Decommissioning Programme |
Operator at approval |
Operator following licence / company change |
Approved Decommissioning solution |
Year of Approval |
Close out report |
Year close out report accepted |
Saltire A Topsides and Saltire Area Subsea Infrastructure DPs (PDF, 7.37 MB, 69 pages) Saltire EA (PDF, 7.09 MB, 109 pages) Saltire CA (PDF, 4.61 MB, 111 pages)
|
Repsol Sinopec Resources UK Limited |
- |
The topsides will be recovered for reuse, recycling or disposal. Subsea installations will be returned to shore for reuse, recycling or disposal. Bundles will be left in situ. Trenched and buried power cables and umbilicals will be left in situ with exposed sections being trenched and buried. Spools and transition sections shall be recovered to shore for reuse, recycling and disposal. |
December 2022 |
|
|
Causeway & Fionn DP (PDF, 4.56 MB, 64 pages) Causeway & Fionn EA (PDF, 6.78 MB, 94 pages) Causeway & Fionn CA (PDF, 2.03 MB, 41 pages)
|
Ithaca Energy (UK) Limited |
- |
All Causeway and Fionn Subsea Installations and exposed tie-in spools will be removed and transported to shore for re-use or recycling. Pipelines and umbilicals will remain in situ with cut ends being buried. All wells will be plugged and abandoned. |
December 2022 |
|
|
Johnston DP (PDF, 2.18 MB, 43 pages) Johnston EA (PDF, 5.25 MB, 121 pages) Johnston CA (PDF, 1.64 MB, 62 pages)
|
Premier Oil E&P UK EU Limited |
- |
Subsea installations will be recovered to shore for recycling and disposal. Trenched and buried rigid flowlines will be left in situ with exposed ends remediated with rock. Trenched and buried flexible flowlines, umbilicals, spool pieces and jumpers will be removed. |
December 2022 |
|
|
Duart DP (PDF, 11.2 MB, 55 pages) Tartan Subsea EA (PDF, 36.4 MB, 137 pages) Tartan Subsea CA (PDF, 5.5 MB, 135 pages)
|
Repsol Sinopec Resources UK Limited |
- |
Subsea installations will recovered to shore. Trenched and buried pipelines and umbilicals will be left in situ, with remediation of any exposed sections |
November 2022 |
|
|
Tartan N Terrace (TNT) & Tartan Satellite (TS) Subsea DPs (PDF, 4.07 MB, 72 pages) Tartan Subsea EA (PDF, 36.4 MB, 137 pages) Tartan Subsea CA (PDF, 5.5 MB, 135 pages)
|
Repsol Sinopec Resources UK Limited |
- |
Subsea installations and exposed surface laid lines will be recovered to shore. Piles will be cut to -3m below the seabed. Trenched and buried lines, and lines in open trenches but not adequately buried will be left in situ, with remediation of any exposed sections. |
November 2022 |
|
|
Tartan Topsides DP (PDF, 8.28 MB, 46 pages) Tartan Subsea EA (PDF, 36.4 MB, 137 pages)
|
Repsol Sinopec Resources UK Limited |
- |
Topsides will be recovered to shore |
November 2022 |
|
|
Lancaster Field Floating Production Storage and Offloading Vessel (FPSO) Decommissioning Programme (PDF, 2.51 MB, 37 pages) |
Hurricane Energy PLC |
- |
The Floating Production Storage and Offloading Vessel (FPSO) will be removed to shore for either re-use or recycling. |
November 2022 |
|
|
Hewett Area Subsea Installations DP (PDF, 4.45 MB, 54 pages)Hewett Area Subsea Installations EA (PDF, 14.8 MB, 150 pages)
|
Eni UK Limited |
- |
Subsea installations will be fully removed and recovered to shore for reuse, recycling or disposal. |
November 2022 |
|
|
Scoter and Merganser DP (PDF, 4.63 MB, 92 pages)Scoter and Merganser CA (PDF, 1.94 MB, 47 pages)Scoter and Merganser EA (PDF, 6.4 MB, 130 pages)
|
Shell UK Limited |
- |
Subsea installations will be recovered to shore along with surface laid spools and jumpers. Buried pipelines will be left in situ. |
September 2022 |
|
|
Sean DP (PDF, 5.05 MB, 64 pages)Sean CA (PDF, 2.8 MB, 110 pages)Sean EA (PDF, 9.44 MB, 171 pages)
|
ONE-Dyas UK Limited |
- |
Removal of 3 small platforms. Removal of pipeline SSIV and mooring buoys. Export pipelines to remain in situ. Cables and umbilicals returned to shore. |
August 2022 |
|
|
Caister CDP1b (PDF, 5.96 MB, 56 pages)CMS Area EA (PDF, 10.4 MB, 171 pages)CMS Area CA (PDF, 13.5 MB, 145 pages)
|
Chrysaor Production (U.K.) Limited |
- |
Buried pipelines will be left in situ and surface laid pipelines will be removed to shore. |
July 2022 |
|
|
Caster-MurdochCaister-Murdoch System CDP2 (PDF, 15.7 MB, 131 pages)CMS Area EA (PDF, 10.4 MB, 171 pages)CMS Area CA (PDF, 13.5 MB, 145 pages)
|
Chrysaor Production (U.K.) Limited |
- |
Topsides and jackets will be recovered to shore. Buried pipelines will be left in situ and surface laid pipelines will be recovered. |
July 2022 |
|
|
Murdoch CDP3 (PDF, 8.53 MB, 83 pages)CMS Area EA (PDF, 10.4 MB, 171 pages)CMS Area CA (PDF, 13.5 MB, 145 pages)
|
Chrysaor Production (U.K.) Limited |
- |
Topsides and jackets will be recovered to shore. Buried pipelines will be left in situ and surface laid pipelines will be recovered. |
July 2022 |
|
|
Brae Bravo Upper Jacket Decommissioning Programme (PDF, 1.76 MB, 41 pages) |
TAQA Bratani Limited |
- |
The upper jacket and pipeline risers will be removed to 61m below LAT and recovered to shore for recycling or disposal. |
June 2022 |
|
|
LOGGS Saturn Satellites LDP2 (PDF, 20 MB, 90 pages)LOGGS LDP2 - LDP5 Comparative Assessment (PDF, 3.21 MB, 203 pages)LOGGS LDP2 - LDP5 EA (PDF, 7.5 MB, 181 pages)
|
Chrysaor Production (U.K.) Limited |
- |
Topsides and jackets will be recovered to shore. Buried pipelines will be left in situ and the riser sections of pipelines will be removed to shore. |
May 2022 |
|
|
