Wingate |Installations Documentsand |
|—————————————–|————–|————————–|—————-|
Pipelines
Wintershall Noordzee B.V.
Small steel platform, surface laid pipeline sections and associated stabilisation materials will be recovered to shore for reuse or recycling. Buried pipelines will be left in situ.
Wingate DP ( PDF , 2.17 MB , 52 pages )
Wingate EA ( PDF , 28.9 MB , 107 pages )
Wingate CA ( PDF , 4.17 MB , 42 pages )
Wingate Pipeline Survey ( PDF , 1.37 MB , 10 pages )
Don DP
Britoil Limited
Leave the trenched and buried pipelines and umbilical in situ and remove surface laid ends. Remove the Pipebridge and stabilisation features
Don PLs in Thistle 500m Safety Zone DP (PDF , 3.1 MB , 32 pages )
Thistle & Don Combined CA (PDF , 9.13 MB , 124 pages )
Thistle & Don Combined EA (PDF , 7.43 MB , 152 pages )
Thistle PL & SALM Base DP
EnQuest Heather Limited
Remove upper riser, remove umbilical from inside riser caisson, remove surface laid pipelines, remove stabilisation features and remove the SALM base
Thistle PL & SALM Base DP (PDF , 6.29 MB , 50 pages )
Thistle & Don Combined CA (PDF , 9.13 MB , 124 pages )
Thistle & Don Combined EA (PDF , 7.43 MB , 152 pages )
Gannet Wells
Shell U.K. Limited
Full removal of GB01S1 and GF01S1 XTs and wellheads
Gannet Wells GB01S1 and GF01S1 DP (PDF , 761 KB , 20 pages )
Pierce WI Wells
Enterprise Oil Limited
Full removal of A7z, A13Y, B4 wellheads and A8Z, B3, B4A XTs and wellheads.
Pierce WI Wells DP (PDF , 1.03 MB , 20 pages )
Trees Decommissioning Programmes (Birch, Larch & Sycamore)
Spirit Energy North Sea Oil Limited
Full removal of all surface laid pipelines, exposed stabilisation features and Birch and Larch Manifolds and Sycamore wellhead. Trenched and/or buried pipelines, pipelines in open trenches and stabilisation features within trenches and below seabed will be left in situ.
Trees DP (PDF , 2.63 MB , 63 pages )
Trees EA (PDF , 8.33 MB , 103 pages )
Trees CA (PDF , 2.77 MB , 50 pages )
Gryphon Alpha FPSO and Riser Disconnection Decommissioning Programmes
TotalEnergies E&P North Sea UK Limited
Full removal of the FPSO, flexible risers, dynamic umbilical’s and associated MWA’s (buoyant elements only), mooring lines and anchors.
Gryphon Alpha FPSO DP (PDF , 1.28 MB , 42 pages )
Kilmar Installations and Pipelines
Energean UK Limited
Small steel platform and surface laid sections of pipelines will be recovered to shore for reuse or recycling, buried section of pipelines and stabilisation features to be left in situ.
Kilmar DP (PDF , 3.92 MB , 48 pages )
Kilmar CA (PDF , 5.22 MB , 47 pages )
Kilmar EA (PDF , 8.64 MB , 110 pages )
Liverpool Bay Asset - Lennox, Hamilton, Hamilton North
Eni UK Limited
Topsides removal, removal of spools, umbilicals and exposed stabilisation features in the near platform areas
LBA DP (MS Word Document , 5.85 MB )
LBA CA (MS Word Document , 4.98 MB )
LBA EA (MS Word Document , 8.97 MB )
Appendix A (MS Excel Spreadsheet , 251 KB )
Appendix B (MS PowerPoint Presentation , 1.09 MB )
Solan Decommissioning Programmes
Premier Oil UK Limited
Topside, Jacket, subsea installations, stabilisation features, pipelines, umbilicals and risers to be recovered to shore for re-use, recycling or disposal. Any deposited rock will be dispersed and left in situ. All piles will be cut to a target depth of 3m below the average natural seabed level.
Solan Decommissioning Programmes (PDF , 9.2 MB , 76 pages )
Solan Comparative Assessment (PDF , 6.19 MB , 65 pages )
Solan Environmental Appraisal (PDF , 6.97 MB , 133 pages )
Calder, Dalton & Millom Installations and Pipelines
Chrysaor Resources (Irish Sea) Limited
Platforms, subsea installations, surface laid pipelines and umbilicals to be recovered to shore for re-use or recycling. Buried pipelines and Calder trunkline to be left in situ. Protection/stabilisation features will be recovered to shore.
EIS DP (PDF , 6.96 MB , 78 pages )
EIS CA (PDF , 11.7 MB , 115 pages )
EIS EA (PDF , 7.53 MB , 157 pages )
Otter Protection Structures Roof Hatches Removal
TAQA Bratani Limited
Removal of nine roof hatches from the Otter manifold and WHPS . Hatches will be returned to shore for re-use, recycling or disposal.
Otter Protection Structures Roof Hatches Removal (PDF , 1.37 MB , 34 pages )
Garrow
Energean UK Ltd
Small steel platform and surface laid sections of pipelines will be recovered to shore for re-use or recycling. Protection/stabilisation features will be recovered to shore. Buried section of pipelines and stabilisation features to be left in situ.
Garrow DP (PDF , 5.16 MB , 47 pages )
Garrow CA (PDF , 2.88 MB , 36 pages )
Garrow EA (PDF , 8.05 MB , 103 pages )
Thistle Upper Jacket
EnQuest Heather Limited
The upper jacket and pipeline risers will be cut between 65 m and 75 m below LAT and recovered to shore.
Thistle Upper Jacket DP (PDF , 3.53 MB , 46 pages )
Eider Upper Jacket
TAQA Bratani Limited
The Eider Upper Jacket and pipeline risers will be cut to a depth of approximately 127m below lowest astronomical tide and recovered to shore for recycling or disposal.
Eider Upper Jacket DP (PDF , 3.47 MB , 44 pages )
Eider Upper Jacket EA (PDF , 3.22 MB , 93 pages )
Beauly
Repsol Sinopec Resources UK Limited
The wellhead and WHPS will be recovered to shore. The trenched and buried pipelines and umbilicals will be decommissioned in situ. The exposed sections will be either trenched and buried or covered with rock. All surface laid spools/jumpers will be recovered to shore.
Beauly DP (PDF , 4.89 MB , 40 pages )
Beauly & Burghley CA (PDF , 11.5 MB , 73 pages )
Beauly & Burghley EA (PDF , 12.6 MB , 97 pages )
Burghley
Repsol Sinopec Resources UK Limited
The valve skid, wellhead and WHPS will be recovered to shore. The trenched and buried pipelines and umbilicals will be decommissioned in situ. The exposed sections will be either trenched and buied or covered with rock. All surface laid spools/jumpers will be recovered to shore.
Burghley DP (PDF , 5.16 MB , 42 pages )
Beauly & Burghley CA (PDF , 11.5 MB , 73 pages )
Beauly & Burghley EA (PDF , 12.6 MB , 97 pages )
Dunlin Alpha
Fairfield Betula Limited
Decommissioning in situ of Dunlin Alpha concrete gravity based structure and storage cells.
Dunlin Alpha Decommissioning Programme (PDF , 6.5 MB , 77 pages )
Dunlin Alpha Decommissioning Comparative Assessment Report (PDF , 3.66 MB , 133 pages )
Dunlin Alpha Decommissioning Environmental Appraisal (PDF , 6.58 MB , 176 pages )
Brae Alpha, Brae Bravo, Central Brae, West Brae and Sedgwick
Marathon Oil UK LLC
Removal of Brae Alpha and Brae Bravo jackets to the top of the footings. Removal of Central Brae, West Brae and Sedgwick subsea installations. Pipelines to be decommissioned in a variety of ways including removal, trenching and leave in situ.
Brae Alpha, Brae Bravo, Central Brae, West Brae and Sedgwick Decommissioning Programmes (PDF , 15.3 MB , 120 pages )
Brae A etc, Environmental Statement – Main Report (PDF , 14.6 MB , 80 pages )
Brae A etc. Environmental Statement - Technical Appendices (PDF , 13.3 MB , 96 pages )
Brae A Substructure Comparative Assessment (PDF , 1.7 MB , 30 pages )
Brae B Substructure Comparative Assessment (PDF , 1.59 MB , 30 pages )
Brae Area Subsea Assets Comparative Assessment (PDF , 6.84 MB , 43 pages )
Brent
Shell U.K. Limited
Decommissioning in situ of Brent Bravo, Charlie and Delta concrete gravity based structures.
