The 2020 EIA Regulations

The 2020 EIA Regulations

From 1st January 2021

Environmental Impact Assessments (EIA)

Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.

Environmental Impact Assessments (EIA) - Transitional Cases

For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA’s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.

Screening Directions

Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.

Deep Drilling Screening Directions

Pipeline Screening Directions

Production Screening Directions

Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction

Schedule 3 Projects

The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:

  • The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.

A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:

Published 5 January 2021
Last updated 1317 October 2023 + show all updates
  1. Schedule 3 Spreadsheet updated

  2. Schedule 3 Projects Register updated to most recent version

  3. Link added to EIA Submissions and Decisions - 2023 webpage

  4. Schedule 3 Projects Register updated to most recent version

  5. Schedule 3 Projects Register updated to most recent version

  6. Schedule 3 project register - updated

  7. Schedule 3 Projects register updated

  8. Schedule 3 Projects Register - file attachment UPDATED

  9. Schedule 3 Projects Register weekly update

  10. Schedule 3 Projects Register updated to most recent version

  11. Schedule 3 Projects register - weekly update

  12. Schedule 3 updated

  13. Schedule 3 spreadsheet updated

  14. Schedule 3 Projects register updated to most recent version

  15. Updated Schedule 3 Projects Register - 03/07/2023

  16. Schedule 3 Projects Register w.c. 26.06.2023 - updated

  17. Schedule 3 spreadsheet updated

  18. Schedule 3 Projects Register updated to most recent version

  19. Schedule 3 Project Register updated to most recent version

  20. Schedule 3 Projects Register - 29.05.2023 - UPDATE

  21. Current Schedule 3 Spreadsheet

  22. Schedule 3 Projects Register updated to most recent version

  23. Updated Schedule 3

  24. Schedule 3 Project Register updated to latest version

  25. add 2023 Pipeline Screening Directions link

  26. Schedule 3 projects register update

  27. Schedule 3 Projects Register updated

  28. Link added to Deep Drilling Screening Directions - 2023

  29. Schedule 3 Projects Register updated to most recent version

  30. Schedule 3 spreadsheet updated

  31. Schedule 3 Project Register updated.

  32. Most recent Schedule 3 projects register uploaded

  33. Schedule 3 register updated

  34. Updated Schedule 3 Projects Register added

  35. Updated Schedule 3 spreadsheet

  36. Schedule 3 Projects Register Updated

  37. Update to schedule 3 projects register

  38. Updated Schedule 3 Projects Register as at 22.08.2022

  39. Schedule 3 uploaded

  40. Schedule 3 Projects Register updated

  41. Schedule 3 register updated

  42. Schedule 3 Projects Register w.c. 18.07.2022 - Update

  43. Schedule 3 projects register updated

  44. Schedule 3 updated

  45. Schedule 3 updated

  46. Schedule 3 spreadsheet updated

  47. Schedule 3 register updated

  48. Schedule 3 updated

  49. Schedule 3 Projects Register updated to most recent version

  50. A link to 2022 Environmental Statements added.

  51. Schedule 3 updated

  52. Schedule 3 updated

  53. Schedule 3 register updated

  54. Schedule 3 replaced with the newest version

  55. Schedule 3 Register updated

  56. Schedule 3 Register updated

  57. Schedule 3 project register updated

  58. Update to Schedule 3 Projects Register

  59. Updated schedule 3 spreadsheet

  60. Addition of Pipeline Screening Directions - 2022

  61. Schedule 3 register updated

  62. Addition of link to Production Screening Direction 2022 page

  63. Weekly Schedule 3 Projects Register update

  64. Weekly Schedule 3 Projects Register Spreadsheet Update

  65. Weekly Update to Schedule 3 Projects Register

  66. Addition of Deep Drilling Screening Directions page for 2022

  67. Schedule 3 Project Tracker updated

  68. Schedule 3 tracking sheet updated.

  69. Schedule 3 tracking spreadsheet updated

  70. Schedule 3 register updated

  71. Schedule 3 tracker updated.

  72. Schedule 3 Projects Register updated.

  73. Weekly Schedule 3 Projects Register Spreadsheet

  74. Updated Schedule 3 register

  75. Schedule 3 tracking register updated.

  76. New schedule 3 register uploaded

  77. Schedule 3 Projects Register updated.

  78. Updated Schedule 3 register

  79. Updated Schedule 3 Projects Register,

  80. Schedule 3 Register updated

  81. updated schedule 3 register

  82. Weekly Schedule 3 Projects Register udpate

  83. Updated schedule 3 register

  84. Updated Schedule 3 Register

  85. Schedule 3 Projects Register weekly update

  86. Weekly Schedule 3 Projects Register update

  87. Schedule 3 projects register updated.

  88. Schedule 3 register updated

  89. Updated Schedule 3 Register

  90. Schedule 3 tracking spreadsheet updated.

  91. Updated Schedule 3 Register

  92. Schedule 3 tracker updated.

  93. Schedule 3 tracker updated.

  94. Schedule 3 register updated.

  95. Weekly 'Schedule 3 Projects Register' update

  96. Schedule 3 Register updated

  97. Schedule 3 tracking sheet updated.

  98. Schedule 3 Projects Register updated.

  99. Weekly Update to Schedule 3 Projects Register Spreadsheet

  100. Schedule 3 tracking updated.

  101. Schedule 3 tracking spreadsheet updated.

  102. Schedule 3 tracking spreadsheet updated.

  103. Update to Schedule 3 Projects Register

  104. Schedule 3 Projects Register updated.

  105. Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section

  106. Weekly update to the Schedule 3 Projects spreadsheet

  107. Update of - Sched 3 spreadsheets - 25/01/2021

  108. 'Schedule 3 Projects Register' spreadsheet weekly update