Guidance

The 2020 EIA Regulations

The 2020 EIA Regulations

From 1st January 2021

Environmental Impact Assessments (EIA)

Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.

Environmental Impact Assessments (EIA) - Transitional Cases

For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA’s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.

Screening Directions

Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.

Deep Drilling Screening Directions

Pipeline Screening Directions

Production Screening Directions

Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction

Schedule 3 Projects

The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:

  • The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.

A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:

Published 5 January 2021
Last updated 1529 August 2023 + show all updates
  1. Schedule 3 Projects Register weekly update

  2. Schedule 3 Projects Register updated to most recent version

  3. Schedule 3 Projects register - weekly update

  4. Schedule 3 updated

  5. Schedule 3 spreadsheet updated

  6. Schedule 3 Projects register updated to most recent version

  7. Updated Schedule 3 Projects Register - 03/07/2023

  8. Schedule 3 Projects Register w.c. 26.06.2023 - updated

  9. Schedule 3 spreadsheet updated

  10. Schedule 3 Projects Register updated to most recent version

  11. Schedule 3 Project Register updated to most recent version

  12. Schedule 3 Projects Register - 29.05.2023 - UPDATE

  13. Current Schedule 3 Spreadsheet

  14. Schedule 3 Projects Register updated to most recent version

  15. Updated Schedule 3

  16. Schedule 3 Project Register updated to latest version

  17. add 2023 Pipeline Screening Directions link

  18. Schedule 3 projects register update

  19. Schedule 3 Projects Register updated

  20. Link added to Deep Drilling Screening Directions - 2023

  21. Schedule 3 Projects Register updated to most recent version

  22. Schedule 3 spreadsheet updated

  23. Schedule 3 Project Register updated.

  24. Most recent Schedule 3 projects register uploaded

  25. Schedule 3 register updated

  26. Updated Schedule 3 Projects Register added

  27. Updated Schedule 3 spreadsheet

  28. Schedule 3 Projects Register Updated

  29. Update to schedule 3 projects register

  30. Updated Schedule 3 Projects Register as at 22.08.2022

  31. Schedule 3 uploaded

  32. Schedule 3 Projects Register updated

  33. Schedule 3 register updated

  34. Schedule 3 Projects Register w.c. 18.07.2022 - Update

  35. Schedule 3 projects register updated

  36. Schedule 3 updated

  37. Schedule 3 updated

  38. Schedule 3 spreadsheet updated

  39. Schedule 3 register updated

  40. Schedule 3 updated

  41. Schedule 3 Projects Register updated to most recent version

  42. A link to 2022 Environmental Statements added.

  43. Schedule 3 updated

  44. Schedule 3 updated

  45. Schedule 3 register updated

  46. Schedule 3 replaced with the newest version

  47. Schedule 3 Register updated

  48. Schedule 3 Register updated

  49. Schedule 3 project register updated

  50. Update to Schedule 3 Projects Register

  51. Updated schedule 3 spreadsheet

  52. Addition of Pipeline Screening Directions - 2022

  53. Schedule 3 register updated

  54. Addition of link to Production Screening Direction 2022 page

  55. Weekly Schedule 3 Projects Register update

  56. Weekly Schedule 3 Projects Register Spreadsheet Update

  57. Weekly Update to Schedule 3 Projects Register

  58. Addition of Deep Drilling Screening Directions page for 2022

  59. Schedule 3 Project Tracker updated

  60. Schedule 3 tracking sheet updated.

  61. Schedule 3 tracking spreadsheet updated

  62. Schedule 3 register updated

  63. Schedule 3 tracker updated.

  64. Schedule 3 Projects Register updated.

  65. Weekly Schedule 3 Projects Register Spreadsheet

  66. Updated Schedule 3 register

  67. Schedule 3 tracking register updated.

  68. New schedule 3 register uploaded

  69. Schedule 3 Projects Register updated.

  70. Updated Schedule 3 register

  71. Updated Schedule 3 Projects Register,

  72. Schedule 3 Register updated

  73. updated schedule 3 register

  74. Weekly Schedule 3 Projects Register udpate

  75. Updated schedule 3 register

  76. Updated Schedule 3 Register

  77. Schedule 3 Projects Register weekly update

  78. Weekly Schedule 3 Projects Register update

  79. Schedule 3 projects register updated.

  80. Schedule 3 register updated

  81. Updated Schedule 3 Register

  82. Schedule 3 tracking spreadsheet updated.

  83. Updated Schedule 3 Register

  84. Schedule 3 tracker updated.

  85. Schedule 3 tracker updated.

  86. Schedule 3 register updated.

  87. Weekly 'Schedule 3 Projects Register' update

  88. Schedule 3 Register updated

  89. Schedule 3 tracking sheet updated.

  90. Schedule 3 Projects Register updated.

  91. Weekly Update to Schedule 3 Projects Register Spreadsheet

  92. Schedule 3 tracking updated.

  93. Schedule 3 tracking spreadsheet updated.

  94. Schedule 3 tracking spreadsheet updated.

  95. Update to Schedule 3 Projects Register

  96. Schedule 3 Projects Register updated.

  97. Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section

  98. Weekly update to the Schedule 3 Projects spreadsheet

  99. Update of - Sched 3 spreadsheets - 25/01/2021

  100. 'Schedule 3 Projects Register' spreadsheet weekly update

  101. First published.