Brent Decommissioning Programme (PDF , 12 MB , 322 pages )
Brent ES (PDF , 12.5 MB , 475 pages )
Brent EIA (PDF , 5.05 MB , 429 pages )
Brent ES Appendix (PDF , 2.52 MB , 45 pages ) A suite of detailed Technical Documents which support the Decommissioning Programmes documents are available on the Shell Website
Atlantic and Cromarty
BG Global Energy Limited and Hess Limited
Manifold and WHPS to be removed for recycling/disposal. Partial removal of pipelines and remaining section of buried/trenched pipelines to remain in situ.
Atlantic & Cromarty Decommissioning Programmes (PDF , 1.76 MB , 50 pages )
Atlantic & Cromarty Stakeholder Report (PDF , 1.11 MB , 32 pages )
Atlantic & Cromarty Environmental Impact Assessment (PDF , 4.5 MB , 109 pages )
Atlantic & Cromarty Comparative Assessment (PDF , 2.06 MB , 110 pages )
Approved decommissioning programmes
Decommissioning Programme and Approval Date
Operator at approval
Operator following licence / company change
Revision Details and Approval Date
Close out report and Date Accepted
Guinevere Pipelines DP (PDF , 3.72 MB , 47 pages )
Guinevere Pipelines EA (PDF , 4.3 MB , 103 pages )
Guinevere Pipelines CA (PDF , 2.71 MB , 63 pages ) October 2024
Perenco Gas (UK) Limited
-
-
-
Durango DP (PDF , 1.35 MB , 38 pages )
Durango EA (PDF , 3.77 MB , 82 pages ) September 2024
Perenco North Sea Limited
-
-
-
East Brae Upper Jacket (PDF , 1.96 MB , 50 pages ) July 2024
TAQA Bratani Limited
-
1. Change of parties to the approved Programmes October 2024
-
KGP Final DP (PDF , 2.49 MB , 56 pages )
KGP Final CA (PDF , 1.83 MB , 48 pages )
KGP Final EA (PDF , 3.12 MB , 74 pages ) May 2024
Gassco AS
-
-
-
Rochelle WHPS and Jumper DPs (PDF , 2.87 MB , 41 pages ) May 2024
CNOOC Petroleum Europe Limited
-
-
-
Leman 27H + 27J Topsides DP (PDF , 3.36 MB , 80 pages ) April 2024
Perenco UK Limited
-
-
-
Trees Protection Cages (Birch, Larch and Sycamore) DP (PDF , 2.59 MB , 38 pages ) February 2024
Spirit Energy North Sea Oil Limited
-
-
-
Leman F & G DP (PDF , 9.92 MB , 86 pages )
Leman F & G CA (PDF , 9.5 MB , 63 pages )
Leman F & G EA (PDF , 15.1 MB , 165 pages ) January 2024
Shell U.K. Limited
-
-
-
Helvellyn CA (PDF , 9.84 MB , 46 pages )
Helvellyn EA (PDF , 7.37 MB , 101 pages )
Helvellyn DP (PDF , 4.75 MB , 44 pages ) January 2024
Waldorf Petroleum Resources Limited
-
-
-
Western Isles Subsea Final DP (PDF , 9.34 MB , 75 pages )
Western Isles Subsea EA Final (PDF , 7.1 MB , 141 pages )
Western Isles Subsea CA Final (PDF , 5.49 MB , 74 pages ) October 2023
Dana Petroleum (E&P) Limited
-
1. Change of parties to the approved Programme September 2024
-
Devenick (PDF , 2.24 MB , 54 pages )
Devenick CA (PDF , 2.02 MB , 58 pages )
Devenick EA (PDF , 6.14 MB , 127 pages ) October 2023
Taqa Bratani Limited
-
-
-
Western Isles FPSO DP (PDF , 5.78 MB , 65 pages ) September 2023
Dana Petroleum (E&P) Limited
-
1. Change of parties to the approved Programme September 2024
-
Heather Pipelines DP (PDF , 4.22 MB , 56 pages )
Heather Pipelines CA (PDF , 5.35 MB , 72 pages )
Heather Pipelines EA (PDF , 6.78 MB , 117 pages ) September 2023
EnQuest Heather Limited
-
-
-
PLU6294 DP (PDF , 1.08 MB , 37 pages ) September 2023
Shell U.K. Limited
-
-
-
Chestnut Phase 2 DP (PDF , 5.6 MB , 57 pages )
Chestnut Phase 2 EA (PDF , 7.97 MB , 104 pages )
Chestnut Phase 2 CA (PDF , 4.42 MB , 67 pages ) June 2023
Spirit Energy North Sea Oil Limited
-
-
-
Heather Upper Jacket DP (PDF , 3.24 MB , 41 pages ) March 2023
EnQuest Heather Limited
-
-
-
Saltire A Topsides and Saltire Area Subsea Infrastructure DPs (PDF , 7.37 MB , 69 pages )
Saltire EA (PDF , 7.09 MB , 109 pages )
Saltire CA (PDF , 4.61 MB , 111 pages ) December 2022
Repsol Sinopec Resources UK Limited
-
-
-
Causeway & Fionn DP (PDF , 4.56 MB , 64 pages )
Causeway & Fionn EA (PDF , 6.78 MB , 94 pages )
Causeway & Fionn CA (PDF , 2.03 MB , 41 pages ) December 2022
Ithaca Energy (UK) Limited
-
-
-
Johnston DP (PDF , 2.18 MB , 43 pages )
Johnston EA (PDF , 5.25 MB , 121 pages )
Johnston CA (PDF , 1.64 MB , 62 pages ) December 2022
Premier Oil E&P UK EU Limited
-
-
-
Duart DP (PDF , 11.2 MB , 55 pages )
Tartan Subsea EA (PDF , 36.4 MB , 137 pages )
Tartan Subsea CA (PDF , 5.5 MB , 135 pages ) November 2022
Repsol Sinopec Resources UK Limited
-
-
-
Tartan N Terrace (TNT) & Tartan Satellite (TS) Subsea DPs (PDF , 4.07 MB , 72 pages )
Tartan Subsea EA (PDF , 36.4 MB , 137 pages )
Tartan Subsea CA (PDF , 5.5 MB , 135 pages ) November 2022
Repsol Sinopec Resources UK Limited
-
-
-
Tartan Topsides DP (PDF , 8.28 MB , 46 pages )
Tartan Subsea EA (PDF , 36.4 MB , 137 pages ) November 2022
Repsol Sinopec Resources UK Limited
-
-
-
Lancaster Field Floating Production Storage and Offloading Vessel (FPSO) Decommissioning Programme (PDF , 2.51 MB , 37 pages ) November 2022
Hurricane Energy PLC
-
-
-
Hewett Area Subsea Installations DP (PDF , 4.45 MB , 54 pages )
Hewett Area Subsea Installations EA (PDF , 14.8 MB , 150 pages ) November 2022
Eni UK Limited
-
-
-
Scoter and Merganser DP (PDF , 4.63 MB , 92 pages )
Scoter and Merganser CA (PDF , 1.94 MB , 47 pages )
Scoter and Merganser EA (PDF , 6.4 MB , 130 pages ) September 2022
Shell UK Limited
-
-
-
Sean DP (PDF , 5.05 MB , 64 pages )
Sean CA (PDF , 2.8 MB , 110 pages )
Sean EA (PDF , 9.44 MB , 171 pages ) August 2022
ONE-Dyas UK Limited
-
-
-
Caister CDP1b (PDF , 5.96 MB , 56 pages )
CMS Area EA (PDF , 10.4 MB , 171 pages )
CMS Area CA (PDF , 13.5 MB , 145 pages ) July 2022
Chrysaor Production (U.K.) Limited
-
-
-
Caister-Murdoch System CDP2 (PDF , 15.7 MB , 131 pages )
