The 2020 EIA Regulations
The 2020 EIA Regulations
From 1st January 2021
Environmental Impact Assessments (EIA)
Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.
Environmental Impact Assessments (EIA) - Transitional Cases
For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA’s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.
Screening Directions
Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.
Deep Drilling Screening Directions
Pipeline Screening Directions
Production Screening Directions
Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction
Schedule 3 Projects
The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:
- The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.
A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:
Updates to this page
Published 5 January 2021Last updated
-
10 March 2025 Schedule 3 Projects Register- uploaded
-
3 March 2025 2025 Production Screening Directions and 2025 Pipeline Screening Directions added
-
3 March 2025 Schedule 3 Projects Register - uploaded
-
24 February 2025 Schedule 3 Projects Register updated.
-
17 February 2025 Schedule 3 Projects Register updated
-
11 February 2025 Schedule 3 register updated
-
3 February 2025 Uploaded Schedule 3 Projects Register w.c. 03.02.2025
-
27 January 2025 Schedule 3 Register updated.
-
20 January 2025 Schedule 3 Projects Register updated
-
13 January 2025 Deep Drilling Screening Directions 2025 Environmental Impact Assessments (EIA) 2025
-
13 January 2025 Schedule 3 Projects Register - updated
-
6 January 2025 Schedule 3 Projects Register updated
-
16 December 2024 Updated SNS Activity Tracker W/C 16/12/2024.
-
9 December 2024 Schedule 3 Projects Register - uploaded
-
3 December 2024 Schedule 3 Projects Register updated.
-
25 November 2024 Schedule 3 Projects Register - Uploaded
-
18 November 2024 Schedule 3 Projects Register- Uploaded
-
11 November 2024 Schedule 3 Projects Register- uploaded
-
5 November 2024 Schedule 3 Projects Register - file attachment updated
-
29 October 2024 Schedule 3 Projects Register updated
-
23 October 2024 Update Schedule 3
-
18 October 2024 Schedule 3 Spreadsheet updated.
-
7 October 2024 Schedule 3 Projects Register updated.
-
30 September 2024 Schedule 3 Projects Register updated
-
23 September 2024 Schedule 3 Projects Register updated
-
17 September 2024 Schedule 3 Projects Register updated
-
10 September 2024 Schedule 3 Projects register updated.
-
2 September 2024 Schedule 3 Projects Register updated
-
28 August 2024 Schedule 3 Projects Register updated
-
19 August 2024 Schedule 3 Tracker Update
-
12 August 2024 Schedule 3 Projects Register updated
-
29 July 2024 Schedule 3 Projects Register updated
-
23 July 2024 Schedule 3 Projects Register updated to most recent version
-
15 July 2024 Schedule 3 Projects Register updated
-
8 July 2024 Schedule 3 Projects Register updated
-
1 July 2024 Schedule 3 Projects Register updated
-
24 June 2024 Update Schedule 3 - 24.06.24
-
20 June 2024 Schedule 3 project register updated.
-
10 June 2024 Schedule 3 Projects Register Updated to most recent version
-
3 June 2024 Schedule 3 Projects Register updated
-
27 May 2024 Schedule 3 register updated
-
20 May 2024 Schedule 3 Projects Register updated
-
14 May 2024 Schedule 3 Projects Register updated
-
30 April 2024 Schedule 3 Projects Register updated to most recent version
-
22 April 2024 schedule 3 spreadsheet updated
-
18 April 2024 New link to 2024 Production Screening Directions added
-
16 April 2024 Schedule 3 update
-
9 April 2024 Schedule 3 Projects Register updated to most recent version
-
2 April 2024 Schedule 3 projects register updated.
-
26 March 2024 Update of Schedule 3 document
-
21 March 2024 schedule 3 project register updated to most recent version
-
12 March 2024 Schedule 3 Projects Register updated
-
4 March 2024 Schedule 3 Projects Register updated
