Guidance

The 2020 EIA Regulations

The 2020 EIA Regulations

From 1st January 2021

Environmental Impact Assessments (EIA)

Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.

Environmental Impact Assessments (EIA) - Transitional Cases

For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA’s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.

Screening Directions

Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.

Deep Drilling Screening Directions

Pipeline Screening Directions

Production Screening Directions

Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction

Schedule 3 Projects

The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:

  • The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.

A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:

Updates to this page

Published 5 January 2021
Last updated 1930 January 2026 + show all updates
  1. Addition of 2026 page to Pipeline Screening Directions

  2. Schedule 3 Projects Register updated

  3. Schedule 3 Projects Register updated

  4. Schedule 3 Projects Register Updated

  5. Addition of 2026

  6. Schedule 3 Projects Register updated

  7. Schedule 3 Projects Register updated

  8. Schedule 3 Projects Register - updated

  9. Schedule 3 Projects Register updated.

  10. Schedule 3 Projects Register updated.

  11. Schedule 3 updated.

  12. Schedule 3 Projects Register - Updated

  13. Schedule 3 updated.

  14. Schedule 3 Projects Register - file attachment updated

  15. Schedule 3 Projects Register updated.

  16. Schedule 3 Projects Register - Updated

  17. Schedule 3 Projects Register updated

  18. Schedule 3 Projects Register Updated

  19. Schedule 3 Projects Register - updated

  20. Schedule 3 Projects Register updated

  21. Schedule 3 Projects Register uploaded

  22. Schedule 3 Projects Register Update

  23. Schedule 3 updated

  24. Schedule 3 Projects Register updated.

  25. Schedule 3 Projects Register Updated

  26. Schedule 3 Projects Register updated.

  27. Schedule 3 Projects Register - Updated

  28. Schedule 3 Projects Register

  29. Schedule 3 spreadsheet updated.

  30. Schedule 3 Projects register updated.

  31. Schedule 3 project register - updated

  32. Schedule 3 register updated

  33. Schedule 3 Projects Register - Updated

  34. Schedule 3 Projects Register updated

  35. Updated Schedule 3 Projects Register.

  36. Schedule 3 spreadsheet updated.

  37. Schedule 3 Projects Register - Uploaded

  38. Schedule 3 Projects Register updated

  39. Schedule 3 Projects Register updated

  40. Schedule 3 Project Register uploaded.

  41. Schedule 3 Spreadsheet updated.

  42. Schedule 3 Projects Register updated

  43. Schedule 3 Projects Register - Uploaded

  44. Schedule 3 Projects Register - uploaded

  45. Schedule 3 Projects Register updated

  46. Schedule 3 Spreadsheet updated.

  47. Schedule 3 Projects Register- uploaded

  48. 2025 Production Screening Directions and 2025 Pipeline Screening Directions added