CMS Area EA (PDF , 10.4 MB , 171 pages )
CMS Area CA (PDF , 13.5 MB , 145 pages ) July 2022
Chrysaor Production (U.K.) Limited
-
-
-
Murdoch CDP3 (PDF , 8.53 MB , 83 pages )
CMS Area EA (PDF , 10.4 MB , 171 pages )
CMS Area CA (PDF , 13.5 MB , 145 pages ) July 2022
Chrysaor Production (U.K.) Limited
-
-
-
Brae Bravo Upper Jacket Decommissioning Programme (PDF , 1.76 MB , 41 pages ) June 2022
TAQA Bratani Limited
-
-
-
LOGGS Saturn Satellites LDP2 (PDF , 20 MB , 90 pages )
LOGGS LDP2 - LDP5 Comparative Assessment (PDF , 3.21 MB , 203 pages )
LOGGS LDP2 - LDP5 EA (PDF , 7.5 MB , 181 pages ) June 2022
Chrysaor Production (U.K.) Limited
-
-
-
Foinaven FPSO Offstation DP (PDF , 3.76 MB , 60 pages ) May 2022
Britoil Limited
-
-
-
LOGGS V-Fields LDP4 (PDF , 20.8 MB , 83 pages )
LOGGS LDP2 - LDP5 Comparative Assessment (PDF , 3.21 MB , 203 pages )
LOGGS LDP2 - LDP5 EA (PDF , 7.5 MB , 181 pages ) April 2022
Chrysaor Production (U.K.) Limited
-
-
-
Hummingbird Spirit FPSO Sail away and Chestnut Riser Disconnection (PDF , 2.96 MB , 47 pages ) March 2022
Spirit Energy North Sea Oil Limited
-
-
-
Victoria DP (PDF , 2.54 MB , 42 pages )
Victoria CA (PDF , 1.81 MB , 48 pages )
Victoria EA (PDF , 18.4 MB , 158 pages ) April 2022
NEO Energy (SNS) Limited
-
-
-
Wenlock DP (PDF , 4.72 MB , 51 pages )
Wenlock CA (PDF , 3.84 MB , 44 pages )
Wenlock EA (PDF , 6.74 MB , 119 pages ) February 2022
Alpha Petroleum Resources Limited
Energean UK Ltd
-
-
Cormorant Alpha Topsides DP (PDF , 3.91 MB , 81 pages )
Cormorant Alpha Topsides EA (PDF , 8.21 MB , 117 pages ) February 2022
TAQA Bratani Limited
-
-
-
Caledonia Decommissioning Programme (PDF , 3.1 MB , 50 pages )
Caledonia Comparative Assessment (PDF , 2.04 MB , 64 pages )
Caledonia Environmental Assessment (PDF , 5.56 MB , 113 pages ) February 2022
Premier Oil UK Limited
-
-
-
Thistle Topsides Decommissioning Programme (PDF , 3.11 MB , 38 pages ) December 2021
EnQuest Heather Limited
-
-
-
Indefatigable 18A Topsides Decommissioning Programme (PDF , 1.29 MB , 50 pages ) December 2021
Perenco UK Limited
-
-
-
Banff and Kyle Decommissioning Programmes (PDF , 3.23 MB , 71 pages )
Banff and Kyle Environmental Appraisal (PDF , 7.07 MB , 114 pages )
Banff and Kyle Comparative Assessment (PDF , 2.75 MB , 106 pages ) November 2021
CNR International (U.K.) Limited
-
-
-
Ensign installation DP (PDF , 2.52 MB , 37 pages )
Ensign Pipelines DP (PDF , 1.99 MB , 42 pages )
Ensign CA (PDF , 1.67 MB , 48 pages )
Ensign EA (PDF , 9.45 MB , 134 pages ) August 2021
Spirit Energy North Sea Limited
-
-
-
Conrie, Don SW, W Don and Ythan Decommissioning Programmes (PDF , 7.29 MB , 88 pages )
Don SW and W Don Comparative Assessment (PDF , 5.33 MB , 76 pages )
Conrie, Don SW, W Don and Ythan Environmental Appraisal (PDF , 8.07 MB , 132 pages ) August 2021
EnQuest Heather Limited
-
-
-
Fulmar and Auk North Topsides, Subsea Facilities and Pipelines Decommissioning Programme (PDF , 3.83 MB , 78 pages )
Fulmar and Auk North Subsea Infrastructure and Pipelines Comparative Assessment (PDF , 4.63 MB , 144 pages )
Fulmar & Auk North Environmental Appraisal (PDF , 5.17 MB , 114 pages ) July 2021
Repsol Sinopec Resources UK Limited
-
-
-
Heather Topsides Decommissioning Programme (PDF , 4.07 MB , 43 pages ) July 2021
EnQuest Heather Limited
-
-
-
Kingfisher Decommissioning Programme (PDF , 2.95 MB , 76 pages )
Kingfisher CA (PDF , 2.19 MB , 51 pages )
Kingfisher EA (PDF , 3.48 MB , 119 pages ) June 2021
Shell U.K. Limited
-
1. Change of parties to the approved Programme August 2021
-
Gaupe Decommissioning Programme (PDF , 1.86 MB , 47 pages )
Gaupe CA (PDF , 1.32 MB , 51 pages )
Gaupe EA (PDF , 5.77 MB , 113 pages ) May 2021
A/S Norske Shell
-
-
-
PL301 Heimdal to Brae Pipeline Decommissioning Programme (PDF , 7.71 MB , 53 pages )
PL301 Heimdal to Brae Pipeline Comparative Assessment (PDF , 6.77 MB , 55 pages )
PL301 Heimdal to Brae Environmental Appraisal (PDF , 9.64 MB , 114 pages ) April 2021
Equinor Energy AS
-
-
-
Hunter & Rita Decommissioning Programme (PDF , 2.1 MB , 44 pages )
Hunter & Rita CA (PDF , 1.99 MB , 79 pages )
Hunter & Rita EA (PDF , 4.96 MB , 131 pages ) April 2021
Premier Oil E&P UK Limited
-
-
-
LOGGS PR, LOGGS PC, LOGGS PP, LOGGS PA, North Valiant PD, & Associated Pipelines – LDP5 (PDF , 12.2 MB , 99 pages )
Chrysaor Production (U.K.) Limited April 2021
-
-
-
Windermere Decommissioning Programme (PDF , 1.95 MB , 41 pages )
Windermere CA (PDF , 802 KB , 34 pages )
Windermere ES (PDF , 7.86 MB , 231 pages ) March 2021
INEOS UK SNS Limited
-
1. Schedule Extension to 31/12/2025 & Change to decom solution for covering pipeline ends to use rock rather than backfill January 2024
-
Hewett Decommissioning Programme (PDF , 5.76 MB , 69 pages )
Hewett Environmental Appraisal (PDF , 16.9 MB , 134 pages ) March 2021
ENI Hewett Limited
-
-
Buchan & Hannay Decommissioning Programme (PDF , 3.33 MB , 57 pages )
Buchan & Hannay CA (PDF , 3.83 MB , 91 pages )
Buchan & Hannay EA (PDF , 8.29 MB , 115 pages ) March 2021
Repsol Sinopec Resources UK Limited
-
-
-
Huntington Decommissioning Programme (PDF , 2.52 MB , 41 pages )
Huntington CA (PDF , 1.86 MB , 62 pages )
Huntington EA (PDF , 5.01 MB , 127 pages ) March 2021
Premier Oil E&P UK Limited
-
-
-
Northern Producer FPF and Don SW + W Don riser disconnection (PDF , 4.89 MB , 58 pages ) March 2021
Submitted jointly by Qualimar Shipping Company Limited and EnQuest Heather Limited
-
-
Northern Producer Close Out Report (PDF , 5.79 MB , 45 pages ) July2024
Balmoral Decommissioning Programme (PDF , 4.27 MB , 65 pages )