-
27 February 2024 Schedule 3 Projects Register updated
-
20 February 2024 Schedule 3 Project Register updated
-
14 February 2024 Addition of link to 2024 PL screening directions
-
12 February 2024 Schedule 3 Projects Register updated
-
7 February 2024 Schedule 3 Projects Register updated to most recent version
-
30 January 2024 Schedule 3 - 29/01/2024
-
22 January 2024 2024 page added
-
22 January 2024 Schedule 3 register updated
-
15 January 2024 Schedule 3 updated
-
12 January 2024 Link to Deep Drilling Screening Directions - 2024 added
-
9 January 2024 Schedule 3 spreadsheet updated
-
3 January 2024 Schedule 3 register updated
-
18 December 2023 Schedule 3 Projects register updated to most recent version
-
11 December 2023 Schedule 3 - Updated
-
4 December 2023 Schedule 3 updated
-
27 November 2023 Schedule 3 Projects Register updated
-
23 November 2023 Updated Schedule 3 Projects Register Spreadsheet
-
13 November 2023 Schedule 3 Projects Register updated to most recent version
-
6 November 2023 Schedule 3 projects register updated
-
30 October 2023 Update Schedule 3
-
24 October 2023 Schedule 3 Projects Register updated
-
17 October 2023 Schedule 3 Spreadsheet updated
-
13 October 2023 Schedule 3 Projects Register updated to most recent version
-
5 October 2023 Link added to EIA Submissions and Decisions - 2023 webpage
-
3 October 2023 Schedule 3 Projects Register updated to most recent version
-
28 September 2023 Schedule 3 Projects Register updated to most recent version
-
19 September 2023 Schedule 3 project register - updated
-
12 September 2023 Schedule 3 Projects register updated
-
5 September 2023 Schedule 3 Projects Register - file attachment UPDATED
-
29 August 2023 Schedule 3 Projects Register weekly update
-
15 August 2023 Schedule 3 Projects Register updated to most recent version
-
9 August 2023 Schedule 3 Projects register - weekly update
-
2 August 2023 Schedule 3 updated
-
17 July 2023 Schedule 3 spreadsheet updated
-
10 July 2023 Schedule 3 Projects register updated to most recent version
-
6 July 2023 Updated Schedule 3 Projects Register - 03/07/2023
-
28 June 2023 Schedule 3 Projects Register w.c. 26.06.2023 - updated
-
20 June 2023 Schedule 3 spreadsheet updated
-
14 June 2023 Schedule 3 Projects Register updated to most recent version
-
5 June 2023 Schedule 3 Project Register updated to most recent version
-
30 May 2023 Schedule 3 Projects Register - 29.05.2023 - UPDATE
-
16 May 2023 Current Schedule 3 Spreadsheet
-
24 April 2023 Schedule 3 Projects Register updated to most recent version
-
5 April 2023 Updated Schedule 3
-
21 February 2023 Schedule 3 Project Register updated to latest version
-
10 February 2023 add 2023 Pipeline Screening Directions link
-
8 February 2023 Schedule 3 projects register update
-
25 January 2023 Schedule 3 Projects Register updated
-
5 January 2023 Link added to Deep Drilling Screening Directions - 2023
-
20 December 2022 Schedule 3 Projects Register updated to most recent version
-
13 December 2022 Schedule 3 spreadsheet updated
-
28 November 2022 Schedule 3 Project Register updated.
-
15 November 2022 Most recent Schedule 3 projects register uploaded
-
12 October 2022 Schedule 3 register updated
-
4 October 2022 Updated Schedule 3 Projects Register added
-
27 September 2022 Updated Schedule 3 spreadsheet
-
20 September 2022 Schedule 3 Projects Register Updated
-
30 August 2022 Update to schedule 3 projects register
-
23 August 2022 Updated Schedule 3 Projects Register as at 22.08.2022
-
15 August 2022 Schedule 3 uploaded
-
9 August 2022 Schedule 3 Projects Register updated
-
27 July 2022 Schedule 3 register updated
-
20 July 2022 Schedule 3 Projects Register w.c. 18.07.2022 - Update
-
11 July 2022 Schedule 3 projects register updated
-
28 June 2022 Schedule 3 updated
-
23 June 2022 Schedule 3 updated
-