Foinaven FPSO Offstation DP (PDF, 3.76 MB, 60 pages) |
Britoil Limited |
- |
FPSO and mooring lines removed to shore for re-use or recycling. associated risers and umbilicals removed to shore for recycling. |
May 2022 |
|
|
LOGGS V-Fields LDP4 (PDF, 20.8 MB, 83 pages)LOGGS LDP2 - LDP5 Comparative Assessment (PDF, 3.21 MB, 203 pages)LOGGS LDP2 - LDP5 EA (PDF, 7.5 MB, 181 pages)
|
Chrysaor Production (U.K.) Limited |
- |
Topsides and jackets will be recovered to shore. Buried pipelines will be left in situ. |
April 2022 |
|
|
Hummingbird Spirit FPSO Sail away and Chestnut Riser Disconnection (PDF, 2.96 MB, 47 pages) |
Spirit Energy North Sea Oil Limited |
- |
FPSO, mooring suction anchors and risers Removal to shore for either re-use or recycling |
March 2022 |
|
|
Victoria DP (PDF, 2.54 MB, 42 pages)Victoria CA (PDF, 1.81 MB, 48 pages)Victoria EA (PDF, 18.4 MB, 158 pages)
|
NEO Energy (SNS) Limited |
- |
WHPS will be recovered to shore for reuse, recycling or disposal. Trenched and buried sections of pipelines will be left in situ, removing the pipeline ends. Exposed concrete mattresses and grout bags will be recovered to shore. |
April 2022 |
|
|
Wenlock DP (PDF, 4.72 MB, 51 pages)Wenlock CA (PDF, 3.84 MB, 44 pages)Wenlock EA (PDF, 6.74 MB, 119 pages)
|
Alpha Petroleum Resources Limited |
- |
Platform, mid line tee protection structure, exposed tie-in spools and stabilisation features will be removed to shore. Trenched and buried pipelines will remain in situ. |
February 2022 |
|
|
Cormorant Alpha Topsides DP (PDF, 3.91 MB, 81 pages)Cormorant Alpha Topsides EA (PDF, 8.21 MB, 117 pages)
|
TAQA Bratani Limited |
- |
Topsides Recovered to shore for reuse/recycling or disposal |
February 2022 |
|
|
Caledonia Decommissioning Programme (PDF, 3.1 MB, 50 pages)Caledonia Comparative Assessment (PDF, 2.04 MB, 64 pages)Caledonia Environmental Assessment (PDF, 5.56 MB, 113 pages)
|
Premier Oil UK Limited |
- |
Subsea installations, trenched and buried flexible pipelines, umbilicals, spools and jumpers returned to shore for recycling or disposal, Trenched and buried rigid pipelines will be left in situ. |
February 2022 |
|
|
Thistle Topsides Decommissioning Programme (PDF, 3.11 MB, 38 pages) |
EnQuest Heather Limited |
- |
Recovery of topsides to shore for reuse, recycling or disposal |
December 2021 |
|
|
Indefatigable 18A Topsides Decommissioning Programme (PDF, 1.29 MB, 50 pages) |
Perenco UK Limited |
- |
Recovery of topsides to shore for reuse, recycling or disposal |
December 2021 |
|
|
Banff and Kyle Decommissioning Programmes (PDF, 3.23 MB, 71 pages)Banff and Kyle Environmental Appraisal (PDF, 7.07 MB, 114 pages)Banff and Kyle Comparative Assessment (PDF, 2.75 MB, 106 pages)
|
CNR International (U.K.) Limited |
- |
Subsea installations, mooring piles, chains and surface laid pipelines returned to shore for reuse, recycling or disposal. Trenched pipelines will be left in situ. |
November 2021 |
|
|
Ensign installation DP (PDF, 2.52 MB, 37 pages)Ensign Pipelines DP (PDF, 1.99 MB, 42 pages)Ensign CA (PDF, 1.67 MB, 48 pages)Ensign EA (PDF, 9.45 MB, 134 pages)
|
Spirit Energy North Sea Limited |
- |
Installations and all exposed grout bags and concrete mattresses will be recovered to shore for reuse or recycling. Buried pipelines will be left in situ with exposed ends cut and removed. Concrete Plinths and existing rock will be left in situ. |
August 2021 |
|
|
Conrie, Don SW, W Don and Ythan Decommissioning Programmes (PDF, 7.29 MB, 88 pages)Don SW and W Don Comparative Assessment (PDF, 5.33 MB, 76 pages)Conrie, Don SW, W Don and Ythan Environmental Appraisal (PDF, 8.07 MB, 132 pages)
|
EnQuest Heather Limited |
- |
Installations, surface laid pipelines and associated concrete mattresses and grout bags will be recovered to shore for reuse, recycling or disposal. Trenched and buried sections of pipelines and existing rock dump will be left in situ. |
August 2021 |
|
|
Fulmar and Auk North Topsides, Subsea Facilities and Pipelines Decommissioning Programme (PDF, 3.83 MB, 78 pages)Fulmar and Auk North Subsea Infrastructure and Pipelines Comparative Assessment (PDF, 4.63 MB, 144 pages)Fulmar & Auk North Environmental Appraisal (PDF, 5.17 MB, 114 pages)
|
Repsol Sinopec Resources UK Limited |
- |
Removal of topsides and subsea installations to shore for reuse, recycling or disposal. Trenched and buried pipelines will be left in situ. Tie-in spools and trench transition sections of the pipelines shall be cut, recovered and returned to shore for recycling. Exposed remaining sections of pipe shall be rock covered. |
July 2021 |
|
|
Heather Topsides Decommissioning Programme (PDF, 4.07 MB, 43 pages) |
EnQuest Heather Limited |
- |
Recovery of topsides to shore for reuse, recycling or disposal |
July 2021 |
|
|
Kingfisher Decommissioning Programme (PDF, 2.95 MB, 76 pages)Kingfisher CA (PDF, 2.19 MB, 51 pages)Kingfisher EA (PDF, 3.48 MB, 119 pages)
|
Shell U.K. Limited |
- |
Removal of installations to shore for recycling or reuse. Trenched and/or buried pipeline sections will be decommissioned in situ. The end of the pipelines will be cut, and additional rock cover will be added to cut ends to reduce snagging risk. |
June 2021 |
|
|
Gaupe Decommissioning Programme (PDF, 1.86 MB, 47 pages)Gaupe CA (PDF, 1.32 MB, 51 pages)Gaupe EA (PDF, 5.77 MB, 113 pages)
|
A/S Norske Shell |
- |
Full removal of SSIV, full removal of risers. Partial removal of pipelines and umbilicals. |
May 2021 |
|
|
