Change of https://www.gov.uk/guidance/oil-and-gas-decommissioning-of-offshore-installations-and-pipelines

Change description : 2026-06-02 13:42:00: Approval of DP [Guidance and regulation]

Showing diff : 2026-05-22 07:00:01.371138525 +00:00..2026-06-02 12:42:14.770415499 +00:00

Guidance

Oil & Gas: decommissioning of offshore installations & pipelines

Decommissioning programmes, including dates, locations, installations decommissioned, method of decommissioning and close-out reports where available.

Overview

The decommissioning of offshore oil and gas installations and pipelines on the United Kingdom Continental Shelf (UKCS) is controlled through the Petroleum Act 1998.

The responsibility for ensuring that the requirements of the Petroleum Act 1998 are complied with rests with the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) which sits within the Department for Business, Energy and Industrial Strategy.

Owners of oil and gas installations and pipelines are required to decommission their offshore infrastructure at the end of a field’s economic life and the 1998 Act requires owners to set out the measures to decommission disused installations and/or pipelines in a decommissioning programme.

A decommissioning programme must identify all the items of equipment, infrastructure and materials that have been installed or drilled and describe the decommissioning solution for each.

OPRED aims to be transparent in its consideration of decommissioning programmes. As a result members of the public, other organisations, non-governmental organisations and other government departments or agencies are invited to comment on the proposals set out in a programme.

Details of the current programmes under consideration are noted in the table below.

OPRED provides guidance on the regulatory requirements for decommissioning. Final guidance on the Environmental Considerations for Decommissioning (Section 12) has now been incorporated into the guidance notes Offshore Oil and Gas Decommissioning Guidance Notes November 2018 (PDF, 1.27 MB, 138 pages). Please see Updates to Offshore Oil and Gas Decommissioning Guidance

Financial Assurance Guidance for the Decommissioning of Offshore Oil and Gas Installations and Pipelines. Financial Assurance Guidance (PDF, 278 KB, 17 pages)

The guidance outlines how the government assesses the financial capability of persons with a relevant interest in or considering taking an interest in an offshore oil or gas field. For the purposes of satisfying the Secretary of State that that person will be capable of carrying out a decommissioning programme in relation to that interest.

It explains our financial assurance policy and existing processes setting out the steps taken to assess the financial health of offshore oil and gas companies with an interest or potential interest in a field, outlining how and when we may use the statutory powers set out in the Petroleum Act 1998.

If you have any comments or questions relevant to the guidance, please email us at odu@energysecurity.gov.uk.

Proposed changes to charging a fee in respect of decommissioning offshore (oil and gas) installations and pipelines under the Petroleum Act 1998 as amended by the Energy Act 2008 and the Energy Act 2023

In 2021 the Government consulted on the proposed change to the method for calculating charges to industry for work undertaken by OPRED in connection to the Secretary of State’s functions under Part IV of the Petroleum Act 1998 (PA 1998). These changes were enabled by amendments to the PA 1998 made by the Energy Act 2023, and require further, secondary legislation (regulations) to bring into force. The aim of this consultation was to formally seek views from stakeholders such as offshore oil and gas operators, companies with an interest in decommissioning offshore oil and gas installations and pipelines, and other interested parties. Fees consultation document - May 2021 (PDF, 224 KB, 19 pages) Offshore oil and gas cost recovery consultation impact assessment (PDF, 247 KB, 11 pages) Response to consultation document - April 2022 (PDF, 189 KB, 12 pages)

As part of the process for making the new legislation OPRED consulted on draft regulations and draft guidance explaining how the new charging regime will work in practice, and also consulted on new hourly rates to calculate the fees recovered from industry. These consultations are now closed, and the government response can be found here: Government Response - Joint Consultation on Decommissioning Charging Regulations and OPRED Fee Rates (PDF, 265 KB, 20 pages)

Copies of the consultation documents can be found here: OPRED Decommissioning Charging Regulations 2026 Consultation Document (PDF, 194 KB, 13 pages) OPRED Fee Rates Consultation 2026 (PDF, 209 KB, 15 pages)

If you have any questions regarding the proposed changes, please direct these to odu@energysecurity.gov.uk.

Draft decommissioning programmes under consideration

Decommissioning Programme Operator Main Points of DP Documents
Brae Alpha Upper Jacket TAQA Bratani Limited The Brae Alpha Upper Jacket and pipeline risers will be recovered to shore for recycling or disposal.  Brae Alpha Upper Jacket DP (PDF, 1.45 MB, 60 pages)
Otter Subsea Facilities & Pipelines TAQA Bratani Limited Subsea installations, surface laid pipelines, spools, jumpers and umbilicals to be recovered to shore for re-use or recycling. Trenched and buried pipelines to be left in situ. Protection/stabilisation features will be recovered to shore. Otter - Consultation DP (PDF, 1.34 MB, 50 pages) Otter EA (PDF, 4.2 MB, 135 pages) Otter CA (PDF, 5.66 MB, 255 pages)
Orlando Field Serica Energy Chinook Limited Subsea installations, one surface laid pipeline and one umbilical will be recovered to shore for re-use or recycling. Protection/stabilisation features will be recovered to shore. All piles will be cut to a target depth of 3m below the average natural seabed level. Orlando Field DP (PDF, 3.21 MB, 54 pages) Orlando Field CA (PDF, 5.54 MB, 35 pages) Orlando Field EA (PDF, 20.9 MB, 97 pages)
Rough Alpha Installation and Risers Centrica Energy Storage Limited Topsides, Jackets and bridge link to be removed to shore for reuse/recycling or disposal. The risers will be removed and returned to shore for recycling. Rough Alpha Installation inc Risers DP (MS Word Document, 3.05 MB) Rough Alpha Installation EA (MS Word Document, 9.54 MB)
Brae Alpha Topsides, Central Brae, West Brae and Sedgwick TAQA Bratani Limited Topsides, subsea installations, surface laid pipelines and umbilicals to be recovered to shore for recycling or disposal.  Trenched or buried pipelines and umbilicals to be left in situ.  Protection/stabilisation features will be recovered to shore. Brae Alpha Topsides Central Brae West Brae and Sedgwick DP (PDF, 2.44 MB, 107 pages) Brae Area EA (PDF, 2.28 MB, 57 pages) Brae Area CA (PDF, 3.61 MB, 100 pages)
South Magnus and Magnus Swift Wellheads and Xmas Trees DP EnQuest Heather Limited Xmas Trees and Wellheads to be removed to shore for reuse, recycling or disposal. South Magnus and Magnus Swift DP (PDF, 2.27 MB, 41 pages)
Leman SW 53/02a-15Y WHPS DP Perenco UK Limited WHPS and associated stabilisation material to be removed to shore for reuse, recycling or disposal. Pipeline ends will be cut and recovered to shore for reuse, recycling or disposal alongside associated stabilisation features. Leman SW 53/02a-15Y WHPS DP (PDF, 1.15 MB, 40 pages)
Inde 23AC and AQ Installations, bridges and risers Perenco UK Limited Topsides, Jackets and bridges to be removed to shore for reuse/recycling or disposal. The risers will be removed and returned to shore for recycling. Inde 23AC and AQ Installations, bridges and risers DP (PDF, 1.45 MB, 46 pages) Inde 23AC and AQ Installations, bridges and risers EA (PDF, 5.55 MB, 116 pages)
Miller Infield Pipelines BP Exploration (Alpha) Limited Surface laid concrete coated export pipeline will be trenched and buried; trenched and rock covered gas import pipeline will be decommissioned in situ with surface laid ends removed; Surface laid umbilical will be recovered to shore. Pipeline structures to be recovered to shore for re-use or recycling. Miller Infield Pipelines DP (PDF, 3.51 MB, 38 pages) Miller Infield Pipelines EA (PDF, 7.17 MB, 110 pages) Miller Infield Pipelines CA (PDF, 4.41 MB, 67 pages)
Atlantic and Cromarty Part 1 Shell Global LNG Limited Manifold and WHPS to be removed for recycling/disposal. Surface laid pipelines recovered to shore for recycling/disposal. Trenched and buried pipelines and associated protection/stabilisation features to be left in situ. Atlantic and Cromarty DP (PDF, 2.65 MB, 67 pages) Atlantic and Cromarty EA (PDF, 5.27 MB, 129 pages) Atlantic and Cromarty CA (PDF, 2.98 MB, 67 pages)
Inde 18A Jackets, Bridges and Riser DP Perenco UK Limited Jackets, bridges and riser to be removed to shore for reuse, recycling or disposal Inde 18A Jackets, Bridges and Riser DP (PDF, 1.73 MB, 42 pages) Inde 18A Jackets, Bridges and Riser EA (PDF, 4.68 MB, 108 pages)
Cladhan Subsea Facilities Taqa Bratani Limited Subsea installations, surface laid pipelines and umbilicals to be recovered to shore for re-use or recycling. Buried pipelines to be left in situ. Protection/stabilisation features will be recovered to shore. Cladhan DP (PDF, 1.32 MB, 45 pages) Tern Subsea EA (PDF, 6.79 MB, 196 pages) Tern Subsea CA (PDF, 11.8 MB, 255 pages)
Hudson Subsea Facilities Taqa Bratani Limited Subsea installations, surface laid pipelines and umbilicals to be recovered to shore for re-use or recycling. Buried pipelines to be left in situ. Protection/stabilisation features will be recovered to shore. Hudson DP (PDF, 1.81 MB, 60 pages) Tern Subsea EA (PDF, 6.79 MB, 196 pages) Tern Subsea CA (PDF, 11.8 MB, 255 pages)
Kestrel and Falcon Subsea Facilities Taqa Bratani Limited Subsea installations, surface laid pipelines and umbilicals to be recovered to shore for re-use or recycling. Buried pipelines to be left in situ. Protection/stabilisation features will be recovered to shore. Kestrel_Falcon DP (PDF, 1.41 MB, 52 pages) Tern Subsea EA (PDF, 6.79 MB, 196 pages) Tern Subsea CA (PDF, 11.8 MB, 255 pages)
Tern Upper Jacket TAQA Bratani Limited The Tern Upper Jacket and pipeline risers will be cut to a depth of approximately 132m below lowest astronomical tide and recovered to shore for recycling or disposal. Tern Upper Jacket - DP (PDF, 3.98 MB, 50 pages) Tern Upper Jacket - EA (PDF, 9.17 MB, 99 pages)
North Cormorant Upper JacketTAQA Bratani LimitedThe North Cormorant Upper Jacket and pipeline risers will be cut to a depth of approximately 116m below lowest astronomical tide and recovered to shore for recycling or disposal. North Cormorant Upper Jacket - DP (PDF, 3.52 MB, 48 pages) North Cormorant Upper Jacket - EA (PDF, 8.05 MB, 102 pages)
Dunlin Alpha Fairfield Betula Limited Decommissioning in situ of Dunlin Alpha concrete gravity based structure and storage cells. Dunlin Alpha Decommissioning Programme (PDF, 6.5 MB, 77 pages) Dunlin Alpha Decommissioning Comparative Assessment Report (PDF, 3.66 MB, 133 pages) Dunlin Alpha Decommissioning Environmental Appraisal (PDF, 6.58 MB, 176 pages)
Brae Alpha, Brae Bravo, Central Brae, West Brae and Sedgwick Marathon Oil UK LLC Removal of Brae Alpha and Brae Bravo jackets to the top of the footings. Removal of Central Brae, West Brae and Sedgwick subsea installations. Pipelines to be decommissioned in a variety of ways including removal, trenching and leave in situ. Brae Alpha, Brae Bravo, Central Brae, West Brae and Sedgwick Decommissioning Programmes (PDF, 15.3 MB, 120 pages) Brae A etc, Environmental Statement – Main Report (PDF, 14.6 MB, 80 pages) Brae A etc. Environmental Statement - Technical Appendices (PDF, 13.3 MB, 96 pages) Brae A Substructure Comparative Assessment (PDF, 1.7 MB, 30 pages) Brae B Substructure Comparative Assessment (PDF, 1.59 MB, 30 pages) Brae Area Subsea Assets Comparative Assessment (PDF, 6.84 MB, 43 pages)
Brent Shell U.K. Limited Decommissioning in situ of Brent Bravo, Charlie and Delta concrete gravity based structures. Brent Decommissioning Programme (PDF, 12 MB, 322 pages) Brent ES (PDF, 12.5 MB, 475 pages) Brent EIA (PDF, 5.05 MB, 429 pages) Brent ES Appendix (PDF, 2.52 MB, 45 pages) A suite of detailed Technical Documents which support the Decommissioning Programmes documents are available on the Shell Website