14 June 2022 Schedule 3 spreadsheet updated
-
23 May 2022 Schedule 3 register updated
-
17 May 2022 Schedule 3 updated
-
3 May 2022 Schedule 3 Projects Register updated to most recent version
-
28 April 2022 A link to 2022 Environmental Statements added.
-
26 April 2022 Schedule 3 updated
-
19 April 2022 Schedule 3 updated
-
5 April 2022 Schedule 3 register updated
-
29 March 2022 Schedule 3 replaced with the newest version
-
21 March 2022 Schedule 3 Register updated
-
14 March 2022 Schedule 3 Register updated
-
8 March 2022 Schedule 3 project register updated
-
28 February 2022 Update to Schedule 3 Projects Register
-
23 February 2022 Updated schedule 3 spreadsheet
-
9 February 2022 Addition of Pipeline Screening Directions - 2022
-
7 February 2022 Schedule 3 register updated
-
4 February 2022 Addition of link to Production Screening Direction 2022 page
-
24 January 2022 Weekly Schedule 3 Projects Register update
-
17 January 2022 Weekly Schedule 3 Projects Register Spreadsheet Update
-
13 January 2022 Weekly Update to Schedule 3 Projects Register
-
7 January 2022 Addition of Deep Drilling Screening Directions page for 2022
-
14 December 2021 Schedule 3 Project Tracker updated
-
6 December 2021 Schedule 3 tracking sheet updated.
-
30 November 2021 Schedule 3 tracking spreadsheet updated
-
9 November 2021 Schedule 3 register updated
-
2 November 2021 Schedule 3 tracker updated.
-
27 October 2021 Schedule 3 Projects Register updated.
-
18 October 2021 Weekly Schedule 3 Projects Register Spreadsheet
-
12 October 2021 Updated Schedule 3 register
-
5 October 2021 Schedule 3 tracking register updated.
-
27 September 2021 New schedule 3 register uploaded
-
7 September 2021 Schedule 3 Projects Register updated.
-
31 August 2021 Updated Schedule 3 register
-
16 August 2021 Updated Schedule 3 Projects Register,
-
10 August 2021 Schedule 3 Register updated
-
2 August 2021 updated schedule 3 register
-
19 July 2021 Weekly Schedule 3 Projects Register udpate
-
12 July 2021 Updated schedule 3 register
-
5 July 2021 Updated Schedule 3 Register
-
28 June 2021 Schedule 3 Projects Register weekly update
-
23 June 2021 Weekly Schedule 3 Projects Register update
-
15 June 2021 Schedule 3 projects register updated.
-
7 June 2021 Schedule 3 register updated
-
1 June 2021 Updated Schedule 3 Register
-
28 May 2021 Schedule 3 tracking spreadsheet updated.
-
20 May 2021 Updated Schedule 3 Register
-
12 May 2021 Schedule 3 tracker updated.
-
11 May 2021 Schedule 3 tracker updated.
-
6 May 2021 Schedule 3 register updated.
-
4 May 2021 Weekly 'Schedule 3 Projects Register' update
-
23 April 2021 Schedule 3 Register updated
-
19 April 2021 Schedule 3 tracking sheet updated.
-
30 March 2021 Schedule 3 Projects Register updated.
-
23 March 2021 Weekly Update to Schedule 3 Projects Register Spreadsheet
-
15 March 2021 Schedule 3 tracking updated.
-
8 March 2021 Schedule 3 tracking spreadsheet updated.
-
4 March 2021 Schedule 3 tracking spreadsheet updated.
-
23 February 2021 Update to Schedule 3 Projects Register
-
19 February 2021 Schedule 3 Projects Register updated.
-
18 February 2021 Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section
-
11 February 2021 Weekly update to the Schedule 3 Projects spreadsheet
-
25 January 2021 Update of - Sched 3 spreadsheets - 25/01/2021
-
19 January 2021 'Schedule 3 Projects Register' spreadsheet weekly update
-
5 January 2021 First published.
Update history
2025-04-01 07:49
Schedule 3 Projects Register – uploaded
2025-03-24 16:44
Schedule 3 Projects Register updated
2025-03-17 13:03
Schedule 3 Spreadsheet updated.
2025-03-10 12:57
Schedule 3 Projects Register- uploaded
2025-03-03 15:48
2025 Production Screening Directions and 2025 Pipeline Screening Directions added
2025-03-03 14:27
Schedule 3 Projects Register – uploaded
2025-02-24 13:43
Schedule 3 Projects Register updated.