PL301 Heimdal to Brae Pipeline Decommissioning Programme (PDF, 7.71 MB, 53 pages)PL301 Heimdal to Brae Pipeline Comparative Assessment (PDF, 6.77 MB, 55 pages)PL301 Heimdal to Brae Environmental Appraisal (PDF, 9.64 MB, 114 pages)
|
Equinor Energy AS |
- |
Majority of pipeline will be left in situ with rock placement over spans/exposures. 20m surface laid section of pipeline out with the existing trench to be removed and recovered to shore. |
April 2021 |
|
|
Hunter & Rita Decommissioning Programme (PDF, 2.1 MB, 44 pages)Hunter & Rita CA (PDF, 1.99 MB, 79 pages)Hunter & Rita EA (PDF, 4.96 MB, 131 pages)
|
Premier Oil E&P UK Limited |
- |
Subsea installations, Trenched & buried Flexible Flowlines & Umbilicals Rigid Spool pieces and jumpers will be returned to shore for recycling or disposal. Trenched and buried pipelines, failed flexible flowlines and umbilical will be left in situ. Exposed ends & areas of exposure to be removed & returned to shore for recycling or disposal. Local rock placement will be used to mitigate snag hazard from cut ends. |
April 2021 |
|
|
LOGGS PR, LOGGS PC, LOGGS PP, LOGGS PA, North Valiant PD, & Associated Pipelines – LDP5 (PDF, 12.2 MB, 99 pages) |
Chrysaor Production (U.K.) Limited |
- |
Removal of topsides and jackets to shore for recycling or disposal. Buried pipelines associated with PP will be left in situ and the riser sections of pipelines will be removed to shore for reuse or recycling with the PP and PR jackets. |
April 2021 |
|
|
Windermere Decommissioning Programme (PDF, 1.95 MB, 41 pages)Windermere CA (PDF, 802 KB, 34 pages)Windermere ES (PDF, 7.86 MB, 231 pages)
|
INEOS UK SNS Limited |
- |
Removal of topsides and jacket to shore for recycling or disposal. The pipelines will be partially removed, the exposed sections adjacent to the platforms will be removed and recycled or disposed onshore. The exposed ends will be lowered to achieve adequate depth of coverage. The existing buried sections of umbilical will be left in situ. All concrete mattresses and grout bags will be recovered to shore for reuse, recycling or disposal. |
March 2021 |
|
|
Hewett Decommissioning Programme (PDF, 5.76 MB, 69 pages)Hewett Environmental Appraisal (PDF, 16.9 MB, 134 pages)
|
ENI Hewett Limited |
- |
All 6 platforms will be removed and returned to shore for processing/recycling or disposal |
March 2021 |
|
|
Buchan & Hannay Decommissioning Programme (PDF, 3.33 MB, 57 pages)Buchan & Hannay CA (PDF, 3.83 MB, 91 pages)Buchan & Hannay EA (PDF, 8.29 MB, 115 pages)
|
Repsol Sinopec Resources UK Limited |
- |
Subsea installations and surface laid pipelines will be removed to shore for either reuse, disposal or recycling. Buried and stable pipelines will be left in situ. |
March 2021 |
|
|
Huntington Decommissioning Programme (PDF, 2.52 MB, 41 pages)Huntington CA (PDF, 1.86 MB, 62 pages)Huntington EA (PDF, 5.01 MB, 127 pages)
|
Premier Oil E&P UK Limited |
- |
Subsea installations, Trench and Buried flexible pipelines, umbilicals, spools and jumpers will be returned to shore for recycling or appropriate treatment and disposal. Trenched and buried rigid, stable pipelines will be left in situ. |
March 2021 |
|
|
Northern Producer FPF and Don SW + W Don riser disconnection (PDF, 4.89 MB, 58 pages) |
Submitted jointly by Qualimar Shipping Company Limited and EnQuest Heather Limited |
- |
Removal for reuse, recycling or disposal of Northern Producer FPF, Mooring and anchor systems, mid water arch and risers and Pipeline sections and exposed mattresses within the 500m safety zone |
March 2021 |
|
|
Balmoral Decommissioning Programme (PDF, 4.27 MB, 65 pages)Balmoral Area CA (PDF, 2.56 MB, 116 pages)Balmoral Area EA (PDF, 8.03 MB, 196 pages)
|
Premier Oil E&P UK Limited |
- |
The Balmoral FPV will be towed to a suitable location for re-sale, reuse, recycling or disposal. The mooring chains will be recovered to the point of burial at the anchor pile. Subsea installations will be returned to shore for recycling or appropriate treatment and disposal. Trenched and buried rigid, stable pipelines will be left in situ. Trenched and buried flexible pipelines, umbilicals, spools and jumpers will be removed to shore for recycling or appropriate treatment and disposal |
February 2021 |
|
|
Brenda Decommissioning Programme (PDF, 1.76 MB, 47 pages) |
Premier Oil E&P UK Limited |
- |
Subsea installations will be returned to shore for recycling or appropriate treatment and disposal. Trenched and buried rigid, stable pipelines will be left in situ. Trenched and buried flexible pipelines, umbilicals, spools and jumpers will be removed to shore for recycling or appropriate treatment and disposal. |
February 2021 |
|
|
Glamis Decommissioning Programme (PDF, 2.53 MB, 46 pages) |
Premier Oil E&P UK Limited |
- |
Subsea installations will be returned to shore for recycling or appropriate treatment and disposal. Trenched and buried rigid, stable pipelines will be left in situ. Trenched and buried flexible pipelines, umbilicals, spools and jumpers will be removed to shore for recycling or appropriate treatment and disposal. |
February 2021 |
|
|
Nicol Decommissioning Programme (PDF, 1.68 MB, 45 pages) |
Premier Oil E&P UK Limited |
- |
Subsea installations will be returned to shore for recycling or appropriate treatment and disposal. Trenched and buried rigid, stable pipelines will be left in situ. Trenched but not backfilled umbilicals will be fully removed by reverse reeling, with deburial, and returned to shore for reuse, recycling or appropriate treatment and disposal. Trenched and buried flexible pipelines, umbilicals, spools and jumpers will be removed to shore for recycling or appropriate treatment and disposal |