Balmoral Area CA (PDF , 2.56 MB , 116 pages )
Balmoral Area EA (PDF , 8.03 MB , 196 pages ) February 2021
Premier Oil E&P UK Limited
-
-
-
Brenda Decommissioning Programme (PDF , 1.76 MB , 47 pages ) February 2021
Premier Oil E&P UK Limited
-
-
-
Glamis Decommissioning Programme (PDF , 2.53 MB , 46 pages ) February 2021
Premier Oil E&P UK Limited
-
-
-
Nicol Decommissioning Programme (PDF , 1.68 MB , 45 pages ) February 2021
Premier Oil E&P UK Limited
-
-
-
Stirling Decommissioning Programme (PDF , 3.13 MB , 44 pages ) February 2021
Premier Oil E&P UK Limited
-
-
-
Topaz Decommissioning Programme (PDF , 2.21 MB , 31 pages )
Topaz CA (PDF , 504 KB , 15 pages )
Topaz EA (PDF , 1.22 MB , 37 pages ) February 2021
INEOS UK SNS Limited
-
1. Schedule Extension to 31/12/2025 & Change to decom solution for covering pipeline ends to use rock rather than backfill January 2024
-
North Cormorant DP (PDF , 2.56 MB , 50 pages )
North Cormorant EA (PDF , 7.26 MB , 93 pages ) November 2020
TAQA Bratani Limited
-
-
-
Tern Topsides - Decommissioning Programme (PDF , 2.84 MB , 52 pages )
Tern Topsides EA (PDF , 7.03 MB , 91 pages ) November 2020
TAQA Bratani Limited
-
-
-
Fulmar & Auk North Preparation Work Scopes Decommissioning Programme (PDF , 1.53 MB , 35 pages ) November 2020
Repsol Sinopec North Sea Limited
-
-
-
East Brae Topsides and Braemar Decommissioning Programmes (PDF , 3.88 MB , 62 pages ) September 2020
RockRose UKCS8 LLC
TAQA Bratani Limited
-
-
Brent Alpha Jacket (PDF , 2.82 MB , 101 pages ) July 2020
Shell U.K. Limited
-
-
-
Amethyst A1D, A2D, B1D & C1D Topsides (PDF , 2.42 MB , 43 pages ) July 2020
Perenco UK Limited
-
-
-
Anglia Decommissioning Programme (PDF , 2.18 MB , 61 pages )
Anglia CA (PDF , 3.74 MB , 49 pages )
Anglia EA (PDF , 5.83 MB , 120 pages ) June 2020
Ithaca Energy UK Limited
-
-
-
Brynhild Pipelines (PDF , 1.98 MB , 50 pages ) June 2020
Lundin Energy Norway AS
Aker BP ASA
-
Brynhild Pipelines Close Out Report (PDF , 2.86 MB , 25 pages ) March 2024
Cormorant Alpha Derrick Structure Removal (PDF , 4.28 MB , 57 pages ) June 2020
TAQA Bratani Limited
-
-
Cormorant Alpha Derrick Structure Removal Close Out Report (PDF , 5.17 MB , 38 pages ) December 2023
Cavendish (PDF , 2.4 MB , 40 pages ) June 2020
INEOS UK SNS Limited
-
1. Schedule Extension to 31/12/2024 August 2022 2. Schedule Extension to 31/12/2025 & Change to decom solution for covering pipeline ends to use rock rather than backfill January 2024
-
Banff and Kyle FPSO and FSO Float Off (PDF , 3.45 MB , 39 pages ) May 2020
CNR International (U.K.) Limited
-
-
Banff and Kyle FPSO and FSO Float Off Interim Close Out Report (PDF , 2.31 MB , 36 pages ) May 2021
Eider Topsides DP (PDF , 2.38 MB , 50 pages ) May 2020
TAQA Bratani Limited
-
-
-
Ganymede, Europa, Callisto and NW Bell – LDP3 (PDF , 4.85 MB , 101 pages ) May 2020
Chrysaor Production (U.K.) Limited
-
-
-
Ganymede ZD Topsides - LDP3b (PDF , 2.31 MB , 46 pages ) April 2020
Chrysaor Production (U.K.) Limited
-
-
-
Huntington FPSO (Voyageur Spirit) (PDF , 1.19 MB , 21 pages ) April 2020
Premier Oil E&P UK Limited
-
-
-
Caister - CDP1a (PDF , 2.93 MB , 49 pages ) March 2020
Chrysaor Production (U.K.) Limited
-
-
-
Alma & Galia DPs (PDF , 4.34 MB , 61 pages ) March 2020
EnQuest Heather Limited
-
-
-
Brent Field Pipelines (PDF , 4.05 MB , 130 pages ) March 2020
Shell U.K. Limited
-
-
-
Thistle COS Tanks (PDF , 3.34 MB , 59 pages ) January 2020
EnQuest Heather Limited
-
-
-
Banff SAL Buoy (PDF , 996 KB , 20 pages ) November 2019
CNR International (U.K.) Limited. Decommissioning Programmes submitted by Teekay Petrojarl Floating Production UK Ltd.
-
-
Banff SAL Buoy Interim Close Out Report (PDF , 1.22 MB , 12 pages ) May 2021
MacCulloch Decommissioning Programmes (PDF , 1.36 MB , 40 pages ) November 2019
Chrysaor Production (U.K.) Limited
-
-
-
Goldeneye (PDF , 3.41 MB , 53 pages ) November 2019
Shell U.K. Limited
-
-
Goldeneye Close out Report (PDF , 1.95 MB , 35 pages ) July 2024
Brae Alpha West Drilling Rig (PDF , 2.2 MB , 24 pages ) September 2019
RockRose Energy UKCS8 LLC
TAQA Bratani Limited
1. Schedule Extension to 31/12/2023 January 2022
Brae Alpha West Drilling Rig Close Out Report (PDF , 1.68 MB , 24 pages ) April 2024
South Morecambe DP3/DP4 (PDF , 2.72 MB , 57 pages ) September 2019
Spirit Energy Production UK Limited
-
-
-
Pickerill A&B Installations (PDF , 1.79 MB , 54 pages ) September 2019
Perenco Gas (UK) Limited
-
1. Schedule Extension to 31/12/2024 February 2022
-
Minke Decommissioning Programmes (PDF , 8.56 MB , 59 pages ) September 2019
Neptune E&P UKCS Limited
-
1. Schedule Extension to 31/12/2024 July 2021
-
Ketch (PDF , 2.65 MB , 60 pages ) August 2019
DNO North Sea (ROGB) Limited
-
1. Allow for installation of UKNG Viking Cable & Change in decom solution of pipelines to full removal June 2022 2. Include pipeline and fibre optic crossings into DP & Change in decom solution for pipelines remaining under rock berms & additional rock dump on pipeline ends September 2022 3. To alter the S29Holders November 2023 4. Change in decom solution of pipeline sections to leave in situ May 2024
-
Schooner (PDF , 4.97 MB , 63 pages ) August 2019
DNO North Sea (ROGB) Limited
-
1. Allow for installation of UKNG Viking Cable June 2022 2. To alter the S29Holders November 2023 3. Addition of WHPS to DP and its removal & Change in decom solution of exposed pipeline sections to full removal May 2024
-
Juliet (PDF , 6.16 MB , 47 pages ) August 2019
Neptune E&P UKCS Limited
-
1. Schedule Extension to 31/12/2024 July 2021
-