Approved decommissioning programmes

Decommissioning Programme and Approval Date Operator at approval Operator following licence / company change Revision Details and Approval Date Close out report and Date Accepted
Final - North Cormorant Upper Jacket and Associated Riser Sections DP (PDF, 2.61 MB, 58 pages) North Cormorant Upper Jacket and Associated Riser Sections EA (PDF, 7.19 MB, 101 pages) May 2026Taqa Bratani Limited-          -          -           
Pelican Final DP (PDF, 2.37 MB, 88 pages) Pelican Subsea CA (PDF, 5.66 MB, 255 pages) Pelican subsea EA (PDF, 6.71 MB, 164 pages) May 2026 Taqa Bratani Limited -           -           -            
Trees DP (PDF, 4.77 MB, 71 pages) Trees EA (PDF, 7.7 MB, 107 pages) Trees CA (PDF, 4.73 MB, 68 pages) April 2026 Spirit Energy North Sea Oil Limited -           -           -            
Leman 27J Jacket and PL207 DP (PDF, 1.97 MB, 49 pages) Leman 27J Jacket and PL207 EA (PDF, 6.51 MB, 117 pages) March 2026 Perenco UK Limited -           -           -            
GPIII FPSO Sailaway and Disconnection of Risers and Pipelines (PDF, 6.2 MB, 60 pages) March 2026 NEO Energy Production UK Limited -           -           -            
Ravenspurn GCD Topside DP (PDF, 2.86 MB, 65 pages) February 2026 Perenco UK Limited -           -           -            
Gannet A Mast DP (PDF, 2.23 MB, 37 pages) February 2026 UK North Sea Limited. DP submitted by Shell U.K. Limited -           -           -            
Ninian Southern Topsides Upper Jacket and Associated Riser Sections DP (PDF, 8.44 MB, 91 pages) February 2026 CNR International (U.K.) Limited -           -           -            
Alba Northern Platform Topsides DP (PDF, 6.92 MB, 59 pages) January 2026 Ithaca Oil and Gas Limited -           -           -            
Tyne Field Pipeline DP (PDF, 4.77 MB, 54 pages) Tyne Field Pipelines CA (PDF, 2.46 MB, 65 pages) Tyne Pipelines EA (PDF, 9.55 MB, 144 pages) December 2025 Perenco UK Limited -           -           -            
Grove G5 WHPS DP (PDF, 2.76 MB, 45 pages) December 2025 Spirit Energy Resources Limited -           -           -            
Pickerill Alpha and Bravo Riser Sections DP (PDF, 1.56 MB, 38 pages) December 2025 Perenco Gas (UK) Limited -           -           -            
Nelson Derrick DP (PDF, 2.54 MB, 40 pages) October 2025 Enterprise Oil Limited Adura Operations Limited -           -            
Pierce WI Wells DP (PDF, 1.53 MB, 27 pages) October 2025 Enterprise Oil Limited Adura Operations Limited -           -            
Stella FPF-1, Moorings and Riser Systems DP (PDF, 9.34 MB, 83 pages) Stella FPF-1, Moorings and Riser Systems CA (PDF, 1.74 MB, 26 pages) September 2025 Ithaca Energy (U.K.) Limited -           -           -            
Alba FSU DP (PDF, 5.58 MB, 60 pages) Alba FSU CA (PDF, 1.64 MB, 27 pages) September 2025 Ithaca Oil and Gas Limited -           1. Change of parties to the approved Programme April 2026           -            
Trent Topsides and Risers DP (PDF, 1.57 MB, 46 pages) September 2025 Perenco UK Limited -           -           -            
Gannet Subsea Wells GB01 and GF01 - Final DP (PDF, 1.08 MB, 25 pages) September 2025 Shell U.K. Limited Adura Operations Limited -           -            
Gryphon Alpha FPSO and Riser Disconnection DP (PDF, 5.83 MB, 79 pages) September 2025 TotalEnergies E&P North Sea UK Limited -           -           -            
Amethyst Jackets and Risers DP (PDF, 2.04 MB, 56 pages) Amethyst Jackets and Risers EA (PDF, 6.02 MB, 113 pages) August 2025 Perenco UK Limited -           -           -            
Calder, Dalton & Millom (EIS) DP (PDF, 8.23 MB, 90 pages) EIS CA (PDF, 12 MB, 119 pages) EIS EA (PDF, 9.31 MB, 231 pages) August 2025 Chrysaor Resources (Irish Sea) Limited -           -           -            
Davy North and Davy East Subsea Installations DP (PDF, 2.05 MB, 45 pages) Davy North and Davy East Subsea Installations EA (PDF, 6.62 MB, 109 pages) July 2025 Perenco UK Limited -           -           -            
Thistle Pipelines & SALM Base DP (PDF, 7.87 MB, 67 pages) Combined Thistle & Don Pipelines CA (PDF, 9.03 MB, 123 pages) Combined Thistle & Don Pipelines EA (PDF, 6.76 MB, 152 pages) July 2025 EnQuest Heather Limited -           -           -            
Thistle Upper Jacket and Associated Risers DP (PDF, 4.96 MB, 70 pages) July 2025 EnQuest Heather Limited -           -           -            
Burghley DP (PDF, 1.74 MB, 55 pages) Beauly and Burghley CA (PDF, 3.08 MB, 74 pages) Beauly and Burghley EA (PDF, 20 MB, 99 pages) June 2025 Repsol North Sea Limited NEO Energy North Sea Limited -           -            
Beauly DP (PDF, 1.85 MB, 49 pages) Beauly and Burghley CA (PDF, 3.08 MB, 74 pages) Beauly and Burghley EA (PDF, 20 MB, 99 pages) June 2025 Repsol North Sea Limited NEO Energy North Sea Limited -           -            
Galahad DP (PDF, 1.71 MB, 49 pages) Galahad EA (PDF, 3.35 MB, 71 pages) June 2025 Perenco Gas (UK) Limited -           -           -            
Seven Seas WHPS DP (PDF, 1.59 MB, 31 pages) June 2025 Spirit Energy Resources Limited -           -           -            
Don Pipelines in Thistle 500m Safety Zone DP (PDF, 4.09 MB, 45 pages) Final EA (PDF, 6.76 MB, 152 pages) Don Comparative Assessment (PDF, 8.88 MB, 123 pages) May 2025 Britoil Limited -           -           -            
Wingate DP (PDF, 6.27 MB, 59 pages) Wingate EA (PDF, 28.9 MB, 107 pages) Wingate CA (PDF, 4.17 MB, 42 pages) Wingate Pipeline Survey (PDF, 1.33 MB, 10 pages) May 2025 Wintershall Noordzee B.V. -           -           -            
LBA DP (MS Word Document, 6.49 MB) LBA CA (MS Word Document, 4.97 MB) LBA EA (MS Word Document, 18.1 MB) May 2025 Eni UK Limited -           -           -            
Kilmar DP (PDF, 5.35 MB, 54 pages) Kilmar CA (PDF, 5.2 MB, 43 pages) Kilmar EA (PDF, 8.66 MB, 110 pages) May 2025 Energean UK Ltd -           1. Change of parties to the approved Programmes June 2025           -           
Garrow DP. (PDF, 6.64 MB, 53 pages) Garrow CA. (PDF, 3.35 MB, 36 pages) Garrow EA. (PDF, 8.07 MB, 105 pages) April 2025 Energean UK Ltd -           1. Change of parties to the approved Programmes May 2025         -            
Eider DP (PDF, 5.29 MB, 52 pages) Eider EA (PDF, 8.17 MB, 99 pages) March 2025 TAQA Bratani Limited -           -           -            
Solan DP (PDF, 8.36 MB, 87 pages) Solan CA (PDF, 6.19 MB, 65 pages) Solan EA (PDF, 6.97 MB, 133 pages) March 2025 Premier Oil UK Limited -           -           -            
Otter Hatches DP (PDF, 2.07 MB, 38 pages) January 2025 TAQA Bratani Limited -           -           Otter Hatches COR (PDF, 2.15 MB, 30 pages) October 2025  
Guinevere Pipelines DP (PDF, 3.72 MB, 47 pages) Guinevere Pipelines EA (PDF, 4.3 MB, 103 pages) Guinevere Pipelines CA (PDF, 2.71 MB, 63 pages) October 2024 Perenco Gas (UK) Limited -           -           Guinevere Close Out Report (PDF, 1.96 MB, 45 pages) November 2025  
Durango DP (PDF, 1.35 MB, 38 pages) Durango EA (PDF, 3.77 MB, 82 pages) September 2024 Perenco North Sea Limited -           -           -            
East Brae Upper Jacket (PDF, 1.96 MB, 50 pages) July 2024 TAQA Bratani Limited -           1. Change of parties to the approved Programmes October 2024 -            
Knarr Gas Pipeline (KGP) Final DP (PDF, 2.49 MB, 56 pages) Knarr Gas Pipeline (KGP) Final CA (PDF, 1.83 MB, 48 pages) Knarr Gas Pipeline (KGP) Final EA (PDF, 3.12 MB, 74 pages) May 2024 Gassco AS -           -           Knarr Gas Pipeline Close Out Report (PDF, 877 KB, 12 pages) July 2025  
Rochelle WHPS and Jumper DPs (PDF, 2.87 MB, 41 pages) May 2024 CNOOC Petroleum Europe Limited -           -           -            
Leman 27H + 27J Topsides DP (PDF, 3.36 MB, 80 pages) April 2024 Perenco UK Limited -           -           -            
Trees Protection Cages (Birch, Larch and Sycamore) DP (PDF, 2.59 MB, 38 pages) February 2024 Spirit Energy North Sea Oil Limited -           -           Trees Protection Cages Close Out Report (PDF, 1.11 MB, 15 pages) May 2026  
Leman F & G DP (PDF, 9.92 MB, 86 pages) Leman F & G CA (PDF, 9.5 MB, 63 pages) Leman F & G EA (PDF, 15.1 MB, 165 pages) January 2024 Shell U.K. Limited -           -           -            
Helvellyn CA (PDF, 9.84 MB, 46 pages) Helvellyn EA (PDF, 7.37 MB, 101 pages) Helvellyn DP (PDF, 4.75 MB, 44 pages) January 2024 Waldorf Petroleum Resources Limited -           -           -            
Western Isles Subsea Final DP (PDF, 9.34 MB, 75 pages) Western Isles Subsea EA Final (PDF, 7.1 MB, 141 pages) Western Isles Subsea CA Final (PDF, 5.49 MB, 74 pages) October 2023 Dana Petroleum (E&P) Limited -           1. Change of parties to the approved Programme September 2024  -            
Devenick (PDF, 2.24 MB, 54 pages) Devenick CA (PDF, 2.02 MB, 58 pages) Devenick EA (PDF, 6.14 MB, 127 pages) October 2023 Taqa Bratani Limited -           -           -            
Western Isles FPSO DP (PDF, 5.78 MB, 65 pages) September 2023 Dana Petroleum (E&P) Limited -           1. Change of parties to the approved Programme September 2024    -            
Heather Pipelines DP (PDF, 4.22 MB, 56 pages) Heather Pipelines CA (PDF, 5.35 MB, 72 pages) Heather Pipelines EA (PDF, 6.78 MB, 117 pages) September 2023 EnQuest Heather Limited -           -           -            
Brent PLU6294 DP (PDF, 1.08 MB, 37 pages) September 2023 Shell U.K. Limited -           -           -            
Chestnut Phase 2 DP (PDF, 5.6 MB, 57 pages) Chestnut Phase 2 EA (PDF, 7.97 MB, 104 pages) Chestnut Phase 2 CA (PDF, 4.42 MB, 67 pages) June 2023 Spirit Energy North Sea Oil Limited -           -           -            