February 2021 |
|
|
Stirling Decommissioning Programme (PDF, 3.13 MB, 44 pages) |
Premier Oil E&P UK Limited |
- |
Trenched and buried rigid, stable pipelines will be left in situ. Trenched and buried flexible pipelines, umbilicals, spools and jumpers will be removed to shore for recycling or appropriate treatment and disposal. |
February 2021 |
|
|
Topaz Decommissioning Programme (PDF, 2.21 MB, 31 pages)Topaz CA (PDF, 504 KB, 15 pages)Topaz EA (PDF, 1.22 MB, 37 pages)
|
INEOS UK SNS Limited |
- |
Wellhead Protection Structure, will be returned to shore for recycling or appropriate treatment and disposal. The Trenched and Buried, stable pipeline and umbilical will both be left in situ. |
February 2021 |
|
|
North Cormorant DP (PDF, 2.56 MB, 50 pages)North Cormorant EA (PDF, 7.26 MB, 93 pages)
|
TAQA Bratani Limited |
- |
Removal to shore for recycling or reuse |
November 2020 |
|
|
Tern Topsides - Decommissioning Programme (PDF, 2.84 MB, 52 pages)Tern Topsides EA (PDF, 7.03 MB, 91 pages)
|
TAQA Bratani Limited |
- |
Removal to shore for recycling or reuse |
November 2020 |
|
|
Fulmar & Auk North Preparation Work Scopes Decommissioning Programme (PDF, 1.53 MB, 35 pages) |
Repsol Sinopec North Sea Limited |
- |
preparation work scopes relating to the Fulmar and Auk North installations |
November 2020 |
|
|
East Brae Topsides and Braemar Decommissioning Programmes (PDF, 3.88 MB, 62 pages) |
RockRose UKCS8 LLC |
TAQA Bratani Limited |
Removal of topsides and subsea installations to shore for reuse or recycling. Removal to shore of surface laid pipelines. Trenched and buried pipelines to remain in situ |
September 2020 |
|
|
Brent Alpha Jacket (PDF, 2.82 MB, 101 pages) |
Shell U.K. Limited |
- |
Jacket to be removed to 84.5m below sea level for removal to shore for recycling/disposal. Footings to remain in situ |
July 2020 |
|
|
Amethyst A1D, A2D, B1D & C1D Topsides (PDF, 2.42 MB, 43 pages) |
Perenco UK Limited |
- |
Removal of topsides to shore for reuse, recycling or disposal |
July 2020 |
|
|
Anglia Decommissioning Programme (PDF, 2.18 MB, 61 pages)Anglia CA (PDF, 3.74 MB, 49 pages) Anglia EA (PDF, 5.83 MB, 120 pages)
|
Ithaca Energy UK Limited |
Removal of topsides and jacket to shore for recycling or reuse. Pipelines will remain in-situ. All tie-in spools for the 8” import line, 12” export line and 3” Methanol line will be completely removed. Partial removal of 6” umbilical. |
June 2020 |
|
|
|
Brynhild Pipelines (PDF, 1.98 MB, 50 pages) |
Lundin Energy Norway AS |
- |
The trenched and buried sections of pipelines and umbilicals will be decommissioned in situ. The exposed sections will be remediated by either cut with removal to shore, trench and burial or rock cover. Exposed mattresses will be removed to shore for reuse, recycling or disposal. The PLET, support frames and protection covers will be completely removed to shore for reuse, recycling or disposal. |
June 2020 |
|
|
Cormorant Alpha Derrick Structure Removal (PDF, 4.28 MB, 57 pages) |
TAQA Bratani Limited |
- |
Removal of drilling derrick structure and installation of modular drilling rig to facilitate well P&A |
June 2020 |
|
|
Cavendish (PDF, 2.4 MB, 40 pages) |
INEOS UK SNS Limited |
- |
Removal to shore of topsides and jacket. Partial removal of pipelines (buried sections left it situ). |
June 2020 |
|
|
Banff and Kyle FPSO and FSO Float Off (PDF, 3.45 MB, 39 pages) |
CNR International (U.K.) Limited. |
- |
Removal of FPSO and FSO to shore for redeployment. The STL Buoy and associated mooring lines will be removed to shore for recycling. Associated riser sections and umbilicals within the water column will be removed to shore for recycling |
May 2020 |
Banff and Kyle FPSO and FSO Float Off Interim Close Out Report (PDF, 2.31 MB, 36 pages) |
May 2021 |
Eider Topsides DP (PDF, 2.38 MB, 50 pages) |
TAQA Bratani Limited |
- |
Removal of topsides to shore for recycling or reuse |
May 2020 |
|
|
Ganymede, Europa, Callisto and NW Bell – LDP3 (PDF, 4.85 MB, 101 pages) |
Chrysaor Production (U.K.) Limited |
- |
Removal of topside and jackets to shore. NW Bell pipelines will be recovered to shore. Ganymede, Europa and Callisto interfield pipelines will be decommissioned in situ. |
May 2020 |
|
|
Ganymede ZD Topsides - LDP3b (PDF, 2.31 MB, 46 pages) |
Chrysaor Production (U.K.) Limited |
- |
Removal of topsides to shore for recycling or reuse. |
April 2020 |
|
|
Huntington FPSO (Voyageur Spirit) (PDF, 1.19 MB, 21 pages) |
Premier Oil E&P UK Limited |
- |
The Huntington FPSO (Voyageur Spirit) is to be floated off station and redeployed. The risers and mooring system will be removed and taken to shore |
April 2020 |
|
|
Caister - CDP1a (PDF, 2.93 MB, 49 pages) |
Chrysaor Production (U.K.) Limited |
- |
Topsides and Jacket and associated sections of pipeline risers attached to the Caister platform removed to shore for recycling or reuse. |
March 2020 |
|
|
Alma & Galia DPs (PDF, 4.34 MB, 61 pages) |
EnQuest Heather Limited |
- |
Removal of FPSO to shore for recycling. Partial removal of the mooring anchor piles. The mooring chain will be cut locally to the mooring pile and buried to 1m below seabed. Removal of manifolds, wellhead protection structures and pipelines. |
March 2020 |