Dunlin Alpha to Cormorant Alpha Pipeline - PL5 (PDF , 4.36 MB , 73 pages ) July 2019
Fairfield Betula Limited
-
-
PL5 Close Out Report (PDF , 4.74 MB , 27 pages ) February 2021
Ninian Northern Platform (PDF , 2.34 MB , 70 pages )
CNR International (U.K.) Limited June 2019
-
-
-
Nevis N11 WHPS (PDF , 1.66 MB , 26 pages ) June 2019
Apache Beryl I Limited
-
-
Nevis N11 WHPS Close out report (PDF , 1.86 MB , 25 pages ) September 2022
Dunlin Alpha Topsides (PDF , 4.97 MB , 44 pages ) May 2019
Fairfield Betula Limited
-
-
Dunlin Alpha Topsides Close Out Report (PDF , 1.63 MB , 36 pages ) September 2024
Hewett (PDF , 1.5 MB , 21 pages ) April 2019
Eni Hewett Limited
ENI UK Limited
-
Hewett Vent Stack Close Out Report (PDF , 595 KB , 11 pages ) September 2021
Pickerill A & B (PDF , 1.26 MB , 21 pages ) March 2019
Perenco Gas (UK) Limited
-
-
-
Curlew B, C and D (PDF , 2.4 MB , 61 pages ) March 2019
Shell U.K. Limited
-
1. Schedule Extension to 31/12/2026 August 2023
-
Viking Platforms, Vixen and associated Pipelines (VDP2) (PDF , 33.3 MB , 84 pages ) January 2019
ConocoPhillips (U.K.) Limited
-
-
-
Victor (VDP3) (PDF , 21.1 MB , 55 pages ) January 2019
ConocoPhillips (U.K.) Limited
-
-
-
Tyne South Installations (PDF , 1.83 MB , 42 pages ) January 2019
Perenco UK Limited
-
-
-
Guinevere Installation (PDF , 2.05 MB , 43 pages ) January 2019
Perenco UK Limited
-
-
-
Beatrice Decommissioning Programmes (PDF , 4.45 MB , 88 pages ) January 2019
Repsol Sinopec Resources UK Limited
-
1. Terminate agreement for Beatrice AD, AP, B & C reuse July 2019
-
Bains Decommissioning Programmes (PDF , 2.57 MB , 36 pages ) January 2019
Spirit Energy Production UK Limited
-
-
-
Jacky (PDF , 2.34 MB , 52 pages ) October 2018
Ithaca Energy (UK) Limited
-
1. Schedule Extension to 31/12/2024 and change to decom solution August 2023
-
Brae Bravo Topsides, Flare Bridge, Flare Tower and Flare Jacket and Substructure (PDF , 4.9 MB , 52 pages ) August 2018
Marathon Oil UK LLC
TAQA Bratani Limited
-
Brae Bravo Topsides Close Out Report (PDF , 3.29 MB , 36 pages ) January 2024
Brent Alpha, Bravo and Charlie Topsides (PDF , 3.34 MB , 81 pages ) August 2018
Shell U.K. Limited
-
-
-
Stirling A33 WHPS Decommissioning Programme (PDF , 1.13 MB , 27 pages ) May 2018
Premier Oil E&P UK Limited
-
-
Stirling WHPS Close Out Report (PDF , 2.57 MB , 15 pages ) February 2019
Ann and Alison (PDF , 2.98 MB , 60 pages ) April 2018
Spirit Energy North Sea Limited
-
-
-
Saturn (Annabel) (PDF , 2.49 MB , 47 pages ) April 2018
Spirit Energy North Sea Limited
-
-
-
Audrey (PDF , 2.87 MB , 58 pages ) April 2018
Spirit Energy North Sea Limited
-
-
-
Rev Decommissioning Programme (PDF , 12 MB , 42 pages ) April 2018
Repsol Norge AS
-
1. Schedule Extension to 31/12/2023 November 2019. 2. Schedule Extension to 31/12/2027 February 2023
-
Markham ST-1 (PDF , 2.39 MB , 49 pages ) February 2018
Centrica Production Nederland B.V.
Spirit Energy Nederland B.V.
-
Markham ST-1 Close Out Report (PDF , 6.19 MB , 68 pages ) July 2021
Osprey (PDF , 3.92 MB , 68 pages ) December 2017
Fairfield Fagus Limited
-
-
Osprey Close Out Report (PDF , 1.71 MB , 34 pages ) January 2021
Merlin (PDF , 2.97 MB , 56 pages ) December 2017
Fairfield Fagus Limited
-
-
Merlin Close Out Report (PDF , 1.47 MB , 27 pages ) January 2021
Dunlin Fuel Gas Import (DFGI) and Dunlin Power Import (DPI) (PDF , 3.48 MB , 54 pages ) December 2017
Fairfield Fagus Limited
-
-
DFGI/DPI Close Out Report (PDF , 2.19 MB , 30 pages ) January 2021
Viking Satellites CD, DD, ED, GD, HD Pipelines (PDF , 6.77 MB , 32 pages ) November 2017
ConocoPhillips (U.K.) Limited
-
-
-
LOGGS Satellites Vulcan UR, Viscount VO, Vampire OD - LDP1 (PDF , 17.5 MB , 61 pages ) November 2017
ConocoPhillips (U.K.) Limited
-
-
-
Leman BH Decommissioning Programme (PDF , 4.66 MB , 46 pages ) April 2017
Shell U.K. Limited
-
-
Leman BH Close Out Report (PDF , 1.71 MB , 25 pages ) March 2019
Ettrick and Blackbird (PDF , 2.1 MB , 62 pages ) March 2017
Nexen Petroleum U.K Limited
-
1. Schedule Extension to 31/12/2023 July 2020 2. Schedule Extension to 31/12/2025 (Ettrick Inst only) December 2022
-
Ann A4 Decommissioning Programme (PDF , 1.37 MB , 29 pages ) February 2017
Centrica North Sea Limited
-
-
-
Janice James & Affleck (PDF , 3.8 MB , 115 pages ) September 2016
Maersk Oil UK Limited
-
1. Change of parties to the approved Programmes Affleck PLs only December 2021
-
Athena Decommissioning Programmes (PDF , 3.88 MB , 70 pages ) September 2016
Ithaca Energy (UK) Limited
-
1. Schedule Extension to 31/12/2023 and change of parties to the approved Programmes January 2021
-
Viking Platforms (PDF , 3.53 MB , 40 pages ) September 2016
ConocoPhillips (U.K.) Limited
-
-
-
Leadon (PDF , 1.71 MB , 53 pages ) March 2016
Maersk Oil North Sea UK Limited
TotalEnergies E&P UK Limited
-
Leadon Close Out Report (PDF , 7.78 MB , 31 pages ) February 2023
Harding STL (PDF , 2.61 MB , 73 pages ) December 2015
TAQA Bratani Limited
-
-
Harding STL Close-Out Report (PDF , 1.62 MB , 26 pages ) June 2017
Thames Area – Horne & Wren (PDF , 1.57 MB , 48 pages ) November 2015
Tullow Oil SK Limited
-
-
-
Thames Area – Orwell (PDF , 828 KB , 42 pages ) November 2015
Tullow Oil SK Limited
-
-
-
Thames Area – Wissey (PDF , 1.26 MB , 43 pages ) November 2015
Tullow Oil SK Limited
-
-
-
Thames Area – Thames Complex (PDF , 15.9 MB , 76 pages ) October 2015
Perenco UK Limited
-
1. Removal of pipeline from the programme March 2018 2. Schedule Extension to 31/12/2023 March 2019 3. Schedule Extension to 31/12/2024 and Change in decom solution of mats to leave in situ.