Heather Upper Jacket DP (PDF, 3.24 MB, 41 pages) March 2023 EnQuest Heather Limited -           -           -            
Saltire A Topsides and Saltire Area Subsea Infrastructure DPs (PDF, 7.37 MB, 69 pages) Saltire EA (PDF, 7.09 MB, 109 pages) Saltire CA (PDF, 4.61 MB, 111 pages) December 2022 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited -           -            
Causeway & Fionn DP (PDF, 4.56 MB, 64 pages) Causeway & Fionn EA (PDF, 6.78 MB, 94 pages) Causeway & Fionn CA (PDF, 2.03 MB, 41 pages) December 2022 Ithaca Energy (UK) Limited -           -           -            
Johnston DP (PDF, 2.18 MB, 43 pages) Johnston EA (PDF, 5.25 MB, 121 pages) Johnston CA (PDF, 1.64 MB, 62 pages) December 2022 Premier Oil E&P UK EU Limited -           -           -            
Duart DP (PDF, 11.2 MB, 55 pages) Tartan Subsea EA (PDF, 36.4 MB, 137 pages) Tartan Subsea CA (PDF, 5.5 MB, 135 pages) November 2022 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited -           -            
Tartan N Terrace (TNT) & Tartan Satellite (TS) Subsea DPs (PDF, 4.07 MB, 72 pages) Tartan Subsea EA (PDF, 36.4 MB, 137 pages) Tartan Subsea CA (PDF, 5.5 MB, 135 pages) November 2022 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited -           -            
Tartan Topsides DP (PDF, 8.28 MB, 46 pages) Tartan Subsea EA (PDF, 36.4 MB, 137 pages) November 2022 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited -           -            
Lancaster Field Floating Production Storage and Offloading Vessel (FPSO) Decommissioning Programme (PDF, 2.51 MB, 37 pages) November 2022 Hurricane Energy PLC -           -           -            
Hewett Area Subsea Installations DP (PDF, 4.45 MB, 54 pages) Hewett Area Subsea Installations EA (PDF, 14.8 MB, 150 pages) November 2022 Eni UK Limited -           1. Include mattresses and grout bags into the DP  February 2025 -            
Scoter and Merganser DP (PDF, 4.63 MB, 92 pages) Scoter and Merganser CA (PDF, 1.94 MB, 47 pages) Scoter and Merganser EA (PDF, 6.4 MB, 130 pages) September 2022 Shell UK Limited -           -           -            
Sean DP (PDF, 5.05 MB, 64 pages) Sean CA (PDF, 2.8 MB, 110 pages) Sean EA (PDF, 9.44 MB, 171 pages) August 2022 ONE-Dyas UK Limited -           -           -            
Caister CDP1b (PDF, 5.96 MB, 56 pages) CMS Area EA (PDF, 10.4 MB, 171 pages) CMS Area CA (PDF, 13.5 MB, 145 pages) July 2022 Chrysaor Production (U.K.) Limited -           -           -            
Caister-Murdoch System CDP2 (PDF, 15.7 MB, 131 pages) CMS Area EA (PDF, 10.4 MB, 171 pages) CMS Area CA (PDF, 13.5 MB, 145 pages) July 2022 Chrysaor Production (U.K.) Limited -           -           -            
Murdoch CDP3 (PDF, 8.53 MB, 83 pages) CMS Area EA (PDF, 10.4 MB, 171 pages) CMS Area CA (PDF, 13.5 MB, 145 pages) July 2022 Chrysaor Production (U.K.) Limited -           -           -            
Brae Bravo Upper Jacket Decommissioning Programme (PDF, 1.76 MB, 41 pages) June 2022 TAQA Bratani Limited -           -           -            
LOGGS Saturn Satellites LDP2 (PDF, 20 MB, 90 pages) LOGGS LDP2 - LDP5 Comparative Assessment (PDF, 3.21 MB, 203 pages) LOGGS LDP2 - LDP5 EA (PDF, 7.5 MB, 181 pages) June 2022 Chrysaor Production (U.K.) Limited -           -           -            
Foinaven FPSO Offstation DP (PDF, 3.76 MB, 60 pages) May 2022 Britoil Limited -           -           -            
LOGGS V-Fields LDP4 (PDF, 20.8 MB, 83 pages) LOGGS LDP2 - LDP5 Comparative Assessment (PDF, 3.21 MB, 203 pages) LOGGS LDP2 - LDP5 EA (PDF, 7.5 MB, 181 pages) April 2022 Chrysaor Production (U.K.) Limited -           -           -                
Hummingbird Spirit FPSO Sail away and Chestnut Riser Disconnection (PDF, 2.96 MB, 47 pages) March 2022 Spirit Energy North Sea Oil Limited -           -           Hummingbird Spirit FPSO and Riser Disconnect Close Out Report (PDF, 4.25 MB, 39 pages) July 2025       
Victoria DP (PDF, 2.54 MB, 42 pages) Victoria CA (PDF, 1.81 MB, 48 pages) Victoria EA (PDF, 18.4 MB, 158 pages) April 2022 NEO Energy (SNS) Limited -           -           -            
Wenlock DP (PDF, 4.72 MB, 51 pages) Wenlock CA (PDF, 3.84 MB, 44 pages) Wenlock EA (PDF, 6.74 MB, 119 pages) February 2022 Alpha Petroleum Resources Limited Energean UK Ltd -           -            
Cormorant Alpha Topsides DP (PDF, 3.91 MB, 81 pages) Cormorant Alpha Topsides EA (PDF, 8.21 MB, 117 pages) February 2022 TAQA Bratani Limited -           -           -             
Caledonia Decommissioning Programme (PDF, 3.1 MB, 50 pages) Caledonia Comparative Assessment (PDF, 2.04 MB, 64 pages) Caledonia Environmental Assessment (PDF, 5.56 MB, 113 pages) February 2022 Premier Oil UK Limited -           -           -            
Thistle Topsides Decommissioning Programme (PDF, 3.11 MB, 38 pages) December 2021 EnQuest Heather Limited -           -           -            
Indefatigable 18A Topsides DP (PDF, 1.29 MB, 50 pages) December 2021 Perenco UK Limited -           1. Schedule extension to 31/12/2030 March 2026           -            
Banff and Kyle Decommissioning Programmes (PDF, 3.23 MB, 71 pages) Banff and Kyle Environmental Appraisal (PDF, 7.07 MB, 114 pages) Banff and Kyle Comparative Assessment (PDF, 2.75 MB, 106 pages) November 2021 CNR International (U.K.) Limited -           -           -            
Ensign installation DP (PDF, 2.52 MB, 37 pages) Ensign Pipelines DP (PDF, 1.99 MB, 42 pages) Ensign CA (PDF, 1.67 MB, 48 pages) Ensign EA (PDF, 9.45 MB, 134 pages) August 2021 Spirit Energy North Sea Limited -           -           -            
Conrie, Don SW, W Don and Ythan Decommissioning Programmes (PDF, 7.29 MB, 88 pages) Don SW and W Don Comparative Assessment (PDF, 5.33 MB, 76 pages) Conrie, Don SW, W Don and Ythan Environmental Appraisal (PDF, 8.07 MB, 132 pages) August 2021 EnQuest Heather Limited -           1/ PLU2580JDG added to DP with decommissioning solution of full removal. January 2026           -            
Fulmar and Auk North Topsides, Subsea Facilities and Pipelines Decommissioning Programme (PDF, 3.83 MB, 78 pages) Fulmar and Auk North Subsea Infrastructure and Pipelines Comparative Assessment (PDF, 4.63 MB, 144 pages) Fulmar & Auk North Environmental Appraisal (PDF, 5.17 MB, 114 pages) July 2021 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited -           -            
Heather Topsides Decommissioning Programme (PDF, 4.07 MB, 43 pages) July 2021 EnQuest Heather Limited -           -           -            
Kingfisher Decommissioning Programme (PDF, 2.95 MB, 76 pages) Kingfisher CA (PDF, 2.19 MB, 51 pages) Kingfisher EA (PDF, 3.48 MB, 119 pages) June 2021 Shell U.K. Limited -           1. Change of parties to the approved Programme August 2021 2. Schedule Extension to 31/12/2027 and further change to parties to the approved Programme February 2025 -            
Gaupe DP (PDF, 1.86 MB, 47 pages) Gaupe CA (PDF, 1.32 MB, 51 pages) Gaupe EA (PDF, 5.77 MB, 113 pages) May 2021 A/S Norske Shell -           1. Change of parties to the approved decommissioning programme. 2. Change of decommissioning solution for PLU 2784 and PLU 2785 from leave in situ to full removal due to insufficient depth of cover. December 2024 -            
PL301 Heimdal to Brae Pipeline Decommissioning Programme (PDF, 7.71 MB, 53 pages) PL301 Heimdal to Brae Pipeline Comparative Assessment (PDF, 6.77 MB, 55 pages) PL301 Heimdal to Brae Environmental Appraisal (PDF, 9.64 MB, 114 pages) April 2021 Equinor Energy AS -           1. Extend the scope of the DP to include the entire length of PL301 situated within the UKCS. Extend the schedule to 31/12/2029. April 2022 -            
Hunter & Rita Decommissioning Programme (PDF, 2.1 MB, 44 pages) Hunter & Rita CA (PDF, 1.99 MB, 79 pages) Hunter & Rita EA (PDF, 4.96 MB, 131 pages) April 2021 Premier Oil E&P UK Limited -           -           -            
LOGGS PR, LOGGS PC, LOGGS PP, LOGGS PA, North Valiant PD, & Associated Pipelines – LDP5 (PDF, 12.2 MB, 99 pages) Chrysaor Production (U.K.) Limited April 2021 -           -           -            
Windermere DP (PDF, 1.95 MB, 41 pages) Windermere CA (PDF, 802 KB, 34 pages) Windermere ES (PDF, 7.86 MB, 231 pages) March 2021 INEOS UK SNS Limited - 1. Schedule Extension to 31/12/2025 & Change to decom solution for covering pipeline ends to use rock rather than backfill January 2024 -            
Hewett Installation DP (PDF, 5.76 MB, 69 pages) Hewett EA (PDF, 16.9 MB, 134 pages) March 2021 ENI Hewett Limited -           -              
Buchan & Hannay Decommissioning Programme (PDF, 3.33 MB, 57 pages) Buchan & Hannay CA (PDF, 3.83 MB, 91 pages) Buchan & Hannay EA (PDF, 8.29 MB, 115 pages) March 2021 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited -           -            
Huntington Decommissioning Programme (PDF, 2.52 MB, 41 pages) Huntington CA (PDF, 1.86 MB, 62 pages) Huntington EA (PDF, 5.01 MB, 127 pages) March 2021 Premier Oil E&P UK Limited -           -           -            
Northern Producer FPF and Don SW + W Don riser disconnection (PDF, 4.89 MB, 58 pages) March 2021 Submitted jointly by Qualimar Shipping Company Limited and EnQuest Heather Limited -           -           Northern Producer Close Out Report (PDF, 5.79 MB, 45 pages) July 2024  
Balmoral Decommissioning Programme (PDF, 4.27 MB, 65 pages) Balmoral Area CA (PDF, 2.56 MB, 116 pages) Balmoral Area EA (PDF, 8.03 MB, 196 pages) February 2021 Premier Oil E&P UK Limited -           -           -            