|
|
Brent Field Pipelines (PDF, 4.05 MB, 130 pages) |
Shell U.K. Limited |
- |
Removal to shore for recycling/disposal, trench/backfill, buried pipelines left in situ |
March 2020 |
|
|
Thistle COS Tanks (PDF, 3.34 MB, 59 pages) |
EnQuest Heather Limited |
- |
Removal of crude oil storage tanks to shore for recycling |
January 2020 |
|
|
Banff SAL Buoy (PDF, 996 KB, 20 pages) |
CNR International (U.K.) Limited. Decommissioning Programmes submitted by Teekay Petrojarl Floating Production UK Ltd. |
- |
Removal of subsea installations to shore for either reuse or recycling. Part of pipeline to be returned to shore for recycling |
November 2019 |
Banff SAL Buoy Interim Close Out Report (PDF, 1.22 MB, 12 pages) |
May 2021 |
MacCulloch Decommissioning Programmes (PDF, 1.36 MB, 40 pages) |
Chrysaor Production (U.K.) Limited |
- |
The anchors will be decommissioned in situ. All other installations and pipelines will be removed to shore for either reuse or recycling |
November 2019 |
|
|
Goldeneye (PDF, 3.41 MB, 53 pages) |
Shell U.K. Limited |
- |
Removal of topsides, jacket and sections of pipelines from the Goldeneye Platform up to but excluding the main pipeline tie-in flanges to shore for reuse or recycling. |
November 2019 |
|
|
Brae Alpha West Drilling Rig (PDF, 2.2 MB, 24 pages) |
RockRose Energy UKCS8 LLC |
TAQA Bratani Limited |
Removal of the drilling rig to shore for recycling or disposal |
September 2019 |
|
|
South Morecambe DP3/DP4 (PDF, 2.72 MB, 57 pages) |
Spirit Energy Production UK Limited |
- |
Removal of topsides and jackets to shore for either reuse or recycling. Buried and stable pipelines left in situ, exposed pipeline ends cut and recovered to shore for either reuse or recycling |
September 2019 |
|
|
Pickerill A&B Installations (PDF, 1.79 MB, 54 pages) |
Perenco Gas (UK) Limited |
- |
Removal of topsides and jackets to shore for either reuse or recycling. |
September 2019 |
|
|
Minke Decommissioning Programmes (PDF, 8.56 MB, 59 pages) |
Neptune E&P UKCS Limited |
- |
Removal of WHPS and small surface laid sections of pipelines to shore for reuse or recycling. Buried sections of pipelines to be left in situ |
September 2019 |
|
|
Ketch (PDF, 2.65 MB, 60 pages)Schooner (PDF, 4.97 MB, 63 pages)
|
DNO North Sea (ROGB) Limited |
- |
Topsides, jackets and subsea installation removed to shore for reuse, recycling or disposal. Trenched and buried pipelines left in situ |
August 2019 |
|
|
Juliet (PDF, 6.16 MB, 47 pages) |
Neptune E&P UKCS Limited |
- |
Removal to shore of subsea installations and small surface laid sections of the pipeline and umbilical for either reuse or recycling; buried sections to be left in-situ |
August 2019 |
|
|
Dunlin Alpha to Cormorant Alpha Pipeline - PL5 (PDF, 4.36 MB, 73 pages) |
Fairfield Betula Limited |
- |
Trenched sections will be left in situ, exposed pipeline ends cut and recovered and severed ends rock dumped |
July 2019 |
PL5 Close Out Report (PDF, 4.74 MB, 27 pages) |
February 2021 |
Ninian Northern Platform (PDF, 2.34 MB, 70 pages) |
CNR International (U.K.) Limited |
- |
Topsides and jacket to top of footings to be removed to shore for recycling/disposal. Footings to remain in situ. |
June 2019 |
|
|
Nevis N11 WHPS (PDF, 1.66 MB, 26 pages) |
Apache Beryl I Limited |
- |
Removal of WHPS to shore for reuse or recycling |
June 2019 |
Nevis N11 WHPS Close out report (PDF, 1.86 MB, 25 pages) |
September 2022 |
Dunlin Alpha Topsides (PDF, 4.97 MB, 44 pages) |
Fairfield Betula Limited |
- |
Removal of topsides to shore for recycling or disposal |
May 2019 |
|
|
Hewett (PDF, 1.5 MB, 21 pages) |
Eni Hewett Limited |
ENI UK Limited |
removal of Vent Stack & other preparatory works |
April 2019 |
Hewett Vent Stack Close Out Report (PDF, 595 KB, 11 pages) |
September 2021 |
Pickerill A & B (PDF, 1.26 MB, 21 pages) |
Perenco Gas (UK) Limited |
- |
removal of Telecommunication towers, sub-cellar deck equipment, appurtenances, caissons, associated tanks and lift pumps, supply hoses, a pipeline riser emergency shutdown valve and tertiary steelwork to shore for reuse, recycling or disposal |
March 2019 |
|
|
Curlew B, C and D (PDF, 2.4 MB, 61 pages) |
Shell U.K. Limited |
- |
FPSO, subsea installations, some pipelines removed to shore for recycling / disposal. Buried pipelines to remain in situ |
March 2019 |
|
|
Viking Platforms, Vixen and associated Pipelines (VDP2) (PDF, 33.3 MB, 84 pages) |
ConocoPhillips (U.K.) Limited |
- |
all platforms and subsea installations recovered to shore for reuse, recycling or disposal. Pipelines will be left in situ |
January 2019 |
|
|
Victor (VDP3) (PDF, 21.1 MB, 55 pages) |
ConocoPhillips (U.K.) Limited |
- |
Platform and subsea installation recovered to shore for reuse, recycling or disposal. Pipelines will be left in situ |
January 2019 |
|
|
Tyne South Installations (PDF, 1.83 MB, 42 pages) |
Perenco UK Limited |
- |
Topsides, jacket and subsea installation removed to shore for reuse, recycling or disposal |
January 2019 |
|
|
Guinevere Installation (PDF, 2.05 MB, 43 pages) |
Perenco UK Limited |
- |
Topsides and jacket removed to shore for reuse, recycling or disposal |
January 2019 |
|
|
Beatrice Decommissioning Programmes (PDF, 4.45 MB, 88 pages) |
Repsol Sinopec Resources UK Limited |
- |
AP Topsides, AD, Bravo and Charlie Platforms and AD Drilling Template removal to shore for reuse/recycling. Buried pipelines will be left in situ. Remediation for any exposed sections |
