Guidance

Compliance with BAT-AELs for indirect emissions to water at chemical waste treatment installations: RPS 371

Environment Agency regulatory position on when you cannot comply with best available techniques associated emission limits (BAT-AELs) for certain substances discharged to sewer at chemical waste treatment installations.

Applies to England

Documents

Details

This regulatory position statement (RPS) does not change your legal requirement to comply with the conditions of your environmental permit.

However, the Environment Agency will not normally take enforcement action if you do not comply with this legal requirement if you meet the requirements in this RPS.

This regulatory position does not apply to any other legal requirements.

Updates to this page

Published 15 June 2026
Last updated 18 June 2026 Show all updates
  1. Updated the RPS to clarify that if you intend to use this RPS, you must notify the Environment Agency by email within 4 weeks of your varied permit being issued, or within 4 weeks of the date of this RPS.

  2. First published.