Brenda Decommissioning Programme (PDF, 1.76 MB, 47 pages) February 2021 Premier Oil E&P UK Limited -           -           -            
Glamis Decommissioning Programme (PDF, 2.53 MB, 46 pages) February 2021 Premier Oil E&P UK Limited -           -           -            
Nicol Decommissioning Programme (PDF, 1.68 MB, 45 pages) February 2021 Premier Oil E&P UK Limited -           -           -            
Stirling Decommissioning Programme (PDF, 3.13 MB, 44 pages) February 2021 Premier Oil E&P UK Limited -           -           -            
Topaz Decommissioning Programme (PDF, 2.21 MB, 31 pages) Topaz CA (PDF, 504 KB, 15 pages) Topaz EA (PDF, 1.22 MB, 37 pages) February 2021 INEOS UK SNS Limited - 1. Schedule Extension to 31/12/2025 & Change to decom solution for covering pipeline ends to use rock rather than backfill January 2024 -            
North Cormorant DP (PDF, 2.56 MB, 50 pages) North Cormorant EA (PDF, 7.26 MB, 93 pages) November 2020 TAQA Bratani Limited -           -           -            
Tern Topsides - Decommissioning Programme (PDF, 2.84 MB, 52 pages) Tern Topsides EA (PDF, 7.03 MB, 91 pages) November 2020 TAQA Bratani Limited -           -           -            
Fulmar & Auk North Preparation Work Scopes Decommissioning Programme (PDF, 1.53 MB, 35 pages) November 2020 Repsol Sinopec North Sea Limited -           -           -            
East Brae Topsides and Braemar Decommissioning Programmes (PDF, 3.88 MB, 62 pages) September 2020 RockRose UKCS8 LLC TAQA Bratani Limited -           -            
Brent Alpha Jacket (PDF, 2.82 MB, 101 pages) July 2020 Shell U.K. Limited -           -           -            
Amethyst A1D, A2D, B1D & C1D Topsides (PDF, 2.42 MB, 43 pages) July 2020 Perenco UK Limited -           -           -            
Anglia Decommissioning Programme (PDF, 2.18 MB, 61 pages) Anglia CA (PDF, 3.74 MB, 49 pages) Anglia EA (PDF, 5.83 MB, 120 pages) June 2020 Ithaca Energy UK Limited -           -           -            
Brynhild Pipelines (PDF, 1.98 MB, 50 pages) June 2020 Lundin Energy Norway AS Aker BP ASA - Brynhild Pipelines Close Out Report (PDF, 2.86 MB, 25 pages) March 2024  
Cormorant Alpha Derrick Structure Removal (PDF, 4.28 MB, 57 pages) June 2020 TAQA Bratani Limited -           -           Cormorant Alpha Derrick Structure Removal Close Out Report (PDF, 5.17 MB, 38 pages) December 2023  
Cavendish (PDF, 2.4 MB, 40 pages) June 2020 INEOS UK SNS Limited - 1. Schedule Extension to 31/12/2024 August 2022 2. Schedule Extension to 31/12/2025 & Change to decom solution for covering pipeline ends to use rock rather than backfill January 2024 -            
Banff and Kyle FPSO and FSO Float Off (PDF, 3.45 MB, 39 pages) May 2020 CNR International (U.K.) Limited -           -           Banff and Kyle FPSO and FSO Float Off Interim Close Out Report (PDF, 2.31 MB, 36 pages) May 2021  
Eider Topsides DP (PDF, 2.38 MB, 50 pages) May 2020 TAQA Bratani Limited -           -           -            
Ganymede, Europa, Callisto and NW Bell – LDP3 (PDF, 4.85 MB, 101 pages) May 2020 Chrysaor Production (U.K.) Limited -           -           -            
Ganymede ZD Topsides - LDP3b (PDF, 2.31 MB, 46 pages) April 2020 Chrysaor Production (U.K.) Limited -           -           -            
Huntington FPSO (Voyageur Spirit) (PDF, 1.19 MB, 21 pages) April 2020 Premier Oil E&P UK Limited -           -           -            
Caister - CDP1a (PDF, 2.93 MB, 49 pages) March 2020 Chrysaor Production (U.K.) Limited -           -           -            
Alma & Galia DPs (PDF, 4.34 MB, 61 pages) March 2020 EnQuest Heather Limited -           -           -            
Brent Field Pipelines (PDF, 4.05 MB, 130 pages) March 2020 Shell U.K. Limited -           -           -              
Thistle COS Tanks (PDF, 3.34 MB, 59 pages) January 2020 EnQuest Heather Limited -           -           -            
Banff SAL Buoy (PDF, 996 KB, 20 pages) November 2019 CNR International (U.K.) Limited. Decommissioning Programmes submitted by Teekay Petrojarl Floating Production UK Ltd. -           -             Banff SAL Buoy Interim Close Out Report (PDF, 1.22 MB, 12 pages) May 2021  
MacCulloch Decommissioning Programmes (PDF, 1.36 MB, 40 pages) November 2019 Chrysaor Production (U.K.) Limited -           -           -            
Goldeneye (PDF, 3.41 MB, 53 pages) November 2019 Shell U.K. Limited -           -           Goldeneye Close out Report (PDF, 1.95 MB, 35 pages) July 2024   
Brae Alpha West Drilling Rig (PDF, 2.2 MB, 24 pages) September 2019 RockRose Energy UKCS8 LLC TAQA Bratani Limited 1. Schedule Extension to 31/12/2023 January 2022 Brae Alpha West Drilling Rig Close Out Report (PDF, 1.68 MB, 24 pages) April 2024  
South Morecambe DP3/DP4 (PDF, 2.72 MB, 57 pages) September 2019 Spirit Energy Production UK Limited -           -           -            
Pickerill A&B Installations (PDF, 1.79 MB, 54 pages) September 2019 Perenco Gas (UK) Limited - 1. Schedule Extension to 31/12/2024 February 2022 2. Schedule Extension to 31/12/2027 March 2025 -                
Minke Decommissioning Programmes (PDF, 8.56 MB, 59 pages) September 2019 Neptune E&P UKCS Limited - 1. Schedule Extension to 31/12/2024 July 2021 2. Schedule Extension to 31/12/2025 April 2025 -             
Ketch (PDF, 2.65 MB, 60 pages) August 2019 DNO North Sea (ROGB) Limited - 1. Allow for installation of UKNG Viking Cable & Change in decom solution of pipelines to full removal June 2022 2. Include pipeline and fibre optic crossings into DP & Change in decom solution for pipelines remaining under rock berms & additional rock dump on pipeline ends September 2022 3. To alter the S29Holders November 2023 4. Change in decom solution of pipeline sections to leave in situ May 2024 -             
Schooner (PDF, 4.97 MB, 63 pages) August 2019 DNO North Sea (ROGB) Limited - 1. Allow for installation of UKNG Viking Cable June 2022 2. To alter the S29Holders November 2023 3. Addition of WHPS to DP and its removal & Change in decom solution of exposed pipeline sections to full removal May 2024 -            
Juliet DP (PDF, 6.16 MB, 47 pages) August 2019 Neptune E&P UKCS Limited - 1. Schedule Extension to 31/12/2024 July 2021 2. Schedule Extension to 31/12/2025 April 2025 -             
Dunlin Alpha to Cormorant Alpha Pipeline - PL5 (PDF, 4.36 MB, 73 pages) July 2019 Fairfield Betula Limited -           -           PL5 Close Out Report (PDF, 4.74 MB, 27 pages) February 2021  
Ninian Northern Platform (PDF, 2.34 MB, 70 pages) CNR International (U.K.) Limited June 2019 -           -           -            
Nevis N11 WHPS (PDF, 1.66 MB, 26 pages) June 2019 Apache Beryl I Limited -           -           Nevis N11 WHPS Close out report (PDF, 1.86 MB, 25 pages) September 2022  
Dunlin Alpha Topsides (PDF, 4.97 MB, 44 pages) May 2019 Fairfield Betula Limited -           -           Dunlin Alpha Topsides Close Out Report (PDF, 1.63 MB, 36 pages) September 2024  
Hewett Vent Stack DP (PDF, 1.5 MB, 21 pages) April 2019 Eni Hewett Limited ENI UK Limited - Hewett Vent Stack Close Out Report (PDF, 595 KB, 11 pages) September 2021  
Pickerill A & B (PDF, 1.26 MB, 21 pages) March 2019 Perenco Gas (UK) Limited -           -           -            
Curlew B, C and D (PDF, 2.4 MB, 61 pages) March 2019 Shell U.K. Limited -           1. Schedule Extension to 31/12/2026 August 2023 -            
Viking Platforms, Vixen and associated Pipelines (VDP2) (PDF, 33.3 MB, 84 pages) January 2019 ConocoPhillips (U.K.) Limited -           -           -            
Victor (VDP3) (PDF, 21.1 MB, 55 pages) January 2019 ConocoPhillips (U.K.) Limited -           -           -            
Tyne South Installations (PDF, 1.83 MB, 42 pages) January 2019 Perenco UK Limited -           -           -            
Guinevere Installation (PDF, 2.05 MB, 43 pages) January 2019 Perenco UK Limited -           -           -            
Beatrice Decommissioning Programmes (PDF, 4.45 MB, 88 pages) January 2019 Repsol Sinopec Resources UK Limited NEO Energy Resources UK Limited 1. Terminate agreement for Beatrice AD, AP, B & C reuse July 2019 -            
Bains Decommissioning Programmes (PDF, 2.57 MB, 36 pages) January 2019 Spirit Energy Production UK Limited -           -           -            
Jacky (PDF, 2.34 MB, 52 pages) October 2018 Ithaca Energy (UK) Limited -           1. Schedule Extension to 31/12/2024 and change to decom solution August 2023 2. Schedule Extension to 31/12/2030. December 2024 3. Change in decom solution to cut and remove trenched and buried sections of pipelines. April 2026 -            
Brae Bravo Topsides, Flare Bridge, Flare Tower and Flare Jacket and Substructure (PDF, 4.9 MB, 52 pages) August 2018 Marathon Oil UK LLC TAQA Bratani Limited - Brae Bravo Topsides Close Out Report (PDF, 3.29 MB, 36 pages) January 2024  
Brent Alpha, Bravo and Charlie Topsides (PDF, 3.34 MB, 81 pages) August 2018 Shell U.K. Limited -           -           -            
Stirling A33 WHPS Decommissioning Programme (PDF, 1.13 MB, 27 pages) May 2018 Premier Oil E&P UK Limited -           -           Stirling WHPS Close Out Report (PDF, 2.57 MB, 15 pages) February 2019  
Ann and Alison (PDF, 2.98 MB, 60 pages) April 2018 Spirit Energy North Sea Limited -           -           -            
Saturn (Annabel) (PDF, 2.49 MB, 47 pages) April 2018 Spirit Energy North Sea Limited -           -           -            
Audrey (PDF, 2.87 MB, 58 pages) April 2018 Spirit Energy North Sea Limited -           -           -            