January 2019 |
|
|
Bains Decommissioning Programmes (PDF, 2.57 MB, 36 pages) |
Spirit Energy Production UK Limited |
- |
Subsea Installation removed to shore for reuse/recycling. Pipelines to be decommissioned in situ. |
January 2019 |
|
|
Jacky (PDF, 2.34 MB, 52 pages) |
Ithaca Energy (UK) Limited |
- |
Wellhead Platform and Midline Tee Structure removed to shore for either reuse or recycling. Pipelines are trenched and buried and will be left in situ |
October 2018 |
|
|
Brae Bravo Topsides, Flare Bridge, Flare Tower and Flare Jacket and Substructure (PDF, 4.9 MB, 52 pages) |
Marathon Oil UK LLC |
TAQA Bratani Limited |
Brae Bravo Topsides, Flare Bridge, Flare Tower and Flare Jacket/Substructure removed to shore for either reuse or recycling |
August 2018 |
|
|
Brent Alpha, Bravo and Charlie Topsides (PDF, 3.34 MB, 81 pages) |
Shell U.K. Limited |
- |
Topsides removed to shore for recycling/disposal |
August 2018 |
|
|
Stirling A33 WHPS Decommissioning Programme (PDF, 1.13 MB, 27 pages) |
Premier Oil E&P UK Limited |
- |
Subsea installation removed to shore for recycling |
May 2018 |
Stirling WHPS Close Out Report (PDF, 2.57 MB, 15 pages) |
February 2019 |
Ann and Alison (PDF, 2.98 MB, 60 pages) |
Spirit Energy North Sea Limited |
- |
installations and surface laid pipelines recovered to shore for either reuse or recycling. Buried and stable pipelines left in situ. |
April 2018 |
|
|
Saturn (Annabel) (PDF, 2.49 MB, 47 pages) |
Spirit Energy North Sea Limited |
- |
installations and surface laid pipelines recovered to shore for either reuse or recycling. Buried and stable pipelines left in situ. |
April 2018 |
|
|
Audrey (PDF, 2.87 MB, 58 pages) |
Spirit Energy North Sea Limited |
- |
Topsides and jackets removed to shore for recycling/disposal and surface laid pipelines recovered to shore for either reuse or recycling. Buried and stable pipelines left in situ. |
April 2018 |
|
|
Rev Decommissioning Programme (PDF, 12 MB, 42 pages) |
Repsol Norge AS |
- |
Buried and stable pipeline to be left in situ. Remaining pipelines recovered to shore along with mattresses. |
April 2018 |
|
|
Markham ST-1 (PDF, 2.39 MB, 49 pages) |
Centrica Production Nederland B.V. |
Spirit Energy Nederland B.V. |
Platform removed to shore for reuse/recycling and pipelines to be left in situ. |
February 2018 |
Markham ST-1 Close Out Report (PDF, 6.19 MB, 68 pages) |
July 2021 |
Osprey (PDF, 3.92 MB, 68 pages) |
Fairfield Fagus Limited |
- |
Installation removed to shore for recycling/disposal. Full removal with the exception of the Bundles, Umbilical Risers within the Dunlin Alpha Concrete Gravity Based Structure or those trenched, and rock dumped. |
December 2017 |
Osprey Close Out Report (PDF, 1.71 MB, 34 pages) |
January 2021 |
Merlin (PDF, 2.97 MB, 56 pages) |
Fairfield Fagus Limited |
- |
Installation removed to shore for recycling/disposal. Full removal with the exception of trenched and rock dumped pipelines and umbilicals and umbilical riser within the Dunlin Alpha Concrete Gravity Based Structure. |
December 2017 |
Merlin Close Out Report (PDF, 1.47 MB, 27 pages) |
January 2021 |
Dunlin Fuel Gas Import (DFGI) and Dunlin Power Import (DPI) (PDF, 3.48 MB, 54 pages) |
Fairfield Fagus Limited |
- |
Installation removed to shore for recycling/disposal. Full removal with the exception of trenched and rock dumped pipelines and rigid riser and riser cable within the Dunlin Alpha Concrete Gravity Based Structure. |
December 2017 |
DFGI/DPI Close Out Report (PDF, 2.19 MB, 30 pages) |
January 2021 |
Viking Satellites CD, DD, ED, GD, HD Pipelines (PDF, 6.77 MB, 32 pages) |
ConocoPhillips (U.K.) Limited |
- |
All pipelines and associated mattresses to remain in situ. |
November 2017 |
|
|
LOGGS Satellites Vulcan UR, Viscount VO, Vampire OD - LDP1 (PDF, 17.5 MB, 61 pages) |
ConocoPhillips (U.K.) Limited |
- |
Topsides and jackets removed to shore for recycling/disposal. All pipelines and associated mattresses to remain in situ. |
November 2017 |
|
|
Leman BH Decommissioning Programme (PDF, 4.66 MB, 46 pages) |
Shell U.K. Limited |
- |
Topside and jacket removed to shore for reuse/recycling. |
April 2017 |
Leman BH Close Out Report (PDF, 1.71 MB, 25 pages) |
March 2019 |
Ettrick and Blackbird (PDF, 2.1 MB, 62 pages) |
Nexen Petroleum U.K Limited |
- |
FPSO removed for reuse at different location. Subsea equipment removed to shore for reuse/recycling. Buried pipelines to be left in situ with the remaining pipelines removed to shore. |
March 2017 |
|
|
Ann A4 Decommissioning Programme (PDF, 1.37 MB, 29 pages) |
Centrica North Sea Limited |
- |
WHPS to be removed to shore for reuse/recycling. |
February 2017 |
|
|
Janice James & Affleck (PDF, 3.8 MB, 115 pages) |
Maersk Oil UK Limited |
- |
FPSO removed to shore for recycling. Subsea equipment removed to shore for reuse/recycling. Buried pipelines to be left in situ with the remaining pipelines removed to shore. |
September 2016 |
|
|
Athena Decommissioning Programmes (PDF, 3.88 MB, 70 pages) |
Ithaca Energy (UK) Limited |
- |
FPSO removed for reuse at different location. Subsea equipment removed to shore for reuse/recycling. All pipelines to be removed to shore. |
September 2016 |
|
|
Viking Platforms (PDF, 3.53 MB, 40 pages) |
ConocoPhillips (U.K.) Limited |
- |
Topsides and jackets to be removed to shore for recycling/disposal. |
September 2016 |
|
|
Leadon (PDF, 1.71 MB, 53 pages) |
Maersk Oil North Sea UK Limited |
- |