-
Thames Area – Gawain (PDF , 3.8 MB , 47 pages ) October 2015
Perenco UK Limited
-
1. Schedule Extension to 31/12/2022 March 2019 2. Schedule Extension to 31/12/2024 September 2022
-
Thames Area – Arthur (PDF , 4.41 MB , 46 pages ) October 2015
Perenco UK Limited
-
1. Schedule Extension to 31/12/2022 March 2019 2. Schedule Extension to 31/12/2024 March 2022
-
Brent - Brent Delta Topside (PDF , 3.55 MB , 72 pages ) July 2015
Shell U.K. Limited
-
-
Brent Delta Topside Close Out Report (PDF , 4.42 MB , 53 pages ) February 2020
Rose Decommissioning Programmes (PDF , 2.87 MB , 42 pages ) May 2015
Centrica Resources Limited
-
-
Rose Close Out Report (PDF , 3.31 MB , 36 pages ) October 2018
Stamford (PDF , 2.71 MB , 39 pages ) April 2015
Centrica North Sea Gas Limited
-
-
Stamford Close Out Report (PDF , 2.66 MB , 36 pages ) February 2019
Murchison (PDF , 2.37 MB , 70 pages ) August 2014
CNR
-
-
-
Rubie & Renee (PDF , 2.47 MB , 50 pages ) April 2014
Endeavour Energy UK Limited
-
1. Schedule Extension to 31/12/2017 June 2016 2. Schedule Extension to 31/12/2018 November 2017 3. Schedule Extension to 31/12/2020 December 2018
Rubie Renee Decommissioning Close Out Report (PDF , 9.98 MB , 66 pages ) September 2021
Miller (PDF , 6.57 MB , 198 pages ) December 2013
BP Exploration (Alpha) Limited
-
1. Schedule Extension to 31/12/2024 December 2018
-
Schiehallion & Loyal Phase One (PDF , 1.84 MB , 60 pages ) April 2013
Britoil Limited
-
-
Schiehallion & Loyal Phase One Close Out Report (PDF , 1010 KB , 22 pages ) May 2019
IVRR - decommissoning programme (PDF , 1.57 MB , 102 pages ) February 2013
Hess Limited
-
-
IVRR Close Out Report (PDF , 4.74 MB , 35 pages ) December 2015
Camelot (PDF , 488 KB , 39 pages ) June 2012
Energy Resource Technology (UK) Limited
-
-
Camelot Close out report (PDF , 2.27 MB , 41 pages ) August 2013
Fife, Flora, Fergus, Angus: decommissioning programme (PDF , 8.36 MB , 135 pages ) February 2012
Hess Limited
-
-
FFFA Close Out Report (PDF , 1.49 MB , 33 pages ) December 2014
Don (PDF , 8 MB , 175 pages ) May 2011
Britoil Public Limited Company
-
-
-
Welland DP (PDF , 1.74 MB , 39 pages ) September 2010
Perenco UK Limited
-
-
Welland Close Out Report (PDF , 7.42 MB , 130 pages ) September 2020
Tristan NW DP (PDF , 4.11 MB , 119 pages ) August 2010
Silverstone Energy Limited
Bridge Energy UK Limited
-
Tristan NW close out report (PDF , 2.3 MB , 23 pages ) January 2011
Shelley DP (PDF , 3.23 MB , 83 pages ) June 2010
Premier Oil
-
-
Shelley close out report (PDF , 4.49 MB , 62 pages ) February 2012
Kittiwake Sal DP (PDF , 4.28 MB , 87 pages ) June 2009
Venture North Sea Oil Limited
-
-
Kittiwake Sal close out report (PDF , 588 KB , 13 pages ) July 2012
MCP-01 DP (PDF , 7.41 MB , 336 pages ) September 2007
Total E&P UK Limited
-
-
MCP-01 close out report (PDF , 23.1 MB , 113 pages ) March 2013
Kittiwake Buoy DP (PDF , 3.46 MB , 118 pages ) May 2008
Venture North Sea Oil Limited
-
1. Change of parties to the approved Programme August 2016
-
Linnhe (PDF , 2.25 MB , 66 pages ) July 2008
Mobil North Sea LLC
-
-
Linnhe Close Out Report (PDF , 1000 KB , 22 pages ) November 2013
Indefatigable (Shell) (PDF , 11.6 MB , 224 pages ) May 2007
Shell UK Limited
-
-
Close Out Report (PDF , 2.47 MB , 64 pages ) December 2014
NW Hutton: decommissioning programme (PDF , 14.9 MB , 320 pages ) February 2006
Amoco (U.K.) Exploration Company - now a subsidiary of BP plc
-
-
Close Out Report (PDF , 2.52 MB , 32 pages ) October 2014
Ardmore 2005
British American Offshore Limited
-
-
-
Ardmore 2005
Ugland Nordic Shipping AS
-
-
-
Ardmore 2005
Acorn Oil & Gas Limited
-
-
-
Brent Flare DP (PDF , 2.93 MB , 122 pages ) 2004
Shell
-
-
-
Beatrice 2004
Talisman Energy (UK) Limited
-
-
-
Forbes and Gordon 2003
BHP Billiton
-
-
May 2005
Frigg DP (PDF , 10 MB , 450 pages ) May 2003
Total E&P Norge AS
-
-
Frigg close out report (PDF , 3.46 MB , 62 pages ) May 2011
Durwood and Dauntless 2002
Amerada Hess
-
-
-
Hutton 2002
Kerr McGee
-
-
July 2004
Camelot CB 2001
ExxonMobil
-
-
-
Blenheim and Bladon 2000
Talisman
-
-
-
Durwood and Dauntless 2000
Amerada Hess
-
-
-
Maureen and Moira 2000
Phillips
-
-
-
Brent Spar 1998
Shell
-
-
-
Donan 1998
BP
-
-
-
Fulmar SALM 1998
Shell
-
-
-
Emerald 1996
MSR
-
-
-
Frigg FP 1996
Elf Norge
TotalFinaElf Norge
-
-
Leman BK 1996
Shell
-
-
-
Staffa 1996
Lasmo
-
-
-
Viking AC, AD, AP & FD 1996
Conoco
-
-
-
Esmond CP & CW 1995
BHP
-
-
-
Gordon BW 1995
BHP
-
-
-
Angus 1993
Amerada Hess
-
-
-
Forbes AW 1993
Hamilton
BHP
-
-
Argyll, Duncan and Innes 1992
Hamilton
BHP
-
-
Blair 1992
Sun Oil
AGIP
-
-
Crawford 1991
Hamilton Oil
BHP
-
-
Piper Alpha 1988
Occidental
Talisman
-
-
Notification of disused pipelines
During the course of a field’s life, pipelines/sections of pipelines may be taken out of use, e.g. due to corrosion, problems with reservoir pressure, damage to the pipeline, etc. When this happens, under the Petroleum Act 1998 the Secretary of State has the option of immediately calling for a full decommissioning programme. This is not always considered an appropriate option however, and so it has been agreed consideration will be given to handling suitable pipelines, under an informal decommissioning regime, thereby deferring a formal programme until the end of the field’s life.
If a formal decommissioning programme is not immediately deemed suitable, details of the out of use pipeline(s) will be circulated to other government departments for comment. Following this, OPRED will decide one of the following:
we are content with the proposals for monitoring and maintaining the out-of-use pipeline
we request additional information or further remedial action
we request a formal decommissioning programme
The Interim Pipeline Regime is intended to ensure out of use lines do not pose a risk to other users of the sea or the environment and that they are covered by an appropriate surveying and maintenance regime from the point when they are taken out of use until approval of the formal decommissioning programme, which is usually at the end of field life. It should be noted that any interim solution should not prejudice the final decommissioning options for that line, including complete removal. The department expects operators to submit details of out of use pipelines/sections of a pipeline as soon as they are taken out of use.
Operators are reminded that any works that are proposed on any pipelines under the Pipeline Works Authorisation regime, as per their Terms and Conditions of the PWA , must have a legal consent in place before works can commence which includes but is not exclusive to any proposed decommissioning works. Consents are issued by the North Sea Transition Authority (NSTA) and operators are requested to email consents@nstauthority.co.uk on any queries that they may have relating to legal consents. Further guidance can also be found on the NSTA website .
Once the necessary legal consent has been issued by NSTA, Consents & Authorisations Section, Operators are to email a completed
IPR1 Form (MS Word Document , 63.7 KB ) to odu@energysecurity.gov.uk .
If you are an operator, aware of any out of use pipelines that have not been referred to the department, please submit a completed IPR1 Form at your earliest convenience.
Following confirmation a pipeline has been accepted under the Interim Pipeline Regime, the Offshore Decommissioning Unit will continue to monitor the condition of the pipeline by asking the Operator to confirm the status of the pipeline remains unchanged following future surveys at an agreed frequency. If you are an operator who wishes to request a change to the agreed frequency of surveys following acceptance of a pipeline into the IPR, please submit a completed
IPR2 Form (MS Word Document , 53.4 KB ) to odu@energysecurity.gov.uk . Please note that a recent survey (done that year) must have been completed before any change of survey frequency will be considered.
Further information
A list of all installations on the UKCS and their current status is available from the OSPAR Website
At the first ministerial meeting of the Commission for the Protection of the Marine Environment of the North East Atlantic (OSPAR ) in 1998, a binding decision was agreed that set rules for the disposal of offshore installations at sea. Under the decision the dumping and leaving wholly or partly in place of offshore installations is prohibited. Decision 98/3 recognises it may be difficult to remove the ‘footings’ of large steel jackets weighing more than 10,000 and concrete installations. As a result there are derogations for these categories of installations if the internationally agreed assessment and consultation process shows leaving them in place is justifiable.
OPRED has utilised decommissioning programme templates for derogation and non-derogation projects. These templates include all required content as detailed in Annex C of the guidance notes. There are also templates available which are currently being trialled for more specific and small scale decommissioning activity including rig reactivation and removal of a single Wellhead Protection Structure. Operator’s should discuss all individual cases with OPRED who will advise of the appropriate template.
A
Standard Decommissioning Programme Template (Non-Derogation Cases) (PDF , 674 KB , 33 pages ) is available - (September 2024).
A
Standard Decommissioning Programme Template (Derogation Cases) (PDF , 1.11 MB , 37 pages ) is also available (November 2018).