Rev Decommissioning Programme (PDF, 12 MB, 42 pages) April 2018 Repsol Norge AS -           1. Schedule Extension to 31/12/2023 November 2019. 2. Schedule Extension to 31/12/2027 February 2023 -            
Markham ST-1 (PDF, 2.39 MB, 49 pages) February 2018 Centrica Production Nederland B.V. Spirit Energy Nederland B.V. - Markham ST-1 Close Out Report (PDF, 6.19 MB, 68 pages) July 2021  
Osprey (PDF, 3.92 MB, 68 pages) December 2017 Fairfield Fagus Limited -           -           Osprey Close Out Report (PDF, 1.71 MB, 34 pages) January 2021  
Merlin (PDF, 2.97 MB, 56 pages) December 2017 Fairfield Fagus Limited -           -           Merlin Close Out Report (PDF, 1.47 MB, 27 pages) January 2021  
Dunlin Fuel Gas Import (DFGI) and Dunlin Power Import (DPI) (PDF, 3.48 MB, 54 pages) December 2017 Fairfield Fagus Limited -           -           DFGI/DPI Close Out Report (PDF, 2.19 MB, 30 pages) January 2021  
Viking Satellites CD, DD, ED, GD, HD Pipelines (PDF, 6.77 MB, 32 pages) November 2017 ConocoPhillips (U.K.) Limited -           -           -            
LOGGS Satellites Vulcan UR, Viscount VO, Vampire OD - LDP1 (PDF, 17.5 MB, 61 pages) November 2017 ConocoPhillips (U.K.) Limited -           -           -            
Leman BH Decommissioning Programme (PDF, 4.66 MB, 46 pages) April 2017 Shell U.K. Limited -           -           Leman BH Close Out Report (PDF, 1.71 MB, 25 pages) March 2019  
Ettrick and Blackbird (PDF, 2.1 MB, 62 pages) March 2017 Nexen Petroleum U.K Limited CNOOC Petroleum Europe Limited 1. Schedule Extension to 31/12/2023 July 2020 2. Schedule Extension to 31/12/2025 (Ettrick Inst only) December 2022 3. Schedule Extension to 31/12/2026 August 2025 -            
Ann A4 Decommissioning Programme (PDF, 1.37 MB, 29 pages) February 2017 Centrica North Sea Limited -           -           -            
Janice James & Affleck (PDF, 3.8 MB, 115 pages) September 2016 Maersk Oil UK Limited TotalEnergies Offshore UK Limited 1. Change of parties to the approved Programmes Affleck PLs only December 2021 -            
Athena Decommissioning Programmes (PDF, 3.88 MB, 70 pages) September 2016 Ithaca Energy (UK) Limited -           1. Schedule Extension to 31/12/2023 and change of parties to the approved Programmes January 2021 -            
Viking Platforms (PDF, 3.53 MB, 40 pages) September 2016 ConocoPhillips (U.K.) Limited -           -           -            
Leadon (PDF, 1.71 MB, 53 pages) March 2016 Maersk Oil North Sea UK Limited TotalEnergies E&P UK Limited - Leadon Close Out Report (PDF, 7.78 MB, 31 pages) February 2023  
Harding STL (PDF, 2.61 MB, 73 pages) December 2015 TAQA Bratani Limited -           -           Harding STL Close-Out Report (PDF, 1.62 MB, 26 pages) June 2017  
Thames Area – Horne & Wren (PDF, 1.57 MB, 48 pages) November 2015 Tullow Oil SK Limited -           -           -            
Thames Area – Orwell (PDF, 828 KB, 42 pages) November 2015 Tullow Oil SK Limited -           -           -            
Thames Area – Wissey (PDF, 1.26 MB, 43 pages) November 2015 Tullow Oil SK Limited -           -           -            
Thames Area – Thames Complex (PDF, 15.9 MB, 76 pages) October 2015 Perenco UK Limited - 1. Removal of pipeline from the programme March 2018 2. Schedule Extension to 31/12/2023 March 2019 3. Schedule Extension to 31/12/2024 and Change in decom solution of mats to leave in situ. July 2024 Thames Complex Close Out Report (PDF, 4.27 MB, 65 pages) January 2026  
Thames Area – Gawain (PDF, 3.8 MB, 47 pages) October 2015 Perenco UK Limited - 1. Schedule Extension to 31/12/2022 March 2019 2. Schedule Extension to 31/12/2024 September 2022 3. Schedule Extension to 31/12/2027 and Change in decom solution of mats to leave in situ. August 2025 -            
Thames Area – Arthur (PDF, 4.41 MB, 46 pages) October 2015 Perenco UK Limited - 1. Schedule Extension to 31/12/2022 March 2019 2. Schedule Extension to 31/12/2024 March 2022 3. Schedule Extension to 31/12/2026 April 2025 -            
Brent - Brent Delta Topside (PDF, 3.55 MB, 72 pages) July 2015 Shell U.K. Limited -           -           Brent Delta Topside Close Out Report (PDF, 4.42 MB, 53 pages) February 2020  
Rose DP (PDF, 2.87 MB, 42 pages) May 2015 Centrica Resources Limited -           -           Rose Close Out Report (PDF, 3.31 MB, 36 pages) October 2018  
Stamford (PDF, 2.71 MB, 39 pages) April 2015 Centrica North Sea Gas Limited -           -           Stamford Close Out Report (PDF, 2.66 MB, 36 pages) February 2019  
Murchison (PDF, 2.37 MB, 70 pages) August 2014 CNR -           -           -            
Rubie & Renee (PDF, 2.47 MB, 50 pages) April 2014 Endeavour Energy UK Limited -           1. Schedule Extension to 31/12/2017 June 2016 2. Schedule Extension to 31/12/2018 November 2017 3. Schedule Extension to 31/12/2020 December 2018 Rubie Renee Decommissioning Close Out Report (PDF, 9.98 MB, 66 pages) September 2021  
Miller (PDF, 6.57 MB, 198 pages) December 2013 BP Exploration (Alpha) Limited -           1. Schedule Extension to 31/12/2024 December 2018 -            
Schiehallion & Loyal Phase One (PDF, 1.84 MB, 60 pages) April 2013 Britoil Limited -           -           Schiehallion & Loyal Phase One Close Out Report (PDF, 1010 KB, 22 pages) May 2019  
IVRR - decommissoning programme (PDF, 1.57 MB, 102 pages) February 2013 Hess Limited -           -           IVRR Close Out Report (PDF, 4.74 MB, 35 pages) December 2015  
Camelot (PDF, 488 KB, 39 pages) June 2012 Energy Resource Technology (UK) Limited -           -           Camelot Close out report (PDF, 2.27 MB, 41 pages) August 2013  
Fife, Flora, Fergus, Angus: decommissioning programme (PDF, 8.36 MB, 135 pages) February 2012 Hess Limited -           -           FFFA Close Out Report (PDF, 1.49 MB, 33 pages) December 2014  
Don (PDF, 8 MB, 175 pages) May 2011 Britoil Public Limited Company -           -           -            
Welland DP (PDF, 1.74 MB, 39 pages) September 2010 Perenco UK Limited -           -           Welland Close Out Report (PDF, 7.42 MB, 130 pages) September 2020  
Tristan NW DP (PDF, 4.11 MB, 119 pages) August 2010 Silverstone Energy Limited Bridge Energy UK Limited - Tristan NW close out report (PDF, 2.3 MB, 23 pages) January 2011  
Shelley DP (PDF, 3.23 MB, 83 pages) June 2010 Premier Oil -           -           Shelley close out report (PDF, 4.49 MB, 62 pages) February 2012  
Kittiwake Sal DP (PDF, 4.28 MB, 87 pages) June 2009 Venture North Sea Oil Limited -           -           Kittiwake Sal close out report (PDF, 588 KB, 13 pages) July 2012  
MCP-01 DP (PDF, 7.41 MB, 336 pages) September 2007 Total E&P UK Limited -           -           MCP-01 close out report (PDF, 23.1 MB, 113 pages) March 2013  
Kittiwake Buoy DP (PDF, 3.46 MB, 118 pages) May 2008 Venture North Sea Oil Limited -           1. Change of parties to the approved Programme August 2016 -            
Linnhe (PDF, 2.25 MB, 66 pages) July 2008 Mobil North Sea LLC -           -           Linnhe Close Out Report (PDF, 1000 KB, 22 pages) November 2013  
Indefatigable (Shell) (PDF, 11.6 MB, 224 pages) May 2007 Shell UK Limited -           -           Close Out Report (PDF, 2.47 MB, 64 pages) December 2014  
NW Hutton: decommissioning programme (PDF, 14.9 MB, 320 pages) February 2006 Amoco (U.K.) Exploration Company - now a subsidiary of BP plc -           -           Close Out Report (PDF, 2.52 MB, 32 pages) October 2014  
Ardmore 2005 British American Offshore Limited -           -           -            
Ardmore 2005 Ugland Nordic Shipping AS -           -           -            
Ardmore 2005 Acorn Oil & Gas Limited -           -           -            
Brent Flare DP (PDF, 2.93 MB, 122 pages) 2004 Shell -           -           Brent Flare Close out Report (PDF, 2.7 MB, 31 pages) May 2025  
Beatrice 2004 Talisman Energy (UK) Limited -           -           -            
Forbes and Gordon 2003 BHP Billiton -           -           May 2005  
Frigg DP (PDF, 10 MB, 450 pages) May 2003 Total E&P Norge AS -           -           Frigg close out report (PDF, 3.46 MB, 62 pages) May 2011  
Durwood and Dauntless 2002 Amerada Hess -           -           -            
Hutton 2002 Kerr McGee -           -           July 2004  
Camelot CB 2001 ExxonMobil -           -           -            
Blenheim and Bladon 2000 Talisman -           -           -            
Durwood and Dauntless 2000 Amerada Hess -           -           -            
Maureen and Moira 2000 Phillips -           -           -            
Brent Spar 1998 Shell -           -           -            
Donan 1998 BP -           -           -            
Fulmar SALM 1998 Shell -           -           -            
Emerald 1996 MSR -           -           -            
Frigg FP 1996 Elf Norge TotalFinaElf Norge -           -            
Leman BK 1996 Shell -           -           -            
Staffa 1996 Lasmo -           -           -            
Viking AC, AD, AP & FD 1996 Conoco -           -           -            
Esmond CP & CW 1995 BHP -           -           -            
Gordon BW 1995 BHP -           -           -            
Angus 1993 Amerada Hess -           -           -            
Forbes AW 1993 Hamilton BHP -           -            
Argyll, Duncan and Innes 1992 Hamilton BHP -           -            
Blair 1992 Sun Oil AGIP -           -            
Crawford 1991 Hamilton Oil BHP -           -            
Piper Alpha 1988 Occidental Talisman -           -            