FPSO removed for reuse at different location. Removal of 2 x bundle towheads and mid-line structure to shore for disposal; removal of 2 x drill centres to shore for disposal. 2 x pipeline bundles to be left in situ, partial removal of gas import pipeline. |
March 2016 |
|
|
Harding STL (PDF, 2.61 MB, 73 pages) |
TAQA Bratani Limited |
- |
Harding Submerged Turret Loading (STL) System to be replaced by new Offshore Loading System. STL to be removed to shore for recycling/disposal and shuttle tanker mooring and loading buoy interfaces returned to owner. |
December 2015 |
Harding STL Close-Out Report (PDF, 1.62 MB, 26 pages) |
June 2017 |
Thames Area – Horne & Wren (PDF, 1.57 MB, 48 pages) |
Tullow Oil SK Limited |
- |
Removal of topsides and jackets to shore for recycling/disposal. Pipelines to remain buried in situ. |
November 2015 |
|
|
Thames Area – Orwell (PDF, 828 KB, 42 pages) |
Tullow Oil SK Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Pipelines to remain buried in situ. |
November 2015 |
|
|
Thames Area – Wissey (PDF, 1.26 MB, 43 pages) |
Tullow Oil SK Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Pipelines to remain buried in situ. |
November 2015 |
|
|
Thames Area – Thames Complex (PDF, 15.9 MB, 76 pages) |
Perenco UK Limited |
- |
Removal of topsides and jackets to shore for recycling/disposal. Removal of subsea installations to shore for recycling/disposal. Pipelines to remain buried in situ. |
October 2015 |
|
|
Thames Area – Gawain (PDF, 3.8 MB, 47 pages) |
Perenco UK Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Pipelines to remain buried in situ. |
October 2015 |
|
|
Thames Area – Arthur (PDF, 4.41 MB, 46 pages) |
Perenco UK Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Pipelines to remain buried in situ. |
October 2015 |
|
|
Brent - Brent Delta Topside (PDF, 3.55 MB, 72 pages) |
Shell U.K. Limited |
- |
Removal of topside to shore for recycling and disposal. |
July 2015 |
Brent Delta Topside Close Out Report (PDF, 4.42 MB, 53 pages) |
February 2020 |
Rose Decommissioning Programmes (PDF, 2.87 MB, 42 pages) |
Centrica Resources Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Removal of sections of untrenched pipelines, trenched pipelines to remain in situ. |
May 2015 |
Rose Close Out Report (PDF, 3.31 MB, 36 pages) |
October 2018 |
Stamford (PDF, 2.71 MB, 39 pages) |
Centrica North Sea Gas Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Removal of sections of untrenched pipelines, trenched pipelines to remain in situ. |
April 2015 |
Stamford Close Out Report (PDF, 2.66 MB, 36 pages) |
February 2019 |
Murchison (PDF, 2.37 MB, 70 pages) |
CNR |
- |
Removal of topsides and jackets to shore for recycling/disposal. Footings to remain in situ. Export pipeline to remain in situ with remedial rock placement. Infield Flowlines to be removed for recycling/disposal. |
August 2014 |
|
|
Rubie & Renee (PDF, 2.47 MB, 50 pages) |
Endeavour Energy UK Limited |
- |
Removal of subsea installations to shore for recycling/disposal. Selective recovery of pipelines. |
April 2014 |
Rubie Renee Decommissioning Close Out Report (PDF, 9.98 MB, 66 pages) |
September 2021 |
Miller (PDF, 6.57 MB, 198 pages) |
BP Exploration (Alpha) Limited |
- |
Footings to remain in situ. Steel topsides and jacket to top of footings to be removed to shore. |
December 2013 |
|
|
Schiehallion & Loyal Phase One (PDF, 1.84 MB, 60 pages) |
Britoil Limited |
- |
FPSO removed for potential reuse. Pipeline recovery where possible. Production pipelines to remain in situ. |
April 2013 |
Schiehallion & Loyal Phase One Close Out Report (PDF, 1010 KB, 22 pages) |
May 2019 |
IVRR - decommissoning programme (PDF, 1.57 MB, 102 pages) |
Hess Limited |
- |
FPSO removed for reuse at different location. Removal of subsea installations to shore for recycling/disposal. Selective recovery of pipelines. |
February 2013 |
IVRR Close Out Report (PDF, 4.74 MB, 35 pages) |
December 2015 |
Camelot (PDF, 488 KB, 39 pages) |
Energy Resource Technology (UK) Limited |
- |
Removal of platform to shore for recycling/disposal. Pipelines to remain in situ. |
June 2012 |
Camelot Close out report (PDF, 2.27 MB, 41 pages) |
August 2013 |
Fife, Flora, Fergus, Angus: decommissioning programme (PDF, 8.36 MB, 135 pages) |
Hess Limited |
- |
FPSO removed for reuse at different location. Removal of subsea installations to shore for recycling/disposal. Removal of untrenched pipelines, trenched pipelines to remain in situ. |
February 2012 |
FFFA Close Out Report (PDF, 1.49 MB, 33 pages) |
December 2014 |
Don (PDF, 8 MB, 175 pages) |
Britoil Public Limited Company |
- |
Removal of subsea installation to shore for recycling/disposal. Pipelines to remain in situ with selective recovery. |
May 2011 |
|
|
Welland DP (PDF, 1.74 MB, 39 pages) |
Perenco UK Limited |
- |
Removal of subsea installation to shore for recycling/disposal. Pipelines to remain in situ with selective recovery. |
September 2010 |
Welland Close Out Report (PDF, 7.42 MB, 130 pages) |
September 2020 |
Tristan NW DP (PDF, 4.11 MB, 119 pages) |
Silverstone Energy Limited |
Bridge Energy UK Limited |
Removal of subsea installation to shore for recycling. Production pipeline with piggy-backed umbilical - leave in situ; jumpers, spool pieces and associated pipeline equipment - remove to shore for re-use or recycling. |
August 2010 |
Tristan NW close out report (PDF, 2.3 MB, 23 pages) |
January 2011 |
Shelley DP (PDF, 3.23 MB, 83 pages) |
Premier Oil |
- |
