection with the development proposal will be made publicly available on the website shortly after the end of the representation period. The name of the individual author or organisation will be published however addresses, signatures and contact details will not be published. We advise you not to include any other personal information about yourself or others.
Our Customer Privacy Notice sets out how we handle personal data in accordance with the law.
Send your comments via email to section62a@planninginspectorate.gov.uk
or write to
Section 62A Applications Team,
The Planning Inspectorate,
3rd Floor, Temple Quay House,
2 The Square, Temple Quay,
Bristol,
BS1 6PN
Sending comments by email will enable us to deal with them more quickly and is preferred.
Please include the application reference number and site address.
This application will be determined by an Inspector appointed by the Secretary of State. Shortly after the close of the representation period the Planning Inspectorate will consider whether a hearing is necessary. In the event that a hearing is scheduled, and you would wish to speak at the hearing, you must make this request at the time you submit your written representations.
Where the application is to be considered at a hearing, notice of the date, time and venue for the hearing along with the name of the person holding the hearing, will be published on this website at least two weeks before the date of the hearing.
Application Plans and Documents
Applicant submission in relation to red line boundary - July 18 2024
Questionnaire and supporting documents
Comments
Consultees
Interested Parties
Planning Inspectorate Correspondence
Applicant Correspondence
Updates to this page
Last updated
-
Hearing date and venue added Issues report added
-
Procedure added
-
1 Interested party representation added
-
9 documents added under Consultees
-
interested party response added 25 July 2024.
-
East Herts District Council, Essex County Council Mineral Planning Authority and Thames Water
-
new heading: Applicant submission in relation to red line boundary - July 18 2024. National Highways document and Date by when representations must be made to 29 July 2024.
-
Essex County Council - Ecology, Essex County Council - Lead Local Flood Authority, Farnham Parish Council and Uttlesford District Council - Built Heritage and Conservation
-
Uttlesford District Council - Urban Design
-
Natural England
-
Affinity Water added
-
Environment Agency added under Consultees
-
4 consultee responses added
-
Added - Cadent Gas Ltd 1, Cadent Gas Ltd 2, Cadent Gas Ltd 3 - Solar Farm Guidance, ESP Utilities Group Ltd, Gigaclear Ltd No Plant Affected Letter National Grid Electricity, UK Power Networks 1, UK Power Networks 2, UK Power Networks 3, UK Power Networks 4, UK Power Networks 5, UK Power Networks 6, D Brett
-
4 consultees added - MAG Highways, NATS Safeguarding, Essex Police x 2 Consultation deadline updated to 26 July 2024
-
PS appendices 1.3 & 3 added under application plans and documents
-
First published.