Notification of disused pipelines

During the course of a field’s life, pipelines/sections of pipelines may be taken out of use, e.g. due to corrosion, problems with reservoir pressure, damage to the pipeline, etc. When this happens, under the Petroleum Act 1998 the Secretary of State has the option of immediately calling for a full decommissioning programme. This is not always considered an appropriate option however, and so it has been agreed consideration will be given to handling suitable pipelines, under an informal decommissioning regime, thereby deferring a formal programme until the end of the field’s life.

If a formal decommissioning programme is not immediately deemed suitable, details of the out of use pipeline(s) will be circulated to other government departments for comment. Following this, OPRED will decide one of the following:

  • we are content with the proposals for monitoring and maintaining the out-of-use pipeline
  • we request additional information or further remedial action
  • we request a formal decommissioning programme

The Interim Pipeline Regime is intended to ensure out of use lines do not pose a risk to other users of the sea or the environment and that they are covered by an appropriate surveying and maintenance regime from the point when they are taken out of use until approval of the formal decommissioning programme, which is usually at the end of field life. It should be noted that any interim solution should not prejudice the final decommissioning options for that line, including complete removal. The department expects operators to submit details of out of use pipelines/sections of a pipeline as soon as they are taken out of use.

Operators are reminded that any works that are proposed on any pipelines under the Pipeline Works Authorisation regime, as per their Terms and Conditions of the PWA, must have a legal consent in place before works can commence which includes but is not exclusive to any proposed decommissioning works. Consents are issued by the North Sea Transition Authority (NSTA) and operators are requested to email consents@nstauthority.co.uk on any queries that they may have relating to legal consents. Further guidance can also be found on the NSTA website.

Once the necessary legal consent has been issued by NSTA, Consents & Authorisations Section, Operators are to email a completed IPR1 Form (MS Word Document, 63.7 KB) to odu@energysecurity.gov.uk.

If you are an operator, aware of any out of use pipelines that have not been referred to the department, please submit a completed IPR1 Form at your earliest convenience.

Following confirmation a pipeline has been accepted under the Interim Pipeline Regime, the Offshore Decommissioning Unit will continue to monitor the condition of the pipeline by asking the Operator to confirm the status of the pipeline remains unchanged following future surveys at an agreed frequency. If you are an operator who wishes to request a change to the agreed frequency of surveys following acceptance of a pipeline into the IPR, please submit a completed IPR2 Form (MS Word Document, 53.4 KB) to odu@energysecurity.gov.uk. Please note that a recent survey (done that year) must have been completed before any change of survey frequency will be considered.

Further information

A list of all installations on the UKCS and their current status is available from the OSPAR Website

At the first ministerial meeting of the Commission for the Protection of the Marine Environment of the North East Atlantic (OSPAR) in 1998, a binding decision was agreed that set rules for the disposal of offshore installations at sea. Under the decision the dumping and leaving wholly or partly in place of offshore installations is prohibited. Decision 98/3 recognises it may be difficult to remove the ‘footings’ of large steel jackets weighing more than 10,000 and concrete installations. As a result there are derogations for these categories of installations if the internationally agreed assessment and consultation process shows leaving them in place is justifiable.

OPRED has utilised decommissioning programme templates for derogation and non-derogation projects. These templates include all required content as detailed in Annex C of the guidance notes. There are also templates available which are currently being trialled for more specific and small scale decommissioning activity including rig reactivation and removal of a single Wellhead Protection Structure. Operator’s should discuss all individual cases with OPRED who will advise of the appropriate template.

A Standard Decommissioning Programme Template (Non-Derogation Cases) (PDF, 608 KB, 33 pages) is available - (March 2025).

A Standard Decommissioning Programme Template (Derogation Cases) (PDF, 1.11 MB, 37 pages) is also available (November 2018).

A word version of these templates can also be requested from OPRED. Please email odu@energysecurity.gov.uk for further details.

Cost recovery

OPRED will charge a fee in respect of offshore (oil and gas) installations and pipelines decommissioning programmes under the Petroleum Act 1998. Guidance, including the indicative fee structure, is available in Guidance on charging a fee for offshore (oil and gas) installations and pipelines under the Petroleum Act 1998 (PDF, 308 KB, 9 pages)

Facilities

Pipeline FIR Template Pipeline FIR Template (MS Word Document, 40.3 KB)

Updates to this page

Published 23 January 2013
Last updated 222 JuneMay 2026 + show all updates
  1. Approval of DP

  2. New DP out to Consultation

  3. Approval of Decommissioning Programme

  4. New DPs out for Consultation and a Close Out Report added

  5. New DP out for Consultation

  6. A new DP out for consultation

  7. DP approval

  8. Published the government response to the consultation on OPRED’s decommissioning charging regulations and hourly rates consultations.

  9. Revision approved

  10. DP Revision Approved

  11. Revision to an Approved DP

  12. New approved DP added

  13. Pipeline FIR form added

  14. DP for consultation

  15. A DP has been approved

  16. DP has been approved

  17. New DP out to consultation

  18. DP approval

  19. Consultation - Proposed changes to the rates of fees in respect of environmental functions and decommissioning functions