A word version of these templates can also be requested from OPRED . Please email odu@energysecurity.gov.uk for further details.
Cost recovery
OPRED will charge a fee in respect of offshore (oil and gas) installations and pipelines decommissioning programmes under the Petroleum Act 1998. Guidance, including the indicative fee structure, is available in
Guidance on charging a fee for offshore (oil and gas) installations and pipelines under the Petroleum Act 1998 (PDF , 308 KB , 9 pages )
Updates to this page
Published 23 January 2013
Last updated
1222 November 2024
+ show all updates
22 November 2024
Addition of new DP and associated documents
12 November 2024
New Decommissioning Programmes added to ODU website
23 October 2024
Addition of Approved Decommissioning Programme
17 October 2024
Consultation draft DPs added
9 October 2024
New Non-Derogation Template added to website
3 October 2024
Revision details added
30 September 2024
Revision to approved DP
26 September 2024
DP has been approved
20 September 2024
Approved Close Out Report added
6 September 2024
Consultation Draft DP added
30 August 2024
New DP added to website
23 August 2024
DP out for consultation
1 August 2024
Additional information added for LBA DP
1 August 2024
Approved Close Out Report added
25 July 2024
East Brae UJ DP approved
22 July 2024
Acceptance of Close out Report
22 July 2024
New Decommissioning Programme added to website for consultation
19 July 2024
Solan DP consultation
8 July 2024
A new DP is out for consultation
5 July 2024
Consultation DP added
1 July 2024
Addition of DP revisions to website
23 May 2024
Approved Close Out Report added
22 May 2024
Approved Decommissioning Programme
20 May 2024
Approved DP added
29 April 2024
New Decommissioning Programme added to website
26 April 2024
A DP has been approved
16 April 2024
Change of Operator has occurred in the Wenlock and Garrow Fields
4 April 2024
Consultation DP added
11 March 2024
Close Out Report added to Website
11 March 2024
Approved DP added
14 February 2024
Decommissioning Programme for consultation
26 January 2024
The Brae Bravo Topsides Close Out Report has been accepted and added to the website.
17 January 2024
Acceptance of Close Out Report
11 January 2024
Approved Decommissioning Programme
5 January 2024
Helvellyn - Waldorf has been moved from "under consideration" to "approved".
14 December 2023
Garrow documents added for Public Consultation.
29 November 2023
Final draft of Financial Assurance Guidance published
30 October 2023
Decommissioning Programme approved
4 October 2023
Decommissioning Programme approved
29 September 2023
Approved Decommissioning Programme
14 September 2023
A DP has been approved
14 September 2023
A DP has been approved
17 August 2023
Decommissioning Programme for consultation
14 August 2023
New DP out to consultation.
11 August 2023
ODU email address updated
12 July 2023
Decommissioning Programme out to consultation
30 June 2023
Consultation DP added
29 June 2023
Typo corrected on IPR 1
28 June 2023
Addition of new IPR forms for use
27 June 2023
Consultation DP added
20 June 2023
Consultation DP added
8 June 2023
DP approval
26 May 2023
Decommissioning Programme for consultation
12 May 2023
Decommissioning Programme for consultation
28 April 2023
East Brae UJ DP consultation commenced
21 April 2023
Consultation decommissioning programmes added
28 March 2023
DP approval
3 March 2023
Addition of Western Isles FPSO DP in programme under consideration tab
10 February 2023
Close Out Report added
8 February 2023
link to guidance update page
7 February 2023
Consultation DP added
20 January 2023
DPs withdrawn as added in error
20 January 2023
Consultation DPs added
9 January 2023
DP approval
14 December 2022
DP approval
9 December 2022
DP approved
16 November 2022
DPs have now been approved
14 November 2022
lancaster FPSO DP approved
7 November 2022
DP approval
28 October 2022
Consultation draft DP added
7 October 2022
Consultation draft DPs added
30 September 2022
Decommissioning Programme for consultation
28 September 2022
N11 COR added
21 September 2022
Notification of an approved DP
18 August 2022
DP approval
5 July 2022
Approved DPs published
7 June 2022
Brae B upper jacket DP approved
9 May 2022
Approved DP
6 May 2022
approval of foinaven FPSO DP
29 April 2022
response to consultation document for proposed changes to fee charging regime in respect of offshore oil and gas installations and pipelines published
21 April 2022
DP Approval
21 April 2022
Consultation DPs added
21 April 2022
Decommissioning programme for consultation
20 April 2022
Approval of Decommissioning Programme
7 March 2022
New DPs out to consultation
3 March 2022
wenlock DP approval re-added appears to have been deleted in error
25 February 2022
Consultation DP
23 February 2022
Approved DP
22 February 2022
Approved DP
9 February 2022
DP approval
14 January 2022
Draft programme for consultation
23 December 2021
DP approval
20 December 2021
Consultation DP added
13 December 2021
DP approved
25 November 2021
Causeway and Fionn DP consultation
10 November 2021
DP approval
25 October 2021
Decommissioning Programme for consultation
15 October 2021
Decommissioning Programmes added for Public Consultation
24 September 2021
Acceptance of Close Out Report
21 September 2021
DP Consultation
10 September 2021
COR accepted
31 August 2021
Consultation DP added
27 August 2021
ensign DP approved
26 August 2021
Consultation DP
13 August 2021
markham close out report added
6 August 2021
Consultation DP
3 August 2021
DP approval
28 July 2021
Cost recovery consultation impact assessment added
26 July 2021
DP Approval
22 July 2021
DP approval
28 June 2021
newly approved DP
18 June 2021
Decommissioning programme for consultation
7 June 2021
Consultation draft DP added
24 May 2021
Edited 'Overview' section to publish details of consultation on proposed changes to fee charging regime.
21 May 2021
interim CORs added for Banff FPSO and SAL buoy DPS
13 May 2021
approval of Gaupe DP
6 May 2021
Approval of Decommissioning Programme
21 April 2021
DP approved
16 April 2021
Adding an approved DP
9 April 2021
Consultation DP
1 April 2021
DP approved
1 April 2021
Approved Decommissioning Programme
24 March 2021
Decommissioning Programmes for consultation
22 March 2021
DP approved
16 March 2021
DP approved
11 March 2021
DP approved
26 February 2021
COR added
17 February 2021
Approved DPs added
21 January 2021
Close Out Reports Approved
17 December 2020
Adding A Decommissioning Programme which is out to Public Consultation.
15 December 2020
Consultation DPs added
7 December 2020
Consultation DP added
30 November 2020
Consultation DP added
19 November 2020
Approval of Decommissioning Programme
19 November 2020
Decommissioning Programme Approved
4 November 2020
Approval of preparatory works
16 October 2020
Consultation DP added
9 October 2020
Accepted Close Out Report added
30 September 2020
Approval of Decommissioning Programme
21 September 2020
Five new DPs out to consultation
16 September 2020
A new DP is out to public consultation
31 August 2020
draft DP added
24 July 2020
Decommissioning Programmes for consultation
23 July 2020
Approval of A DP and Derogation
10 July 2020
Draft decommissioning programme for consultation
9 July 2020
Decommissioning Programme for consultation
8 July 2020
document replaced with updated version
1 July 2020
Decommissioning Programme Approval
15 June 2020
Approved Decommissioning Programme
12 June 2020
Consultation DP added
11 June 2020
DP has been approved
11 June 2020
Decommissioning Programme for consultation
8 June 2020
A DP has been added for public consultation
4 June 2020
Approval of Decommissioning Programme
2 June 2020
Approved DP added
27 May 2020
Approval of Decommissioning Programme
25 May 2020
approval of Eider topsides DP
21 May 2020
A Decommissioning Programme has been approved
24 April 2020
consultation DP added
16 April 2020
Approval of a DP
8 April 2020
Approved DP
31 March 2020
Approval of a DP
31 March 2020
Decommissioning Programme for consultation
30 March 2020
Approved DP
16 March 2020
Decommissioning Programme now approved
13 March 2020
Consultation DPs
10 March 2020
Decommissioning Programme for consultation
14 February 2020
CoR added to website
12 February 2020
DP approval
7 February 2020
Huntington Consultation DP added
29 January 2020
New Decommissioning Programmes out to consultation.
