Guidance

The 2020 EIA Regulations

The 2020 EIA Regulations

From 1st January 2021

Environmental Impact Assessments (EIA)

Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.

Environmental Impact Assessments (EIA) - Transitional Cases

For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA’s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.

Screening Directions

Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.

Deep Drilling Screening Directions

Pipeline Screening Directions

Production Screening Directions

Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction

Schedule 3 Projects

The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:

  • The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.

A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:

Published 5 January 2021
Last updated 2028 June 2023 + show all updates
  1. Schedule 3 Projects Register w.c. 26.06.2023 - updated

  2. Schedule 3 spreadsheet updated

  3. Schedule 3 Projects Register updated to most recent version

  4. Schedule 3 Project Register updated to most recent version

  5. Schedule 3 Projects Register - 29.05.2023 - UPDATE

  6. Current Schedule 3 Spreadsheet

  7. Schedule 3 Projects Register updated to most recent version

  8. Updated Schedule 3

  9. Schedule 3 Project Register updated to latest version

  10. add 2023 Pipeline Screening Directions link

  11. Schedule 3 projects register update

  12. Schedule 3 Projects Register updated

  13. Link added to Deep Drilling Screening Directions - 2023

  14. Schedule 3 Projects Register updated to most recent version

  15. Schedule 3 spreadsheet updated

  16. Schedule 3 Project Register updated.

  17. Most recent Schedule 3 projects register uploaded

  18. Schedule 3 register updated

  19. Updated Schedule 3 Projects Register added

  20. Updated Schedule 3 spreadsheet

  21. Schedule 3 Projects Register Updated

  22. Update to schedule 3 projects register

  23. Updated Schedule 3 Projects Register as at 22.08.2022

  24. Schedule 3 uploaded

  25. Schedule 3 Projects Register updated

  26. Schedule 3 register updated

  27. Schedule 3 Projects Register w.c. 18.07.2022 - Update

  28. Schedule 3 projects register updated

  29. Schedule 3 updated

  30. Schedule 3 updated

  31. Schedule 3 spreadsheet updated

  32. Schedule 3 register updated

  33. Schedule 3 updated

  34. Schedule 3 Projects Register updated to most recent version

  35. A link to 2022 Environmental Statements added.

  36. Schedule 3 updated

  37. Schedule 3 updated

  38. Schedule 3 register updated

  39. Schedule 3 replaced with the newest version

  40. Schedule 3 Register updated

  41. Schedule 3 Register updated

  42. Schedule 3 project register updated

  43. Update to Schedule 3 Projects Register

  44. Updated schedule 3 spreadsheet

  45. Addition of Pipeline Screening Directions - 2022

  46. Schedule 3 register updated

  47. Addition of link to Production Screening Direction 2022 page

  48. Weekly Schedule 3 Projects Register update

  49. Weekly Schedule 3 Projects Register Spreadsheet Update

  50. Weekly Update to Schedule 3 Projects Register

  51. Addition of Deep Drilling Screening Directions page for 2022

  52. Schedule 3 Project Tracker updated

  53. Schedule 3 tracking sheet updated.

  54. Schedule 3 tracking spreadsheet updated

  55. Schedule 3 register updated

  56. Schedule 3 tracker updated.

  57. Schedule 3 Projects Register updated.

  58. Weekly Schedule 3 Projects Register Spreadsheet

  59. Updated Schedule 3 register

  60. Schedule 3 tracking register updated.

  61. New schedule 3 register uploaded

  62. Schedule 3 Projects Register updated.

  63. Updated Schedule 3 register

  64. Updated Schedule 3 Projects Register,

  65. Schedule 3 Register updated

  66. updated schedule 3 register

  67. Weekly Schedule 3 Projects Register udpate

  68. Updated schedule 3 register

  69. Updated Schedule 3 Register

  70. Schedule 3 Projects Register weekly update

  71. Weekly Schedule 3 Projects Register update

  72. Schedule 3 projects register updated.

  73. Schedule 3 register updated

  74. Updated Schedule 3 Register

  75. Schedule 3 tracking spreadsheet updated.

  76. Updated Schedule 3 Register

  77. Schedule 3 tracker updated.

  78. Schedule 3 tracker updated.

  79. Schedule 3 register updated.

  80. Weekly 'Schedule 3 Projects Register' update

  81. Schedule 3 Register updated

  82. Schedule 3 tracking sheet updated.

  83. Schedule 3 Projects Register updated.

  84. Weekly Update to Schedule 3 Projects Register Spreadsheet

  85. Schedule 3 tracking updated.

  86. Schedule 3 tracking spreadsheet updated.

  87. Schedule 3 tracking spreadsheet updated.

  88. Update to Schedule 3 Projects Register

  89. Schedule 3 Projects Register updated.

  90. Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section

  91. Weekly update to the Schedule 3 Projects spreadsheet

  92. Update of - Sched 3 spreadsheets - 25/01/2021

  93. 'Schedule 3 Projects Register' spreadsheet weekly update

  94. First published.