2025-02-17 13:41
Schedule 3 Projects Register updated
2025-02-11 13:58
Schedule 3 register updated
2025-02-03 11:09
Uploaded Schedule 3 Projects Register w.c. 03.02.2025
2025-01-27 15:08
Schedule 3 Register updated.
2025-01-20 15:19
Schedule 3 Projects Register updated
2025-01-13 13:57
Deep Drilling Screening Directions 2025Environmental Impact Assessments (EIA) 2025
2025-01-13 13:37
Schedule 3 Projects Register – updated
2025-01-06 09:25
Schedule 3 Projects Register updated
2024-12-16 10:52
Updated SNS Activity Tracker W/C 16/12/2024.
2024-12-09 14:01
Schedule 3 Projects Register – uploaded
2024-12-03 12:47
Schedule 3 Projects Register updated.
2024-11-25 14:10
Schedule 3 Projects Register – Uploaded
2024-11-18 14:27
Schedule 3 Projects Register- Uploaded
2024-11-11 12:09
Schedule 3 Projects Register- uploaded
2024-11-05 10:54
Schedule 3 Projects Register – file attachment updated
2024-10-29 09:33
Schedule 3 Projects Register updated
2024-10-23 10:50
Update Schedule 3
2024-10-18 12:54
Schedule 3 Spreadsheet updated.
2024-10-07 11:51
Schedule 3 Projects Register updated.
2024-09-30 15:08
Schedule 3 Projects Register updated
2024-09-23 09:54
Schedule 3 Projects Register updated
2024-09-17 10:29
Schedule 3 Projects Register updated
2024-09-10 13:31
Schedule 3 Projects register updated.
2024-09-02 13:25
Schedule 3 Projects Register updated
2024-08-28 10:15
Schedule 3 Projects Register updated
2024-08-19 14:54
Schedule 3 Tracker Update
2024-08-12 15:10
Schedule 3 Projects Register updated
2024-07-29 10:05
Schedule 3 Projects Register updated
2024-07-23 08:56
Schedule 3 Projects Register updated to most recent version
2024-07-15 11:12
Schedule 3 Projects Register updated
2024-07-08 11:27
Schedule 3 Projects Register updated
2024-07-01 10:41
Schedule 3 Projects Register updated
2024-06-24 10:50
Update Schedule 3 – 24.06.24
2024-06-20 10:19
Schedule 3 project register updated.
2024-06-10 16:17
Schedule 3 Projects Register Updated to most recent version
2024-06-03 09:35
Schedule 3 Projects Register updated
2024-05-27 11:27
Schedule 3 register updated
2024-05-20 11:52
Schedule 3 Projects Register updated
2024-05-14 13:21
Schedule 3 Projects Register updated
2024-04-30 14:22
Schedule 3 Projects Register updated to most recent version
2024-04-22 16:04
schedule 3 spreadsheet updated
2024-04-18 14:37
New link to 2024 Production Screening Directions added
2024-04-16 13:29
Schedule 3 update
2024-04-09 15:22
Schedule 3 Projects Register updated to most recent version
2024-04-02 13:33
Schedule 3 projects register updated.