FPSO removed for reuse at different location. Removal of subsea installations to shore for recycling/disposal. Production pipeline to remain in situ. Umbilical removed in sections. |
June 2010 |
Shelley close out report (PDF, 4.49 MB, 62 pages) |
February 2012 |
Kittiwake Sal DP (PDF, 4.28 MB, 87 pages) |
Venture North Sea Oil Limited |
- |
SAL Assembly - removal to shore for re-use. Revision to approved decommissioning programme: Completion of the removal of the SAL Assembly extended to 31 July 2012. The flexible flowline removed to shore for re-use. |
June 2009 |
Kittiwake Sal close out report (PDF, 588 KB, 13 pages) |
July 2012 |
MCP-01 DP (PDF, 7.41 MB, 336 pages) |
Total E&P UK Limited |
- |
Concrete substructure to remain in situ; topsides to be removed to shore for re-use, recycling or disposal. |
September 2007 |
MCP-01 close out report (PDF, 23.1 MB, 113 pages) |
March 2013 |
Kittiwake Buoy DP (PDF, 3.46 MB, 118 pages) |
Venture North Sea Oil Limited |
- |
Exposed Location Single Buoy Mooring System (ELSBM) removal to shore for recycling or disposal. |
May 2008 |
|
|
Linnhe (PDF, 2.25 MB, 66 pages) |
Mobil North Sea LLC |
- |
Removal of WHPS to shore for recycling. Removal of subsea installations to shore for recycling/disposal. Pipelines to remain in situ; pipeline sections outside trenches removed to shore. |
July 2008 |
Linnhe Close Out Report (PDF, 1000 KB, 22 pages) |
November 2013 |
Indefatigable (Shell) (PDF, 11.6 MB, 224 pages) |
Shell UK Limited |
- |
Removal of installations to shore. Infield and export pipelines to remain in situ; hose bundles removed to shore. |
May 2007 |
Close Out Report (PDF, 2.47 MB, 64 pages) |
December 2014 |
NW Hutton: decommissioning programme (PDF, 14.9 MB, 320 pages) |
Amoco (U.K.) Exploration Company - now a subsidiary of BP plc |
- |
Footings to remain in place, steel topsides and jacket to top of footings to be removed to shore. Pipelines to remain in situ. |
February 2006 |
Close Out Report (PDF, 2.52 MB, 32 pages) |
October 2014 |
Ardmore |
British American Offshore Limited |
- |
Mobile Jack-Up rig removed for reuse. |
2005 |
|
|
Ardmore |
Ugland Nordic Shipping AS |
- |
Single Anchor Loading Systems to be removed to shore for reuse. Pipelines to be removed for reuse |
2005 |
|
|
Ardmore |
Acorn Oil & Gas Limited |
- |
Subsea equipment including guide frame removed to shore. |
2005 |
|
|
Brent Flare DP (PDF, 2.93 MB, 122 pages) |
Shell |
- |
Brent Flare removal to shore for recycling and disposal. |
2004 |
|
|
Beatrice |
Talisman Energy (UK) Limited |
- |
Platforms to be removed for reuse. |
2004 |
|
|
Forbes and Gordon |
BHP Billiton |
- |
Pipelines to be left in situ - retrench any area of pipeline with less than 0.4m depth of cover. |
2003 |
- |
May 2005 |
Frigg DP (PDF, 10 MB, 450 pages) |
Total E&P Norge AS |
- |
Concrete substructures to remain in place; concrete topsides to be removed to shore; steel installations to be removed to shore; infield pipelines to be removed to shore |
May 2003 |
Frigg close out report (PDF, 3.46 MB, 62 pages) |
May 2011 |
Durwood and Dauntless |
Amerada Hess |
- |
Pipelines to be left in situ. |
2002 |
|
|
Hutton |
Kerr McGee |
- |
Tension Leg Platform to be removed for reuse. 1 pipeline to be removed to shore. 1 pipeline to be left in situ. |
2002 |
- |
July 2004 |
Camelot CB |
ExxonMobil |
- |
Platform to be removed for reuse or recycling. |
2001 |
|
|
Blenheim and Bladon |
Talisman |
- |
FPSO to be removed for reuse. Pipelines to be removed to shore. |
2000 |
|
|
Durwood and Dauntless |
Amerada Hess |
- |
FPSO to be removed for reuse. Subsea facilities removal to shore. |
2000 |
|
|
Maureen and Moira |
Phillips |
- |
Platform removal to shore for reuse or recycling. Concrete Loading Column removal to shore for reuse or recycling. 2 pipelines removal to shore. 1 pipeline to be left in situ. |
2000 |
|
|
Brent Spar |
Shell |
- |
Oil Storage and Loading Facility to be removed for reuse as part of quay extension. Brent Spar Anchor Blocks - removal to shore for reuse, recycling or disposal |
1998 |
|
|
Donan |
BP |
- |
FPSO to be removed for reuse. |
1998 |
|
|
Fulmar SALM |
Shell |
- |
Single Anchor Leg Mooring Buoy to be removed to shore. Pipeline to be left in situ. |
1998 |
|
|
Emerald |
MSR |
- |
FPSO to be removed for reuse. Pipeline to be left in situ. |
1996 |
|
|
Frigg FP |
Elf Norge |
TotalFinaElf Norge |
Flare column to be removed to shore. |
1996 |
|
|
Leman BK |
Shell |
- |
Platform removal to shore. |
1996 |
|
|
Staffa |
Lasmo |
- |
Pipeline to be removed to shore. |
1996 |
|
|
Viking AC, AD, AP & FD |
Conoco |
- |
Platforms to be removed to shore. |
1996 |
|
|
Esmond CP & CW |
BHP |
- |
Platforms to be removed to shore. |
1995 |
|
|
Gordon BW |
BHP |
- |
Platform to be removed to shore. |
1995 |
|
|
Angus |
Amerada Hess |
- |
FPSO to be removed for reuse. |
1993 |
|
|
Forbes AW |
Hamilton |
BHP |
Platform to be removed to shore. |
1993 |
|
|
Argyll, Duncan and Innes |
Hamilton |
BHP |
FPSO to be removed to shore. Catenary Anchor Leg Mooring (CALM) Buoy to be removed to shore. Pipelines to be removed to shore. |
1992 |
|
|
Blair |
Sun Oil |
AGIP |
1 pipeline removal for reuse. 1 pipeline to be left in situ. |
1992 |
|
|
Crawford |
Hamilton Oil |
BHP |
FPF to be removed to shore. Catenary Anchor Leg Mooring (CALM) Buoy to be removed to shore. Subsea facilities removal to shore. |
1991 |
|
|
Piper Alpha |
Occidental |
Talisman |
Platform left in situ. |
1988 |
|
|