22 January 2020
New DP out to consultation
20 January 2020
New DP out to consultation
10 January 2020
Decommissioning Programmes for consultation
20 December 2019
Decommissioning Programme for consultation
18 December 2019
Decommissioning Programme for consultation
20 November 2019
Approved of Banff SAL Buoy DP
8 November 2019
Consultation of Cavendish Decommissioning Programme
6 November 2019
MacCulloch DP approved
1 November 2019
New approved DP
8 October 2019
Consultation of Ensign
3 October 2019
Approval of Decommissioning Programme
27 September 2019
Approval of South Morecambe DP3/DP4 Decommissioning Programmes
11 September 2019
Pickerill installations DP approved
4 September 2019
Minke DP approved
2 September 2019
Banff SAL buoy DP for consultation
22 August 2019
Addition of two approved decommissioning programmes
1 August 2019
Added the approved Juliet DP to the website
3 July 2019
PL5 approved
1 July 2019
NNP approved
1 July 2019
Decommissioning Programme for consultation
26 June 2019
Consultation of MacCulloch Field Decommissioning Programmes
25 June 2019
Revised CAs for Brae A, Brae B and East Brae
6 June 2019
Approval of Nevis N11 WHPS Decommissioning Programme
29 May 2019
Change of email to a generic one rather than a personal email.
28 May 2019
Schiehallion & Loyal Phase One Close Out Report Approved
3 May 2019
Approval of the Dunlin Alpha Topsides Decommissioning Programme
30 April 2019
Update of the content of the DP
18 April 2019
Approval of Hewett Vent Stack DP
17 April 2019
consultation closed
5 April 2019
Consultation DP and supporting documents for PL5
28 March 2019
Minke and Juliet consultation DPs published
22 March 2019
Addition of Close Out Report
14 March 2019
New Approved Programme
14 March 2019
New programme for consultation
8 March 2019
Publishing approved Curlew DP
19 February 2019
Morecambe DPs published for consultation
18 February 2019
Added a CoR
6 February 2019
Addition of Close Out Report
31 January 2019
Approved DPs for VDP2 and VDP3 added
25 January 2019
Addition of approved DPs for Tyne South Installations and Guinevere Installation
23 January 2019
Addition of approved decommissioning programme
17 January 2019
Approval of a Decommissioning Programme
21 December 2018
Addition of Brent Delta Close Out Report
14 December 2018
Addition of 2 decommissioning programmes for consultation
30 November 2018
Update decommissioning templates added
22 November 2018
Guidance document was updated and uploaded
6 November 2018
Adding Goldeneye DP for consultation.
25 October 2018
Jacky Decommissioning Programmes Approved
3 October 2018
Approval of Close out Report
15 August 2018
Approval of Decommissioning Programme
15 August 2018
VDP2 and VDP3 consultation draft Decommissioning Programmes added
6 August 2018
Approval of Brent Alpha, Bravo and Charlie Topsides Decommissioning Programme
3 August 2018
Offshore Oil and Gas Decommissioning Programme out to consultation
2 August 2018
Addition of a new decommissioning programme for consultation
20 July 2018
Tyne South and Guinevere Installation Decommissioning Programmes published for consultation
18 June 2018
Addition of Curlew DPs, CA and EIA for Public Consultation.
12 June 2018
Decommissioning Programme Approved
3 May 2018
Updated Offshore decommissioning guidance has been added
2 May 2018
Ann & Alison, Saturn (Annabel) and Audrey DPs have been approved
16 April 2018
Changed document to final version
16 April 2018
A decommissioning programme has been approved
23 March 2018
Approved Markham DP
23 March 2018
Bains Documents Added
9 March 2018
Updated Environmental Guidance on Decommissioning
6 March 2018
Jacky DP Consultation
12 January 2018
Draft Consultation Decommissioning Programme uploaded
21 December 2017
Updated guidance for Offshore Decommissioning on website for feedback
15 December 2017
Addition of approved DPs
4 December 2017
Approved DPs added
6 September 2017
Saturn Annabel, Audrey and LDP1 Programmes for public consultation
27 July 2017
DPN form corrected
5 July 2017
generic email address added and DPN form updated (with generic email address)
30 June 2017
Ann and Alison DP's and associated documents added for public consultation
23 June 2017
Fairfield Fagus Limited's Dunlin Fuel Gas Import and Power Import, Merlin and Osprey Decommissioning Documents uploaded
21 June 2017
Brae Area DPs and associated documents available for consultation
5 June 2017
Harding STL Close Out Report added
3 May 2017
Disused Pipeline Notification Form revised - 03 May 17
28 April 2017
Leman BH Decommissioning Programme approved
21 April 2017
Approval of Ettrick and Blackbird DP
3 March 2017
Ninian North Platform documents published for public consultation
A4 Programme approved
8 February 2017
Brent Decommissioning Programmes published for consultation
27 January 2017
IVRR Close Out Report added
8 November 2016
Ann A4 Installation Decommissioning Programme added for consultation
6 October 2016
Approved Decommissioning Programmes added
20 September 2016
Atlantic and Cromarty Draft Decommissioning Programmes Consultation
6 September 2016
references of DECC amended to BEIS (including DPN form)
15 July 2016
Janice, James & Affleck Fields - Draft programmes under consideration (added)
13 July 2016
Markham ST-1 Decommissioning Programmes - (added)
16 June 2016
Oil & Gas: Update Notification of Disused Pipelines
16 June 2016
Oil & Gas: Update Table of draft decommissioning programmes under consideration.
2 March 2016
Leadon Decommissioning Programmes - (added)
17 February 2016
Notification of Disused Pipelines form - (updated)
3 February 2016
Harding STL approved decommissioning programme - (added)
3 December 2015
Thames Area - Horne & Wren, Orwell and Wissey approved decommissioning programmes - (added)
23 November 2015
Fife, Flora, Fergus, Angus: decommissioning programme FFFA Close Out Report - (added)
2 November 2015
Thames Area – Thames Complex, Gawain & Arthur - Approved decommissioning programmes - (added)
7 October 2015
Viking Satellites CD,DD,ED,GD,HD draft decommissioning programmes under consideration - (added)
21 September 2015
Oil and Gas: Updated document for Harding STL Decommissioning Programme
18 September 2015
Oil and Gas: Updated “Table of approved decommissioning programmes” table.
6 August 2015
Leman BH draft decommissioning programme - (added)
3 July 2015
Oil and Gas: Addition of Brent field to approved decommissioning programme
29 May 2015
Oil and gas: Rose approved decommissioning programme - (added)
20 May 2015
Decommissioning - Leadon draft programme, follow up consultation - (added)
15 May 2015
Oil and gas: Stamford decommissioning programme - (added)
25 March 2015
Oil and gas: Rose Field decommissioning programmes - (added)
18 February 2015
Oil and gas: Brent – Brent Delta Topside draft decommissioning programme - (added)
3 February 2015
Oil and Gas: Addition of Stamford Field to decommissioning programmes table
9 January 2015
Oil and Gas: Updated the disused pipeline notification form
20 November 2014
Oil and gas: Decommissioning - Streamlined Decommissioning Programme Template (Derogation Cases) - (added)
6 November 2014
Oil and gas: NW Hutton close out report - (added)
16 October 2014
Oil and gas: Decommissioning draft prgrams - Thames - (added)
13 October 2014
Oil and gas: Indefatigable (Shell) close out report - (added)
8 August 2014
Oil and gas: Streamlined Decommissioning Programme Template (Non-Derogation Cases) - (updated)
4 August 2014
Oil and gas: Murchison approved decommissioning programme - (added)
5 March 2014
Oil and gas: Rubie & Renee - Approved decommissioning programme - (added)
14 February 2014
Oil and gas: Decommisiioning Linhe close out report - (added)
27 January 2014
Oil and gas: Streamlined Decommissioning Programme Template (Non Derogation Cases) - updated
27 January 2014
Oil and gas: Leadon Draft Decommissioning Programme - added
10 December 2013
Oil and gas: Miller decommissioning programme - (added)
19 November 2013
Oil and gas: Rubie/Renee Draft Decommissioning Programme - (added)
13 September 2013
Camelot close out report - added
3 June 2013
Added Murchison draft decommissioning programme
28 January 2013
Added streamlined decommissioning programme template
23 January 2013
Re-created table, added H2's and anchors
23 January 2013
First published.