  20. New approved DP

  21. New approved Close Out Report

  22. New DP added to website

  23. Revision to approved DP

  24. Consultation draft DP added

  25. New approved DP added

  26. New DP Approval

  27. Approval of Decommissioning Programme

  28. Added Consultation on OPRED Decommissioning Charging Regulations 2026

  29. New approved DP

  30. A new DP has been added to the website

  31. Consultation draft added

  32. Close Out Report added

  33. New draft DP added to website

  34. New DP Approval

  35. A new DP has been added to the website

  36. Acceptance of Close Out Report

  37. New approved DP

  38. A new DP is out for Consultation

  39. DP approval

  40. DP Approval

  41. A DP has been approved

  42. A DP has gone out to public consultation

  43. DP has been approved

  44. Approval of Decommissioning Programme

  45. Approval of Decommissioning Programme

  46. DP has been approved

  47. Revision to approved DP

  48. A DP added for Consultation

  49. New approved DP

  50. A new DP out to consultation and a DP approved

  51. Addition of new approved DP

  52. New DP out to Consultation

  53. Acceptance of Close out Report

  54. Close Out Report added to the website

  55. New draft DP under consideration

  56. DPs have been approved

  57. Addition of Decommissioning Programme under consideration.

  58. Revision to Approved Programme

  59. A DP has been approved

  60. Decommissioning Programme Approved

  61. A DP has been approved

  62. A revision to a DP date has been added

  63. Approval of DP

  64. Acceptance of Close out Report

  65. DP has been approved

  66. Addition of new DP

  67. Revisions to approved Decommissioning Programmes

  68. Draft DP approved

  69. New approved Decommissioning Programme

  70. Decommissioning Programmes for consultation

  71. Three new DPs have been added to the OPRED website.

  72. A DP Revision approval and Updated non-derogation DP Template

  73. draft decommissioning programme removed

  74. Addition of new draft programmes under consideration and approved decommissioning programme

  75. Revision details added

  76. A new DP is out to consultation.

  77. New draft Decommissioning Programme added

  78. New DPs under consideration added

  79. Addition of new approved DP

  80. Revision details and approval date added

  81. Revision details added

  82. Addition of new draft decommissioning programme

  83. Document names updated for Knarr Gas Pipeline (KGP) and Brent PLU6294

  84. Addition of two draft Decommissioning Programmes and Environmental Appraisals.

  85. Addition of new DP and associated documents

  86. New Decommissioning Programmes added to ODU website

  87. Addition of Approved Decommissioning Programme

  88. Consultation draft DPs added

  89. New Non-Derogation Template added to website

  90. Revision details added

  91. Revision to approved DP

  92. DP has been approved

  93. Approved Close Out Report added

  94. Consultation Draft DP added

  95. New DP added to website

  96. DP out for consultation

  97. Additional information added for LBA DP

  98. Approved Close Out Report added

  99. East Brae UJ DP approved

  100. Acceptance of Close out Report

  101. New Decommissioning Programme added to website for consultation

  102. Solan DP consultation

  103. A new DP is out for consultation

  104. Consultation DP added

  105. Addition of DP revisions to website

  106. Approved Close Out Report added

  107. Approved Decommissioning Programme

  108. Approved DP added

  109. New Decommissioning Programme added to website

  110. A DP has been approved

  111. Change of Operator has occurred in the Wenlock and Garrow Fields

  112. Consultation DP added

  113. Close Out Report added to Website

  114. Approved DP added

  115. Decommissioning Programme for consultation

  116. The Brae Bravo Topsides Close Out Report has been accepted and added to the website.

  117. Acceptance of Close Out Report

  118. Approved Decommissioning Programme

  119. Helvellyn - Waldorf has been moved from "under consideration" to "approved".

  120. Garrow documents added for Public Consultation.

  121. Final draft of Financial Assurance Guidance published

  122. Decommissioning Programme approved

  123. Decommissioning Programme approved

  124. Approved Decommissioning Programme

  125. A DP has been approved

  126. A DP has been approved

  127. Decommissioning Programme for consultation

  128. New DP out to consultation.

  129. ODU email address updated

  130. Decommissioning Programme out to consultation

  131. Consultation DP added

  132. Typo corrected on IPR 1

  133. Addition of new IPR forms for use

  134. Consultation DP added

  135. Consultation DP added

  136. DP approval

  137. Decommissioning Programme for consultation

  138. Decommissioning Programme for consultation

  139. East Brae UJ DP consultation commenced

  140. Consultation decommissioning programmes added

  141. DP approval

  142. Addition of Western Isles FPSO DP in programme under consideration tab

  143. Close Out Report added

  144. link to guidance update page

  145. Consultation DP added

  146. DPs withdrawn as added in error

  147. Consultation DPs added

  148. DP approval

  149. DP approval

  150. DP approved

  151. DPs have now been approved

  152. lancaster FPSO DP approved

  153. DP approval

  154. Consultation draft DP added

  155. Consultation draft DPs added

  156. Decommissioning Programme for consultation

  157. N11 COR added

  158. Notification of an approved DP

  159. DP approval

  160. Approved DPs published

  161. Brae B upper jacket DP approved

  162. Approved DP

  163. approval of foinaven FPSO DP

  164. response to consultation document for proposed changes to fee charging regime in respect of offshore oil and gas installations and pipelines published

  165. DP Approval

  166. Consultation DPs added

  167. Decommissioning programme for consultation

  168. Approval of Decommissioning Programme

  169. New DPs out to consultation

  170. wenlock DP approval re-added appears to have been deleted in error

  171. Consultation DP

  172. Approved DP

  173. Approved DP

  174. DP approval

  175. Draft programme for consultation

  176. DP approval

  177. Consultation DP added

  178. DP approved

  179. Causeway and Fionn DP consultation

  180. DP approval

  181. Decommissioning Programme for consultation

  182. Decommissioning Programmes added for Public Consultation

  183. Acceptance of Close Out Report

  184. DP Consultation

  185. COR accepted

  186. Consultation DP added

  187. ensign DP approved

  188. Consultation DP

  189. markham close out report added

  190. Consultation DP

  191. DP approval

  192. Cost recovery consultation impact assessment added

  193. DP Approval

  194. DP approval

  195. newly approved DP

  196. Decommissioning programme for consultation

  197. Consultation draft DP added

  198. Edited 'Overview' section to publish details of consultation on proposed changes to fee charging regime.

  199. interim CORs added for Banff FPSO and SAL buoy DPS

  200. approval of Gaupe DP

  201. Approval of Decommissioning Programme

  202. DP approved

  203. Adding an approved DP

  204. Consultation DP

  205. DP approved

  206. Approved Decommissioning Programme

  207. Decommissioning Programmes for consultation

  208. DP approved

  209. DP approved

  210. DP approved

  211. COR added

  212. Approved DPs added

  213. Close Out Reports Approved

  214. Adding A Decommissioning Programme which is out to Public Consultation.

  215. Consultation DPs added

  216. Consultation DP added

  217. Consultation DP added

  218. Approval of Decommissioning Programme

  219. Decommissioning Programme Approved

  220. Approval of preparatory works

  221. Consultation DP added

  222. Accepted Close Out Report added

  223. Approval of Decommissioning Programme

  224. Five new DPs out to consultation

  225. A new DP is out to public consultation

  226. draft DP added

  227. Decommissioning Programmes for consultation

  228. Approval of A DP and Derogation

  229. Draft decommissioning programme for consultation

  230. Decommissioning Programme for consultation

  231. document replaced with updated version

  232. Decommissioning Programme Approval

  233. Approved Decommissioning Programme

  234. Consultation DP added

  235. DP has been approved

  236. Decommissioning Programme for consultation

  237. A DP has been added for public consultation

  238. Approval of Decommissioning Programme

  239. Approved DP added

  240. Approval of Decommissioning Programme

  241. approval of Eider topsides DP

  242. A Decommissioning Programme has been approved

  243. consultation DP added

  244. Approval of a DP

  245. Approved DP

  246. Approval of a DP

  247. Decommissioning Programme for consultation

  248. Approved DP

  249. Decommissioning Programme now approved

  250. Consultation DPs

  251. Decommissioning Programme for consultation

  252. CoR added to website

  253. DP approval

  254. Huntington Consultation DP added

  255. New Decommissioning Programmes out to consultation.

  256. New DP out to consultation

  257. New DP out to consultation

  258. Decommissioning Programmes for consultation

  259. Decommissioning Programme for consultation

  260. Decommissioning Programme for consultation

  261. Approved of Banff SAL Buoy DP

  262. Consultation of Cavendish Decommissioning Programme

  263. MacCulloch DP approved

  264. New approved DP

  265. Consultation of Ensign

  266. Approval of Decommissioning Programme

  267. Approval of South Morecambe DP3/DP4 Decommissioning Programmes

  268. Pickerill installations DP approved

  269. Minke DP approved

  270. Banff SAL buoy DP for consultation

  271. Addition of two approved decommissioning programmes

  272. Added the approved Juliet DP to the website

  273. PL5 approved

  274. NNP approved

  275. Decommissioning Programme for consultation

  276. Consultation of MacCulloch Field Decommissioning Programmes

  277. Revised CAs for Brae A, Brae B and East Brae

  278. Approval of Nevis N11 WHPS Decommissioning Programme

  279. Change of email to a generic one rather than a personal email.

  280. Schiehallion & Loyal Phase One Close Out Report Approved

  281. Approval of the Dunlin Alpha Topsides Decommissioning Programme

  282. Update of the content of the DP

  283. Approval of Hewett Vent Stack DP

  284. consultation closed

  285. Consultation DP and supporting documents for PL5

  286. Minke and Juliet consultation DPs published

  287. Addition of Close Out Report

  288. New Approved Programme

  289. New programme for consultation

  290. Publishing approved Curlew DP

  291. Morecambe DPs published for consultation

  292. Added a CoR

  293. Addition of Close Out Report

  294. Approved DPs for VDP2 and VDP3 added

  295. Addition of approved DPs for Tyne South Installations and Guinevere Installation

  296. Addition of approved decommissioning programme

  297. Approval of a Decommissioning Programme

  298. Addition of Brent Delta Close Out Report

  299. Addition of 2 decommissioning programmes for consultation

  300. Update decommissioning templates added

  301. Guidance document was updated and uploaded

  302. Adding Goldeneye DP for consultation.

  303. Jacky Decommissioning Programmes Approved

  304. Approval of Close out Report

  305. Approval of Decommissioning Programme

  306. VDP2 and VDP3 consultation draft Decommissioning Programmes added

  307. Approval of Brent Alpha, Bravo and Charlie Topsides Decommissioning Programme

  308. Offshore Oil and Gas Decommissioning Programme out to consultation

  309. Addition of a new decommissioning programme for consultation

  310. Tyne South and Guinevere Installation Decommissioning Programmes published for consultation

  311. Addition of Curlew DPs, CA and EIA for Public Consultation.

  312. Decommissioning Programme Approved

  313. Updated Offshore decommissioning guidance has been added

  314. Ann & Alison, Saturn (Annabel) and Audrey DPs have been approved

  315. Changed document to final version

  316. A decommissioning programme has been approved

  317. Approved Markham DP

  318. Bains Documents Added

  319. Updated Environmental Guidance on Decommissioning

  320. Jacky DP Consultation

  321. Draft Consultation Decommissioning Programme uploaded

  322. Updated guidance for Offshore Decommissioning on website for feedback

  323. Addition of approved DPs

  324. Approved DPs added

  325. Saturn Annabel, Audrey and LDP1 Programmes for public consultation

  326. DPN form corrected

  327. generic email address added and DPN form updated (with generic email address)

  328. Ann and Alison DP's and associated documents added for public consultation

  329. Fairfield Fagus Limited's Dunlin Fuel Gas Import and Power Import, Merlin and Osprey Decommissioning Documents uploaded

  330. Brae Area DPs and associated documents available for consultation

  331. Harding STL Close Out Report added

  332. Disused Pipeline Notification Form revised - 03 May 17

  333. Leman BH Decommissioning Programme approved

  334. Approval of Ettrick and Blackbird DP

  335. Ninian North Platform documents published for public consultation A4 Programme approved

  336. Brent Decommissioning Programmes published for consultation

  337. IVRR Close Out Report added

  338. Ann A4 Installation Decommissioning Programme added for consultation

  339. Approved Decommissioning Programmes added

  340. Atlantic and Cromarty Draft Decommissioning Programmes Consultation

  341. references of DECC amended to BEIS (including DPN form)