  49. Schedule 3 Projects Register - uploaded

  50. Schedule 3 Projects Register updated.

  51. Schedule 3 Projects Register updated

  52. Schedule 3 register updated

  53. Uploaded Schedule 3 Projects Register w.c. 03.02.2025

  54. Schedule 3 Register updated.

  55. Schedule 3 Projects Register updated

  56. Deep Drilling Screening Directions 2025 Environmental Impact Assessments (EIA) 2025

  57. Schedule 3 Projects Register - updated

  58. Schedule 3 Projects Register updated

  59. Updated SNS Activity Tracker W/C 16/12/2024.

  60. Schedule 3 Projects Register - uploaded

  61. Schedule 3 Projects Register updated.

  62. Schedule 3 Projects Register - Uploaded

  63. Schedule 3 Projects Register- Uploaded

  64. Schedule 3 Projects Register- uploaded

  65. Schedule 3 Projects Register - file attachment updated

  66. Schedule 3 Projects Register updated

  67. Update Schedule 3

  68. Schedule 3 Spreadsheet updated.

  69. Schedule 3 Projects Register updated.

  70. Schedule 3 Projects Register updated

  71. Schedule 3 Projects Register updated

  72. Schedule 3 Projects Register updated

  73. Schedule 3 Projects register updated.

  74. Schedule 3 Projects Register updated

  75. Schedule 3 Projects Register updated

  76. Schedule 3 Tracker Update

  77. Schedule 3 Projects Register updated

  78. Schedule 3 Projects Register updated

  79. Schedule 3 Projects Register updated to most recent version

  80. Schedule 3 Projects Register updated

  81. Schedule 3 Projects Register updated

  82. Schedule 3 Projects Register updated

  83. Update Schedule 3 - 24.06.24

  84. Schedule 3 project register updated.

  85. Schedule 3 Projects Register Updated to most recent version

  86. Schedule 3 Projects Register updated

  87. Schedule 3 register updated

  88. Schedule 3 Projects Register updated

  89. Schedule 3 Projects Register updated

  90. Schedule 3 Projects Register updated to most recent version

  91. schedule 3 spreadsheet updated

  92. New link to 2024 Production Screening Directions added

  93. Schedule 3 update

  94. Schedule 3 Projects Register updated to most recent version

  95. Schedule 3 projects register updated.

  96. Update of Schedule 3 document

  97. schedule 3 project register updated to most recent version

  98. Schedule 3 Projects Register updated

  99. Schedule 3 Projects Register updated

  100. Schedule 3 Projects Register updated

  101. Schedule 3 Project Register updated

  102. Addition of link to 2024 PL screening directions

  103. Schedule 3 Projects Register updated

  104. Schedule 3 Projects Register updated to most recent version

  105. Schedule 3 - 29/01/2024

  106. 2024 page added

  107. Schedule 3 register updated

  108. Schedule 3 updated

  109. Link to Deep Drilling Screening Directions - 2024 added

  110. Schedule 3 spreadsheet updated

  111. Schedule 3 register updated

  112. Schedule 3 Projects register updated to most recent version

  113. Schedule 3 - Updated

  114. Schedule 3 updated

  115. Schedule 3 Projects Register updated

  116. Updated Schedule 3 Projects Register Spreadsheet

  117. Schedule 3 Projects Register updated to most recent version

  118. Schedule 3 projects register updated

  119. Update Schedule 3

  120. Schedule 3 Projects Register updated

  121. Schedule 3 Spreadsheet updated

  122. Schedule 3 Projects Register updated to most recent version

  123. Link added to EIA Submissions and Decisions - 2023 webpage

  124. Schedule 3 Projects Register updated to most recent version

  125. Schedule 3 Projects Register updated to most recent version

  126. Schedule 3 project register - updated

  127. Schedule 3 Projects register updated

  128. Schedule 3 Projects Register - file attachment UPDATED

  129. Schedule 3 Projects Register weekly update

  130. Schedule 3 Projects Register updated to most recent version

  131. Schedule 3 Projects register - weekly update

  132. Schedule 3 updated

  133. Schedule 3 spreadsheet updated

  134. Schedule 3 Projects register updated to most recent version

  135. Updated Schedule 3 Projects Register - 03/07/2023

  136. Schedule 3 Projects Register w.c. 26.06.2023 - updated

  137. Schedule 3 spreadsheet updated

  138. Schedule 3 Projects Register updated to most recent version

  139. Schedule 3 Project Register updated to most recent version

  140. Schedule 3 Projects Register - 29.05.2023 - UPDATE

  141. Current Schedule 3 Spreadsheet

  142. Schedule 3 Projects Register updated to most recent version

  143. Updated Schedule 3

  144. Schedule 3 Project Register updated to latest version

  145. add 2023 Pipeline Screening Directions link

  146. Schedule 3 projects register update

  147. Schedule 3 Projects Register updated

  148. Link added to Deep Drilling Screening Directions - 2023

  149. Schedule 3 Projects Register updated to most recent version

  150. Schedule 3 spreadsheet updated

  151. Schedule 3 Project Register updated.

  152. Most recent Schedule 3 projects register uploaded

  153. Schedule 3 register updated

  154. Updated Schedule 3 Projects Register added

  155. Updated Schedule 3 spreadsheet

  156. Schedule 3 Projects Register Updated

  157. Update to schedule 3 projects register

  158. Updated Schedule 3 Projects Register as at 22.08.2022

  159. Schedule 3 uploaded

  160. Schedule 3 Projects Register updated

  161. Schedule 3 register updated

  162. Schedule 3 Projects Register w.c. 18.07.2022 - Update

  163. Schedule 3 projects register updated

  164. Schedule 3 updated

  165. Schedule 3 updated

  166. Schedule 3 spreadsheet updated

  167. Schedule 3 register updated

  168. Schedule 3 updated

  169. Schedule 3 Projects Register updated to most recent version

  170. A link to 2022 Environmental Statements added.

  171. Schedule 3 updated

  172. Schedule 3 updated

  173. Schedule 3 register updated

  174. Schedule 3 replaced with the newest version

  175. Schedule 3 Register updated

  176. Schedule 3 Register updated

  177. Schedule 3 project register updated

  178. Update to Schedule 3 Projects Register

  179. Updated schedule 3 spreadsheet

  180. Addition of Pipeline Screening Directions - 2022

  181. Schedule 3 register updated

  182. Addition of link to Production Screening Direction 2022 page

  183. Weekly Schedule 3 Projects Register update

  184. Weekly Schedule 3 Projects Register Spreadsheet Update

  185. Weekly Update to Schedule 3 Projects Register

  186. Addition of Deep Drilling Screening Directions page for 2022

  187. Schedule 3 Project Tracker updated

  188. Schedule 3 tracking sheet updated.

  189. Schedule 3 tracking spreadsheet updated

  190. Schedule 3 register updated

  191. Schedule 3 tracker updated.

  192. Schedule 3 Projects Register updated.

  193. Weekly Schedule 3 Projects Register Spreadsheet

  194. Updated Schedule 3 register

  195. Schedule 3 tracking register updated.

  196. New schedule 3 register uploaded

  197. Schedule 3 Projects Register updated.

  198. Updated Schedule 3 register

  199. Updated Schedule 3 Projects Register,

  200. Schedule 3 Register updated

  201. updated schedule 3 register

  202. Weekly Schedule 3 Projects Register udpate

  203. Updated schedule 3 register

  204. Updated Schedule 3 Register

  205. Schedule 3 Projects Register weekly update

  206. Weekly Schedule 3 Projects Register update

  207. Schedule 3 projects register updated.

  208. Schedule 3 register updated

  209. Updated Schedule 3 Register

  210. Schedule 3 tracking spreadsheet updated.

  211. Updated Schedule 3 Register

  212. Schedule 3 tracker updated.

  213. Schedule 3 tracker updated.

  214. Schedule 3 register updated.

  215. Weekly 'Schedule 3 Projects Register' update

  216. Schedule 3 Register updated

  217. Schedule 3 tracking sheet updated.

  218. Schedule 3 Projects Register updated.

  219. Weekly Update to Schedule 3 Projects Register Spreadsheet

  220. Schedule 3 tracking updated.

  221. Schedule 3 tracking spreadsheet updated.

  222. Schedule 3 tracking spreadsheet updated.

  223. Update to Schedule 3 Projects Register

  224. Schedule 3 Projects Register updated.

  225. Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section

  226. Weekly update to the Schedule 3 Projects spreadsheet

  227. Update of - Sched 3 spreadsheets - 25/01/2021

  228. 'Schedule 3 Projects Register' spreadsheet weekly update

  229. First published.