This item is part of HigherTierCapital Grants 2025. You must read the Capital Grants 2025 guidance to understand the rules and how to apply.
How much you’ll be paid
50% of actual costs
How this item benefits the environment
It creates and maintains wetland features that treat field run off and other contaminated water generated from agricultural activities. This helps reduce the risk of sediment and other pollutants entering a nearby watercourse.
Where you can use this item
You can only use this item alongside a feasibility study or a Catchment Sensitive Farming water holding structure action plan developed with Natural England either:
in areas targeted to reduce water pollution from agriculture
to treat field and farmyard diffuse runoff
Catchment Sensitive Farming provides advice where there are water quality or flood risk issues linked to farming.
You must also contact your local planning authority to check if planning permission is needed.
You cannot use this item:
to treat slurry, silage liquor, heavily contaminated water or concentrated pesticide spills and washings as defined under the Nitrate Action Plan Regulations, Slurry, Silage and Agricultural Fuel Oil Regulations or by the Health and Safety Executive
provide 3 written quotations for completion of the work with your application, including associated costings according to the specification in your plan or study
agree the selected quotation with Natural England
create, install and complete the works according to the agreed specification and timescale
follow the advice on maintenance and management agreed with Natural England (after you have carried out the work)
Read the constructed farm wetlands guide produced by the Wildfowl and Wetland Trust for further help carrying out this item.
You must not place spoil on any historic or archaeological feature or wildlife area identified on your FER, HEFER or on MAGIC.
You should discuss and agree requirements that are specific to your site with your adviser.
Evidence you must keep
You must keep and provide with your claim:
receipted invoices or bank statements where a receipted invoice is not available
photographs of the site during the different stages of construction or contracts, invoices or other documents confirming the technical specification for the completed works
photographs of the completed work
any consents or permissions connected with the workwork, including from your local planning authority
If you do not need consent or permission from your local planning authority, you must provide evidence to show this. This can be a:
letter from the authority confirming you do not need permission
note of a telephone conversation with a local authority representative, with the name, date, and time of the call
link to online guidance or printout of guidance text which shows you do not need permission
You must also keep and provide on request:
photographs of the site before works start
a copy of the feasibility study or a Catchment Sensitive Farming water holding structure action plan developed with Natural England
The following advice may help you to use this item, but you do not have to follow it to get paid. It’s not part of this item’s requirements.
What the specification needs to include
Your plan or study will create a detailed specification that’s specific to your site. A likely design would be a treatment structure built in at least 3 stages.
Stage 1: create an open pond to act as a sediment trap without much wildlife value. The pond should be accessible to farm machinery for routine maintenance.
Stage 2: plant to encourage settlement and remove nutrients.
Stage 3: there’ll be a shallow wetland, heavily vegetated to reduce pollutants in the water such as:
nitrates or ammonia
biological oxygen demand (BOD)
faecal indicator organisms (FIOs)
Throughout each stage:
restrict livestock access to reduce the risk of eroding or degrading the treatment area
build on a non-permeable substrate (made up of 20% clay) or line the area so there’s a permanent pool of water for most of the year
avoid building on sandy, gravelly and excessively wet soil to prevent contact with groundwater before treatment
build gentle slopes with a gradient of no more than 1 in 4 – the edges should provide good wildlife habitat and act as a safety feature
make sure the pond edges are undulated with higher and lower points to provide more edge habitat
make sure outlet pipes are larger than inlet pipes to prevent water backing up along the system
obtain a waste exemption if excavated material needs removing – this information should be included in the agreed management plan
Managing the outfall
You’ll need to agree an acceptable water quality standard with the Environment Agency before directing any outfall into the local watercourse.
This item is now available for Higher Tier Capital Grants
9 November 2016
In 'Keeping records' section:
* change to records that agreement holders need to keep and supply with a claim
* change to handling of the 3 quotes for completion of the work
* addition of sending photographs of site before work takes place with application