  342. Janice, James & Affleck Fields - Draft programmes under consideration (added)

  343. Markham ST-1 Decommissioning Programmes - (added)

  344. Oil & Gas: Update Notification of Disused Pipelines

  345. Oil & Gas: Update Table of draft decommissioning programmes under consideration.

  346. Leadon Decommissioning Programmes - (added)

  347. Notification of Disused Pipelines form - (updated)

  348. Harding STL approved decommissioning programme - (added)

  349. Thames Area - Horne & Wren, Orwell and Wissey approved decommissioning programmes - (added)

  350. Fife, Flora, Fergus, Angus: decommissioning programme FFFA Close Out Report - (added)

  351. Thames Area – Thames Complex, Gawain & Arthur - Approved decommissioning programmes - (added)

  352. Viking Satellites CD,DD,ED,GD,HD draft decommissioning programmes under consideration - (added)

  353. Oil and Gas: Updated document for Harding STL Decommissioning Programme

  354. Oil and Gas: Updated “Table of approved decommissioning programmes” table.

  355. Leman BH draft decommissioning programme - (added)

  356. Oil and Gas: Addition of Brent field to approved decommissioning programme

  357. Oil and gas: Rose approved decommissioning programme - (added)

  358. Decommissioning - Leadon draft programme, follow up consultation - (added)

  359. Oil and gas: Stamford decommissioning programme - (added)

  360. Oil and gas: Rose Field decommissioning programmes - (added)

  361. Oil and gas: Brent – Brent Delta Topside draft decommissioning programme - (added)

  362. Oil and Gas: Addition of Stamford Field to decommissioning programmes table

  363. Oil and Gas: Updated the disused pipeline notification form

  364. Oil and gas: Decommissioning - Streamlined Decommissioning Programme Template (Derogation Cases) - (added)

  365. Oil and gas: NW Hutton close out report - (added)

  366. Oil and gas: Decommissioning draft prgrams - Thames - (added)

  367. Oil and gas: Indefatigable (Shell) close out report - (added)

  368. Oil and gas: Streamlined Decommissioning Programme Template (Non-Derogation Cases) - (updated)

  369. Oil and gas: Murchison approved decommissioning programme - (added)

  370. Oil and gas: Rubie & Renee - Approved decommissioning programme - (added)

  371. Oil and gas: Decommisiioning Linhe close out report - (added)

  372. Oil and gas: Streamlined Decommissioning Programme Template (Non Derogation Cases) - updated

  373. Oil and gas: Leadon Draft Decommissioning Programme - added

  374. Oil and gas: Miller decommissioning programme - (added)

  375. Oil and gas: Rubie/Renee Draft Decommissioning Programme - (added)

  376. Camelot close out report - added

  377. Added Murchison draft decommissioning programme

  378. Added streamlined decommissioning programme template

  379. Re-created table, added H2's and anchors

  380. First published.

Sign up for emails or print this page

Update history

2026-06-02 13:42
Approval of DP

2026-05-22 07:59
New DP out to Consultation

2026-05-21 07:09
Approval of Decommissioning Programme

2026-05-15 08:22
New DPs out for Consultation and a Close Out Report added

2026-05-14 08:04
New DP out for Consultation

2026-05-08 07:52
A new DP out for consultation

2026-04-22 09:40
DP approval

2026-04-13 16:38
Published the government response to the consultation on OPRED’s decommissioning charging regulations and hourly rates consultations.

2026-04-09 12:01
Revision approved

2026-04-08 09:23
DP Revision Approved

2026-03-26 14:37
Revision to an Approved DP

2026-03-20 10:07
New approved DP added

2026-03-18 15:58
Pipeline FIR form added

2026-03-10 09:56
DP for consultation

2026-03-06 11:17
A DP has been approved

2026-02-26 15:46
DP has been approved

2026-02-20 07:52
New DP out to consultation

2026-02-18 12:00
DP approval

2026-02-17 11:02
Consultation – Proposed changes to the rates of fees in respect of environmental functions and decommissioning functions

2026-02-06 11:47
New approved DP

2026-02-04 15:48
New approved Close Out Report

2026-01-30 07:45
New DP added to website

2026-01-28 13:23
Revision to approved DP

2026-01-27 12:06
Consultation draft DP added

2026-01-19 15:14
New approved DP added

2026-01-06 11:52
New DP Approval

2025-12-19 11:18
Approval of Decommissioning Programme

2025-12-16 12:25
Added Consultation on OPRED Decommissioning Charging Regulations 2026

2025-12-10 12:50
New approved DP

2025-11-21 13:26
A new DP has been added to the website

2025-11-20 10:14
Consultation draft added

2025-11-13 07:35
Close Out Report added

2025-11-10 08:19
New draft DP added to website

2025-10-30 09:05
New DP Approval

2025-10-23 09:58
A new DP has been added to the website

2025-10-23 07:56
Acceptance of Close Out Report

2025-10-08 13:35
New approved DP

2025-10-03 08:36
A new DP is out for Consultation

2025-09-26 08:31
DP approval

2025-09-24 15:17
DP Approval

2025-09-18 11:40
A DP has been approved

2025-09-04 07:51
A DP has gone out to public consultation

2025-09-03 13:18
DP has been approved

2025-09-02 15:11
Approval of Decommissioning Programme

2025-09-02 13:13
Approval of Decommissioning Programme

2025-08-18 16:20
DP has been approved

2025-08-14 14:34
Revision to approved DP

2025-08-14 08:01
A DP added for Consultation

2025-07-30 16:17
New approved DP

2025-07-25 06:58
A new DP out to consultation and a DP approved

2025-07-21 10:38
Addition of new approved DP

2025-07-18 08:29
New DP out to Consultation

2025-07-10 08:44
Acceptance of Close out Report

2025-07-02 15:49
Close Out Report added to the website

2025-07-01 09:24
New draft DP under consideration

2025-06-30 07:36
DPs have been approved

2025-06-16 10:07
Addition of Decommissioning Programme under consideration.

2025-06-06 15:29
Revision to Approved Programme

2025-06-02 18:05
A DP has been approved

2025-05-21 09:55
Decommissioning Programme Approved

2025-05-16 13:18
A DP has been approved

2025-05-15 07:51
A revision to a DP date has been added

2025-05-14 10:02
Approval of DP

2025-05-07 08:36
Acceptance of Close out Report

2025-05-07 07:37
DP has been approved

2025-05-01 08:02
Addition of new DP

2025-04-23 13:01
Revisions to approved Decommissioning Programmes

2025-04-14 14:44
Draft DP approved

2025-04-11 15:00
New approved Decommissioning Programme

2025-04-11 10:07
Decommissioning Programmes for consultation

2025-04-04 12:53
Three new DPs have been added to the OPRED website.

2025-03-18 13:38
A DP Revision approval and Updated non-derogation DP Template

2025-03-11 13:52
draft decommissioning programme removed

2025-03-11 11:27
Addition of new draft programmes under consideration and approved decommissioning programme

2025-02-26 14:54
Revision details added

2025-02-21 10:22
A new DP is out to consultation.

2025-01-15 14:12
New draft Decommissioning Programme added

2025-01-10 12:04
New DPs under consideration added

2025-01-07 10:20
Addition of new approved DP

2024-12-19 15:03
Revision details and approval date added

2024-12-16 10:40
Revision details added

2024-12-12 11:41
Addition of new draft decommissioning programme

2024-12-09 16:47
Document names updated for Knarr Gas Pipeline (KGP) and Brent PLU6294

2024-12-06 09:35
Addition of two draft Decommissioning Programmes and Environmental Appraisals.

2024-11-22 10:57
Addition of new DP and associated documents

2024-11-12 07:52
New Decommissioning Programmes added to ODU website

2024-10-23 16:08
Addition of Approved Decommissioning Programme

2024-10-17 08:30
Consultation draft DPs added

2024-10-09 15:32
New Non-Derogation Template added to website

2024-10-03 11:49
Revision details added

2024-09-30 08:32
Revision to approved DP

2024-09-26 16:25
DP has been approved

2024-09-20 08:51
Approved Close Out Report added

2024-09-06 08:35
Consultation Draft DP added

2024-08-30 11:24
New DP added to website

2024-08-23 11:28
DP out for consultation

2024-08-01 15:55
Additional information added for LBA DP

2024-08-01 14:42
Approved Close Out Report added

2024-07-25 08:07
East Brae UJ DP approved

2024-07-22 14:38
Acceptance of Close out Report

2024-07-22 11:20
New Decommissioning Programme added to website for consultation

2024-07-19 09:39
Solan DP consultation

2024-07-08 11:56
A new DP is out for consultation

2024-07-05 09:31
Consultation DP added

2024-07-01 13:45
Addition of DP revisions to website

2024-05-23 16:02
Approved Close Out Report added

2024-05-22 10:42
Approved Decommissioning Programme

2024-05-20 14:45
Approved DP added

2024-04-29 13:33
New Decommissioning Programme added to website

2024-04-26 10:22
A DP has been approved

2024-04-16 16:22
Change of Operator has occurred in the Wenlock and Garrow Fields

2024-04-04 10:14
Consultation DP added

2024-03-11 13:46
Close Out Report added to Website

2024-03-11 08:51
Approved DP added

2024-02-14 11:03
Decommissioning Programme for consultation

2024-01-26 10:26
The Brae Bravo Topsides Close Out Report has been accepted and added to the website.

2024-01-17 08:39
Acceptance of Close Out Report

2024-01-11 13:56
Approved Decommissioning Programme

2024-01-05 14:19
Helvellyn – Waldorf has been moved from “under consideration” to “approved”.

2023-12-14 11:48
Garrow documents added for Public Consultation.

2023-11-29 16:20
Final draft of Financial Assurance Guidance published

2023-10-30 10:33
Decommissioning Programme approved

2023-10-04 12:20
Decommissioning Programme approved

2023-09-29 12:04
Approved Decommissioning Programme

2023-08-17 08:01
Decommissioning Programme for consultation

2023-08-14 15:55
New DP out to consultation.

2023-08-11 10:33
ODU email address updated

2023-07-12 10:57
Decommissioning Programme out to consultation

2023-06-30 10:32
Consultation DP added

2023-06-29 11:47
Typo corrected on IPR 1

2023-06-28 13:29
Addition of new IPR forms for use

2023-06-27 12:47
Consultation DP added

2023-06-20 09:50
Consultation DP added

2023-06-08 12:22
DP approval

2023-05-26 08:21
Decommissioning Programme for consultation

2023-05-12 07:42
Decommissioning Programme for consultation

2023-04-28 08:04
East Brae UJ DP consultation commenced

2023-04-21 08:46
Consultation decommissioning programmes added

2023-03-28 13:44
DP approval

2023-03-03 08:04
Addition of Western Isles FPSO DP in programme under consideration tab

2023-02-10 09:40
Close Out Report added

2023-02-08 09:39
link to guidance update page

2023-02-07 11:32
Consultation DP added

2023-01-20 11:39
DPs withdrawn as added in error

2023-01-20 09:47
Consultation DPs added

2023-01-09 16:17
DP approval

2022-12-14 07:37
DP approval

2022-12-09 11:40
DP approved

2022-11-16 12:02
DPs have now been approved

2022-11-14 11:08
lancaster FPSO DP approved

2022-11-07 11:42
DP approval

2022-10-28 07:53
Consultation draft DP added

2022-10-07 09:14
Consultation draft DPs added

2022-09-30 08:38
Decommissioning Programme for consultation

2022-09-28 09:31
N11 COR added

2022-09-21 12:50
Notification of an approved DP

2022-08-18 09:44
DP approval

2022-07-05 07:21
Approved DPs published

2022-06-07 12:01
Brae B upper jacket DP approved

2022-05-09 12:26
Approved DP

2022-05-06 09:34
approval of foinaven FPSO DP

2022-04-29 13:06
response to consultation document for proposed changes to fee charging regime in respect of offshore oil and gas installations and pipelines published

2022-04-21 11:59
DP Approval

2022-04-21 10:28
Consultation DPs added

2022-04-21 08:51
Decommissioning programme for consultation

2022-04-20 16:40
Approval of Decommissioning Programme

2022-03-07 13:38
New DPs out to consultation

2022-03-03 10:02
wenlock DP approval re-added appears to have been deleted in error

2022-02-25 09:49
Consultation DP

2022-02-23 15:25
Approved DP

2022-02-22 14:31
Approved DP