2024-03-26 14:16
Update of Schedule 3 document
2024-03-21 10:11
schedule 3 project register updated to most recent version
2024-03-12 15:18
Schedule 3 Projects Register updated
2024-03-04 15:39
Schedule 3 Projects Register updated
2024-02-27 08:21
Schedule 3 Projects Register updated
2024-02-20 11:21
Schedule 3 Project Register updated
2024-02-14 15:35
Addition of link to 2024 PL screening directions
2024-02-12 15:50
Schedule 3 Projects Register updated
2024-02-07 09:20
Schedule 3 Projects Register updated to most recent version
2024-01-30 08:41
Schedule 3 – 29/01/2024
2024-01-22 13:54
2024 page added
2024-01-22 11:00
Schedule 3 register updated
2024-01-15 14:08
Schedule 3 updated
2024-01-12 13:35
Link to Deep Drilling Screening Directions – 2024 added
2024-01-09 09:37
Schedule 3 spreadsheet updated
2024-01-03 14:17
Schedule 3 register updated
2023-12-18 11:47
Schedule 3 Projects register updated to most recent version
2023-12-11 16:19
Schedule 3 – Updated
2023-12-04 14:17
Schedule 3 updated
2023-11-27 14:49
Schedule 3 Projects Register updated
2023-11-23 16:14
Updated Schedule 3 Projects Register Spreadsheet
2023-11-13 13:37
Schedule 3 Projects Register updated to most recent version
2023-11-06 14:49
Schedule 3 projects register updated
2023-10-30 16:35
Update Schedule 3
2023-10-24 15:38
Schedule 3 Projects Register updated
2023-10-17 11:37
Schedule 3 Spreadsheet updated
2023-10-13 10:59
Schedule 3 Projects Register updated to most recent version
2023-10-05 15:06
Link added to EIA Submissions and Decisions – 2023 webpage
2023-10-03 15:16
Schedule 3 Projects Register updated to most recent version
2023-09-05 13:18
Schedule 3 Projects Register – file attachment UPDATED
2023-08-29 16:55
Schedule 3 Projects Register weekly update
2023-08-15 16:05
Schedule 3 Projects Register updated to most recent version
2023-08-09 14:59
Schedule 3 Projects register – weekly update
2023-08-02 14:07
Schedule 3 updated
2023-07-17 11:32
Schedule 3 spreadsheet updated
2023-07-10 16:21
Schedule 3 Projects register updated to most recent version
2023-07-06 13:13
Updated Schedule 3 Projects Register – 03/07/2023
2023-06-28 10:36
Schedule 3 Projects Register w.c. 26.06.2023 – updated
2023-06-20 09:01
Schedule 3 spreadsheet updated
2023-06-14 09:43
Schedule 3 Projects Register updated to most recent version
2023-06-05 14:53
Schedule 3 Project Register updated to most recent version
2023-05-30 10:05
Schedule 3 Projects Register – 29.05.2023 – UPDATE
2023-05-16 10:12
Current Schedule 3 Spreadsheet
2023-04-24 13:57
Schedule 3 Projects Register updated to most recent version
2023-04-05 16:06
Updated Schedule 3
2023-02-21 16:45
Schedule 3 Project Register updated to latest version
2023-02-10 15:34
add 2023 Pipeline Screening Directions link
2023-02-08 14:28
Schedule 3 projects register update
2023-01-25 14:38
Schedule 3 Projects Register updated
2023-01-05 15:36
Link added to Deep Drilling Screening Directions – 2023
2022-12-20 10:26
Schedule 3 Projects Register updated to most recent version
2022-12-13 11:57
Schedule 3 spreadsheet updated
2022-11-28 10:44
Schedule 3 Project Register updated.
2022-11-15 13:39
Most recent Schedule 3 projects register uploaded
2022-10-12 08:45
Schedule 3 register updated
2022-10-04 12:14
Updated Schedule 3 Projects Register added
2022-09-27 10:20
Updated Schedule 3 spreadsheet
2022-09-20 13:43
Schedule 3 Projects Register Updated
2022-08-30 11:21
Update to schedule 3 projects register
2022-08-23 14:01
Updated Schedule 3 Projects Register as at 22.08.2022
2022-08-15 14:00
Schedule 3 uploaded
2022-08-09 09:37
Schedule 3 Projects Register updated
2022-07-27 09:27
Schedule 3 register updated
2022-07-20 12:46
Schedule 3 Projects Register w.c. 18.07.2022 – Update
2022-07-11 13:08
Schedule 3 projects register updated
2022-06-28 09:30
Schedule 3 updated
2022-06-23 13:14
Schedule 3 updated
2022-06-14 15:30
Schedule 3 spreadsheet updated
2022-05-23 13:26
Schedule 3 register updated
2022-05-17 14:51
Schedule 3 updated
2022-05-03 14:08
Schedule 3 Projects Register updated to most recent version
2022-04-28 16:34
A link to 2022 Environmental Statements added.
2022-04-26 15:50
Schedule 3 updated
2022-04-19 12:43
Schedule 3 updated
2022-04-05 12:38
Schedule 3 register updated
2022-03-29 15:16
Schedule 3 replaced with the newest version
2022-03-21 14:44
Schedule 3 Register updated
2022-03-14 15:44
Schedule 3 Register updated
2022-03-08 15:29
Schedule 3 project register updated
2022-02-28 15:07
Update to Schedule 3 Projects Register
2022-02-23 14:32
Updated schedule 3 spreadsheet